Core Mission Computer / Weather Radar
(CMC/WxR) Production Program
Program Manager: Ms. Jennie Pechie Ohlson
AFLCMC/WLSP 937-656-7992
Jennifer.Ohlson.5@us.af.mil
Contracting Officer: Ms. Michelle Pickel
AFLCMC/WLSK 937-656-9540
Michelle.Pickel@us.af.mil
AF Life Cycle Management Center
Rules of Engagement
The Government does not intend to award a contract on the basis of the information received at this event
This is for informational purposes only. The contents of any future Request for Proposal (RFP) take precedence over anything provided during this briefing and one-on-one sessions
Questions and answers will be posted to FBO and are considered public record
Costs incurred as a result of this meeting are considered bid and proposal costs and will not be reimbursed by the Government
Information Presented during Briefings is Subject to Change
30as of 21 Jul 17
CMC/WxR Agenda
Program Overview Current Status Group B Line Replaceable Units (LRUs) Planned Scope Schedule for Contract Award Notional Kit Deliveries Notional Contract Type Key Suppliers
CMC/WxR Program Overview
Permanent sustainment modification to C-5M CMC: Incorporates changes to the Core Processing
Modules (CPM) within the current CMC to improve throughput margin WxR: Replaces the AN/APS-133 with the Rockwell
Collins WXR-2100 to resolve diminishing manufacturing sources (DMS) issues Updates the remaining 50 aircraft
Current Status of CMC/WxR:
Design
Engineering and Manufacturing Development (EMD) Phase nearly complete (Jan 2018) Developmental Test & Evaluation (DT&E) is complete Preparing for Operational Test and Evaluation (OT&E) Technical Data Package is updated and will be included in the upcoming bidders library Record Time Compliance Technical Order (TCTO) Completed and will be included in the upcoming bidders library Technical Order Updates tracking for Jan 2018 delivery
CMC/WxR Design is established, successfully integrated and through initial testing Changes to the design at this time would result in increased cost to the
Government and critical schedule impacts
CMC/WxR Group B LRUs
VIA/AIU
Video Distribution UnitRadar Control Panel
Receiver/ Transmitter
Bunk Panel
Antenna Pedestal
Antenna Array
Waveguide
Bunk Panel: FTG Aerospace
Radar Control Panel: Rockwell Collins
Video Distribution Unit: Ballard
VIA/AIU: Honeywell
Radar Receiver/Transmitter:
Rockwell Collins
Waveguide: Mega Industries
Antenna Array: Rockwell
Prime Contractor Responsibility
Contract for, and/or manufacture as applicable, all components identified in the Record TCTO Integrate all components into kits assembled and organized by installation steps Kits shall be easy for the Depot Personnel to inventory upon receipt Expedite delivery of new components when requested to replace kit components damaged during installation Deliver Initial Spares
Planned Scope for Competition
Task Responsibility 50 aircraft mod kits Mix of GFP/Competition VIA/AIU Modification GFP provided to Prime Rockwell WxR-2100 Prime Responsibility Mega Waveguide Prime Responsibility FTG Aero Bunk Panel Prime Responsibility Ballard VDU Prime Responsibility Group A Wiring, Harnesses, Brackets, etc.
Prime Responsibility
Transportation of Kits and Spares to delivery locations
TBD
Class Justification and Approval (J&A) will be in place for Directed Subcontractors
Planned Scope cont’d
Replacement of Components to support installation
Prime Responsibility (Exception—
VIA/AIU)
DMSMS Plan and Obsolescence Reporting of all Kit Components
Prime Responsibility (Exception—
VIA/AIU)
Attendance and Support for biannual EPMRs, biannual Program Reviews, C-5 Enterprise Telecoms, Weekly IPT Telecoms
Prime Responsibility
Planned Scope cont’d
Associate Contractor Agreements Prime Responsibility (Includes—
Honeywell) Warranty Pass Through Prime Responsibility Technical Data Package Updates Prime Responsibility
Notional Acquisition Schedule
Pre-Solicitation Industry Days Oct 17 RFP Release by 20 Dec 17 Proposals Due 18 Feb 18 Contract Award Nov 18 First Kits Required at Depot Oct 19 Period of Performance End Dec 23
Notional Kit Deliveries
Lot Quantity Delivery Period Lot 1 11 kits Oct 19-Sep 20 Lot 2 21 kits Oct 20-Sep 21 Lot 3 16 kits Oct-21-Sep 22 Lot 4 2 kits Oct 22
Deliveries will be batched every three months and quantities per delivery will be presented in the Draft Request for Proposal (Oct 17)
Lot Deliveries will be front loaded (e.g. Lot 2 may deliver as (8/6/5/2)
Notional Contract Type
Continue to research FAR Part 12 or FAR Part 15 for competition Anticipate a predominantly Firm Fixed Price (FFP) contract for Kits, Initial Spares, and Support Equipment Travel will be Cost Reimbursable, No Fee (CRNF) If determined applicable, Over & Above (O&A) will be
Cost-Plus-Fixed Fee (CPFF) (Dollar Value will be provided by the Government)
Incentives and Disincentives for schedule and kit deliveries are being considered—industry feedback is welcomed
Key Suppliers
Rockwell Collins Mega Industries Ballard FTG Aerospace Honeywell
| Core Mission Computer / Weather Radar (CMC/WxR) �Production Program |
| Rules of Engagement |
| CMC/WxR Agenda |
| CMC/WxR Program Overview |
| Current Status of CMC/WxR: Design |
| CMC/WxR Group B LRUs |
| Prime Contractor Responsibility |
| Planned Scope for Competition |
| Planned Scope cont’d |
| Planned Scope cont’d |
| Notional Acquisition Schedule |
| Notional Kit Deliveries |
| Notional Contract Type |
| Key Suppliers |