This document is a Questions and Answers (Q&A) file for Solicitation FA875125B0002, a Department of the Air Force Materiel Command Research Laboratory project to install boilers in Building 2 and Building 3. The solicitation requires sealed bids with specific submission guidelines, including a mandatory 20% bid guarantee and email submission to Tabitha Haggart and Bryant Soule by 2 PM EST on 21 April 2025. A pre-bid conference and site visit is scheduled for 15 April 2025 at 1:30 PM EST, with attendees required to complete a DBIDS Pre-Enrollment Request and email a confirmation code.
Key procedural details include email-only bid submissions, no partial bids accepted, and bid opening at the Visitor Control Center (AFRL/Information Directorate) in Rome, NY. Potential bidders will be listed on BetaSAM after the site visit, with firms designated as prime or sub-contractors. The contract specialist, Tabitha Haggart, can be reached at tabitha.haggart@us.af.mil or via office (315-330-3787) and cell (347-853-3823) for any inquiries about the solicitation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA875125B0002 Q and A 4-30-25.docx | DOCX document | |
| Solicitation Amendment FA875125B00020001 SF 30.pdf | ||
| FA875125B0002 Q and A _4-24-25.docx | DOCX document | |
| FA875125B0001 Q and A 4-18-25.docx | DOCX document | |
| April 15 site visit attendee list.docx | DOCX document | |
| Attch 1 B2- Construction Specifications.pdf | ||
| Attch 2 B2 - Contract Drawings.pdf | ||
| Attch 3 B2 Addendum.pdf | ||
| Attachment 9_ FRL RI SOW-PWS Supplemental Requirements.pdf | ||
| Solicitation - FA875125B0002.pdf | ||
| Attch 4 B2 Haz Mat Report.pdf | ||
| Attch 5 B3 - Construction Specifications.pdf | ||
| Attch 7 Hazmat AFRL Bldg 3 022924.pdf | ||
| Attch 6 B3 - Construction Drawing.pdf | ||
| Attch 8 Davis Bacon Act WD No. NY20250013.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA875125B0002
Q&A dated 4/11/2025 Q1. What is the bid guarantee requirements for this requirement?
A1. 20% of the bid price, disregard the TBD in the SF 1442 document.
Q2. Who is the sponsor for the site visit?
A2, Tabitha Haggart Contract Specialist, tabitha.haggart@us.af.mil, Office: 315-330-3787, Cell: 347-853-3823
Q3. Is there an intended or pre-qualified bidders list for this project?
A3. We do not pre-qualify, but there will be an attendance list from the site visit posted to BetaSAM where firms will be designated as interested party prime-contractor or sub-contractor.