Blast Booth QA.pdf

PDF 51 KB Posted

Attached to
Blast Booth Removal Federal contract opportunity
Solicitation number
FA910124QB034
Issued by
Department of the Air Force Materiel Command Test Center

About this file

This document is a Question and Answer sheet related to the Blast Booth Removal solicitation (FA910124QB034) issued by the Department of the Air Force Materiel Command Test Center.

The key details are:

  • All utilities (air, electric, gas, water) will be disconnected prior to the contractor's arrival.
  • The blast room base is sitting on top of concrete, not embedded.
  • Contractors are allowed to use torches as long as proper fire watch protocols are followed.
  • The government requires a two-man crew for the approximately 4-day demolition project.
  • Work hours are 0600-1600 Monday through Thursday, and 0630-1600 every other Friday. Weekend work is allowed.
  • The dust collector is located outside the building, not next to a roll-up door.
  • The government plans to award the contract immediately after the due date.
  • No submittals are required prior to mobilization after award.
  • SDVOSB and HubZone certifications will not be considered, as the award must be made in accordance with the solicitation.
  • No performance bond is required.

View the file

Other files for this federal contract opportunity

Other files attached to Blast Booth Removal, newest first.
File Type Posted
Blast Booth QA.pdf PDF
Wage Determination 2015-5455.pdf PDF
Blast Booth QA.pdf PDF
FA9101-24-Q-B034 - Combined Synopsis Solicitation.docx DOCX document
Atch 1 Blast Booth Removal Specifications.pdf PDF
Atch 2 Provision and clauses..pdf PDF
Atch 3 Blast Booth Pictures.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question Answer

Are all utilities: air, electric, gas and water disconnected from unit or will they be prior to our arrival? YES

2 Is the blast room base embedded in the concrete or sitting on top of the concrete? Sitting on top of the concrete

If embedded, are we required to remove from the concrete and pour concrete back?

Or can we cut flush with concrete? N/A

Are we allowed to use torches in this location as long as proper fire watch protocols are followed? YES

What site personnel are we required to have and can we act in a dual role? We see this as a two-man demo for approx. 4 days with no need for increased cost due to added personnel roles.

What ever personnel you need to perform the operation.

6 What are the work hours and can we work over the weekend?

We are here from 0600 Monday thru Thursday and 0630 to 1600 every other Friday.

It appears that there is a roll-up door alongside the dust collector, what are the dimensions of this door, H’xW’? The dust collector is outside.

How quickly are you looking to award after due date? Immediately

How quickly will we be able to mobilize after award and what submittals will be required prior to mobilization?

No submittals required, and able to mobilize after notice of award

We have our SDVOSB & HubZone certifications, will these be considered for the contract?

No, we must award in accordance with the solicitation

11 Will a bond be required? No

FA9101-24-Q-B034 Blast Booth Removal Questions and Answers

Sheet1

File details come from the government source that posted it. Updated .