Attachment 1 - TEMPEST MAV SOO_ Revised.pdf
PDF 122 KB Posted
- Attached to
- 346 Mobile Assessment Vehicle (MAV) Federal contract opportunity
- Solicitation number
- FA877324Q0003
About this file
This document is a Statement of Objectives (SOO) for the purchase of two (2) commercial Mobile Assessment Vehicles (MAV) for the 346th Test Squadron. The key requirements include:
- Chassis and cab specifications, including a minimum 70-gallon fuel tank and diesel engine
- A walk-in vehicle body with insulation, air conditioning, and storage space
- Exterior LED lighting, cable pass-throughs, stabilizers, and a roof access ladder
- Interior features such as lighting, power outlets, workstations, equipment racks, and a 14kW diesel generator
- Technical requirements for compliance with Air Force instructions, the Trade Agreements Act, use of authorized resellers, and warranties. The related federal contract opportunity is Solicitation FA877324Q0003 for the 346 Mobile Assessment Vehicle (MAV), issued by the Department of the Air Force Space Command. The expected delivery timeframe is 180-240 days from award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation_Synopsis Revision.pdf | ||
| Attachment 1 MAV SOO_ Revision 4 Dec 24.pdf | ||
| Attachment 2 - Clauses and Provisions.pdf | ||
| Solicitation_Synopsis Signed.pdf | ||
| Attachment 1 - TEMPEST MAV SOO.pdf | ||
| Attachment 2 - Clauses and Provisions.pdf | ||
| Solicitation_Synopsis FA877324Q0003.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Objectives
Revised
1. SOO PRODUCTS PURCHASE
The 346th Test Squadron (TS) has a requirement to purchase two (2) Mobile Assessment Vehicles
(MAV) to be used for Radio Frequency (RF) testing.
2. SPECIAL ASSET TAGGING
The contractor shall provide special asset tags In Accordance With (IAW) MIL-STD-130N
Change 1, Department of Defense Instruction (DODI) 8320.04 and DFARS 252.211-7703, Item
Identification and Valuation. The current list of accepted unique item identifier types is maintained at https://www.acq.osd.mil/asda/dpc/ce/ds/unique-id.html.
All DoD recognized unique identification equivalents are listed at http://www.acq.osd.mil/dpap/pdi/uid/iuid_equivalents.html.
3. ENERGY STAR MANDATE
The Institute an ENERGY STAR Purchasing Policy | ENERGY STAR guidelines are not necessary/required for this purchase.
4. TEMPEST PROGRAM MANDATES
There are no items for this MAV that require TEMPEST certification.
5. SECTION 508 OF THE REHABILITATION ACT MANDATE
The Contractor shall meet the requirements of the U.S. Access Board’s regulations at 36 CFR
Part 1194 Information and communication technology Standards and Guidelines. which implements Section 508 of the Rehabilitation Act of 1973, as amended.
https://www.ecfr.gov/current/title-36/chapter-XI/part-1194 For more information about DoD
Section 508 specific responsibilities, see the DoD CIO website https://dodcio.defense.gov/DoDSection508.aspx.
6. SPECIFICATIONS
Description Specs/Standards Qty
Chassis and Cab *Minimum 70-gallon fuel tank
Total final weight should be less than 26k pounds
Engine should be diesel powered
*Vehicle must have permanent adjustable driver and passenger seats with 3-point seatbelts
*Vehicle must be comfortable and safe for long road trips, 400 miles or 8 hours per day, multiple days for cross country travel
*Cab must have air conditioning and heating.
Walk-in Vehicle Body 83" high x 96" wide x 20' long all aluminum with 1” wall/ceiling insulation, (2 ea.) Commercial Grade 15k btu air conditioner unit and heater component with wall mounted controls, and main entry door with grab handle with retractable stairs if necessary
Preferred Vehicle color is white
Belly Box Storage Installed on each side 2 https://www.acq.osd.mil/asda/dpc/ce/ds/unique-id.html http://www.acq.osd.mil/dpap/pdi/uid/iuid_equivalents.html https://www.energystar.gov/products/data_center_equipment/5-simple-ways-avoid-energy-waste-your-data-center/institute-energy#:~:text=An%20ENERGY%20STAR%20purchasing%20policy%20makes%20buying%20ENERGY%20STAR%20the,they%20are%20a%20viable%20option.
http://energy.gov/eere/femp/covered-product-categories http://www.access-board.gov/guidelines-and-standards/communications-and-it/about-the-section-508-standards/section-508-standards http://www.access-board.gov/guidelines-and-standards/communications-and-it/about-the-section-508-standards/section-508-standards http://section508.gov/Section-508-Of-The-Rehabilitation-Act https://www.ecfr.gov/current/title-36/chapter-XI/part-1194 http://dodcio.defense.gov/DoDSection508.aspx https://dodcio.defense.gov/DoDSection508.aspx
Exterior LED Lighting * Five (5) flood lights
* All electrical connectors are to be enclosed in the housing providing protection against the elements.
* Two (2) will be mounted on the driver’s side
* Two (2) on the passenger side
* One (1) on the rear of the body, as close to the top of the module as possible and evenly spaced across the width of the body to produce the most effective illumination approximately 15’ around the vehicle for working
* Separate control switches will operate each side of the vehicle independently (three switches)
Mouse hole for cable pass thru
Mousehole to run "ad hoc" cabling into/out of vehicle, installed in the lower portion of the wall on both sides of the vehicle. Mouseholes are lockable when not in use
Automatic stabilizers and foot pads
*Auto leveling and hydraulic stabilizer system
*Stabilizer foot pads
Exterior painting- white * Standard single stage industrial paint
* dry primer sealer
Kitchenette area upper/lower cabinet, counter space, and AC plugs 1
Office Chairs * five (5) high backed contemporary (standard office chair styling and function) Office Chairs
* Mounting clips and strap for transport to secure chairs when vehicle is in motion.
Flooring – Gray Coin Tile
Roll
2mm Industrial Grade coin tile made of premium grade ultra durable vinyl (must be antistatic ESD compliant)
Overhead cabinets and storage closet
* Overhead cabinets on front wall
* Full size storage closet w/shelving
Operator Workstations * Workstation console approximately 105" long by
~16" deep to provide space for four (4) work positions, each about 26" long, in front of or built in to equipment racks.
Each operator workstation shall have:
* Chairs
* Cable pathways for wiring/various plugs
* USB chargers built into power outlets
Roof Access Ladder * Roof Access Ladder installed on the outside rear wall
* Aluminum ladder assembly
Shore Power - 50A 50FT 4-wire 120/240V
* Allows for connection of the truck to shore or generator power, the truck shall include a 50
ft. four-wire 50 amp power cable terminated to a
NEMA 14-50P.
* 6-FT 50A - 125/250VAC pigtail (cheater cord, includes, (2 ea) NEMA 5-15P wired to a NEMA 14-
50R).
* Storage of the power cable in a lower storage compartment.
Interior LED Lighting Minimum eight (8) flush ceiling mounted lighting assemblies throughout work area, especially over workstations.
Power Drops & USB
Charging Ports
* Convenience and utility duplex 120v outlets located throughout vehicle interior.
Power Panel – 100A
125/240V AC and 12VDC panel – Single phase
* Power Panel with a 240-volt, 100-amp, Single phase power
* The power will be routed through a phase, volt and amperage meter then into a breaker box for distribution throughout the shelter
* The shelter will have 120-volt 20 Amp service throughout the shelter.
* The Single-phase power will be routed to a 100-amp
Single-phase electrical main breaker
* All cables will be concealed behind the wall or in an enclosed cable tray.
* The data cables and the electrical cables will be run in separate trays
* The data lines and the electrical lines must be physically separated minimum 1 inch
* Soft copies of electrical wiring schematics will be provided upon completion
DC Auxiliary Power box w/ battery and Charger
* Blue Top Battery (or equiv.) for interior lighting, DC voltage
* Battery tray; Bolt kit w/box
* 90a battery charger
* Wired to power panel with breakers/switches
* Crossover switch to start Gen with either battery
Diesel 120/240VAC, 14kW, single phase AC generator
Wired to power panel w/appropriate breakers
*Generator will be connected to a manual transfer rotary switch to select power the vehicle from generator or shore power.
*The generator should be fueled from the same fuel tank that supplies fuel to the chassis engine (one tank)
Exterior GFCI Outlet Power
Drops
Two (2) total includes 1-streetside and 1-curbside of the truck.
UPS for Rack 1500 VA UPS w/8 outlet power strips for each equipment rack.
Floor D-rings Flush in floor D-rings to secure loose items 6
Full Height Equipment * Single (1) 35RU equipment rack with standard 19" 5
Racks ID width, 31.5 depth, and 68" high w/ open sides for ventilation. Ends of rack are closed.
* Secured to floor and roof via rope shock mounts
* Rack isolators for rack
* Must have personnel access behind the back of rack and wall for set up, running our cable and changing configurations.
24” Monitors * (2) Monitors attached to swing arms secured to upper area of rack 1 and of rack 5 such that arms can swing in front of racks as desired. Arms secure for travel.
* Electrical outlets and signal paths provided for both monitors
55” Monitor LED flat panel High Definition 4k video screen.
Monitor has built in Tuner for direct reception of TV as well
Safety Equipment * Tire Jack for spare tire w/lug nut 4-way lug wrench
* One (1)1 - 10lb ABC dry chemical Fire extinguisher
* One (1) - Fire extinguisher brackets
* One (1) - First aid kit mounted in work area
* Two (2) - 10-year sealed Smoke/Carbon Dioxide
Detectors
* One (1) - Safety Triangle kit
* One (1) - Set of tire chocks
* Installation of components
* Vehicle Height sign placed in cab
* Payload sticker w/vehicle axle ratings
Vehicle and housing alarm Vehicle alarm to protect all entry doors
* Local alarm when any door is opened when system is armed.
* System arms and disarms using a key fob.
* System is independent of chassis systems
Dry erase board Install and secure a 4’x8’ whiteboard (dry erase) to the interior curb side wall
7. TECHNICAL REQUIREMENTS
The contractor shall ensure that all applicable Commercial-Off-The-Shelf (COTS) IA and IA-enabled products comply with Air Force Instruction (AFI) 17-130, Program Management. All
IT hardware, firmware, and software components or products incorporated into Department of
Defense Instruction (DoDIN) must comply with evaluation and validation requirements in
DoDI 8500.01 and Committee on National Security Systems Policy #11(CNSSP), National
Policy Governing Acquisition of IA Products.
Contractor shall provide rendering drawings of the proposed build before the build for review prior to final construction. The contractor shall also provide soft copies of the completed build to include electrical drawings/schematics upon delivery.
http://static.e-publishing.af.mil/production/1/saf_cio_a6/publication/afi17-130/afi33-200.pdf http://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodi/850001_2014.pdf
7.1. Technical Refresh
In order to ensure new design enhancements and technological updates or advances, the contractor shall provide, under this contract, commercial hardware only. Furthermore, the contractor shall make available any commercial updates to the hardware under this contract. If such updates are available to other customers without charge, then they shall also be made available to the Government without additional charge. The contractor will ship these updates to existing customers who have acquired the hardware being updated under this contract. Vendor commercial product offerings shall include “state of the art” technology, i.e., the most current proven level of development available in each product category.
7.2. Trade Agreement Act (TAA)
All proposed products must be compliant with the Trade Agreements Act of 1979 (TAA) and related clauses in Section I of the awarded contract. In accordance with DFARS 252.225-
7021, the Trade Agreements Certificate at DFARS 252.225-7020 shall be provided for each end item defined and specified in a solicitation that exceeds the TAA threshold subject to the waivers and exceptions provided in FAR 25.4, Trade Agreements and DFARS 225.4 offered in response to any RFQ issued under this contract. Please note that Federal Acquisition
Regulation (FAR) paragraph 25.103(e) includes an exemption from the Buy American Act
(BAA) for acquisition of information technology that is commercial items.
7.3. Authorized Resellers
If the contractor is not an OEM reseller, the contractor shall clearly identify this on the submitted proposal and list the OEM resell partner’s registered relationship with the OEM.
DOs may restrict the use of authorized resellers, specific OEMs, or identify required OEMs.
The contractor shall ensure all products are genuine and eligible for any OEM warranties, maintenance agreements and licensing as offered. Genuine products are those products the
OEM, by their policy, considers not “secondary”, destroyed, stolen or scrapped.
7.4. Remanufactured/Refurbished Products
All parts used for this MAV shall be new commercial products.
7.5. Items on Backorder
In the contractor response to this Request for Quote (RFQ), the contractor shall provide notification, if applicable, that a particular item is on backorder, the expected lead-time to fulfill the order, etc. Any items on back order shall be identified in contractors’ proposal at the time of quote submission.
7.6. Warranty
The contractor shall provide any OEM pass through warranty and standard commercial warranties applicable to the products being purchased at no cost. This shall apply to new equipment. The chassis and engine for this build shall maintained a warranty of five (5) years or 60K miles. All warranty work shall be done at the providers build site. Provided generators shall come with a Five (5) year 600 hour warranty.
7.7. Hardware and Associated Software and Peripherals
All hardware delivered under this award shall include associated software, documentation and associated peripherals required for operations (such as controllers, connectors, cables, drivers, adapters, etc.) as provided by the OEM. This is true only if the applicable OEM provides such items with the product itself.
7.8. Safeguarding Classified Information
There is no classified information associated with this acquisition.
8. DELIVERY REQUIREMENTS
8.1. Delivery Delays
Contractors are required to meet the timeframes as stated in section 6.1 unless Department of
Commerce approval and/or review activities prevent the contractor from meeting these timeframes. In the event that the contractor determines they are unable to achieve the stated timeframes, the contractor shall notify the Contracting Officer within fourteen (14) business days of such determination.
Delivery time will be based on the vendors availability to required assets to construct the vehicles. An expectation of 180 to 240 days (six to eight months) from award is expected and acceptable. If vendor is expected to exceed this time frame, then the customer is expected to be notified within 60 days (two months) of known delay.
If contract awarded vendor is located outside a 400-mile radius of JBSA-Lackland, then the vendor will make arrangements to have the vehicle delivered to the delivery address identified below after the in person completion inspection at the vendors facility.
If the contract awarded vendor is within a 400-mile radius of JBSA-Lackland then the
Government will take procession of the vehicle after the in-person final inspection at the facility and driven back to JBSA-Lackland.
Once vendor has gotten to a 40% and 90% design of the vehicle then a telecom will be initiated so that the design can be explained and verified to government satisfaction.
Shipping Information
All products shall be shipped to:
346 TS
Attn: 346 TS/TECS
1303 Billy Mitchell Rd, Bldg. 1005
JBSA-Lackland 78236
Inspection/Acceptance: The following Government officials are responsible for receiving the products and performing inspection:
Primary POC: Milton “Andy” Van Court
Alternate POC: Phil Castellano
Alternate POC: Joseph McCullough
Alternate POC: Randy Henderson
File details come from the government source that posted it. Updated .