Core_Mission_Computer_Weather_Radar_Production_-_Copy.pdf

PDF 421 KB Posted

Attached to
C-5M RFP Follow Up Questions & Answers
Solicitation number
FA8625-18-R-6701
Issued by

About this file

C-5M Enterprise Industry Day_ CMC/WxR Production Briefing

View the file

Other files

File Type Posted
Final_Email_Q&As_Post_to_FBO_27_Dec_17.pdf PDF
QAs_from_Model_Contract_Industry_Day_for_posting_17_Dec_FBO_Posting.docx DOCX document
Draft_Model_Contract.pdf PDF
Copy_of_Kit_Delivery_Dates.xlsx XLSX spreadsheet
Attachment___Initial_Spares_List.xlsx XLSX spreadsheet
Directed_Subs_Contact_List.docx DOCX document
Model_Contract_Section_K_Reps_and_Certs.pdf PDF
Attachment_L004-_Pricing_Matrix_FBO_POSTING.xlsx XLSX spreadsheet
SOW_Industry_Day_QA_(FBO_Posting).docx DOCX document
Directed_Subs_Contact_List.docx DOCX document
QAs_from_TDP_Industry_Day_FBO_Posting.docx DOCX document
Sections_L_and_M_Industry_Day_QAs_(FBO_Posting).docx DOCX document
Section_L__(FBO_Draft)_11.30.17.pdf PDF
Section_M_(FBO_Draft)__11.29.17.pdf PDF
Section_L__(FBO_Draft)_11.29.17(Read-Only).docx DOCX document
FBO_DRAFT_CMC_WXR_PIMA_SOW_15_Nov_17.pdf PDF
PIMA_CDRLs_-_Draft_-_15_Nov_2017.pdf PDF
C-5M_Enterprise_Industry_Days_Q&A_Programs.docx DOCX document
Final_Registration.pdf PDF
RMCD_Program_-_Copy.pdf PDF
Core_Mission_Computer_Weather_Radar_Production_-_Copy.pdf PDF
C5__Industry_Day_2017_Small_Business_Briefing.pptx PPTX presentation
C5_Enterprise_Overview_-_Copy.pdf PDF
CNS_ATM_Production_-_Copy.pdf PDF
MUOS_Program_-_Copy.pdf PDF
LAIRCM_Block_30_Production_-_Copy.pdf PDF
C5M_Industry_Day_Registration_Form.pdf PDF
C5__Industry_Day_2017_Small_Business_Briefing.pptx PPTX presentation
MUOS_Program_-_Copy.pdf PDF
RMCD_Program_-_Copy.pdf PDF
LAIRCM_Block_30_Production_-_Copy.pdf PDF
C5_Enterprise_Overview_-_Copy.pdf PDF
CNS_ATM_Production_-_Copy.pdf PDF
http://www.signupgenius.com/go/30E0F4BAAAD2CA2FF2-oneonone —
C5M_Industry_Day_Registration_Form_1.pdf PDF
AGENDA_Industry_Days.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Core Mission Computer / Weather Radar

(CMC/WxR) Production Program

Program Manager: Ms. Jennie Pechie Ohlson

AFLCMC/WLSP 937-656-7992

Jennifer.Ohlson.5@us.af.mil

Contracting Officer: Ms. Michelle Pickel

AFLCMC/WLSK 937-656-9540

Michelle.Pickel@us.af.mil

AF Life Cycle Management Center

Rules of Engagement

The Government does not intend to award a contract on the basis of the information received at this event

This is for informational purposes only. The contents of any future Request for Proposal (RFP) take precedence over anything provided during this briefing and one-on-one sessions

Questions and answers will be posted to FBO and are considered public record

Costs incurred as a result of this meeting are considered bid and proposal costs and will not be reimbursed by the Government

Information Presented during Briefings is Subject to Change

30as of 21 Jul 17

CMC/WxR Agenda

Program Overview Current Status Group B Line Replaceable Units (LRUs) Planned Scope Schedule for Contract Award Notional Kit Deliveries Notional Contract Type Key Suppliers

CMC/WxR Program Overview

Permanent sustainment modification to C-5M CMC: Incorporates changes to the Core Processing

Modules (CPM) within the current CMC to improve throughput margin WxR: Replaces the AN/APS-133 with the Rockwell

Collins WXR-2100 to resolve diminishing manufacturing sources (DMS) issues Updates the remaining 50 aircraft

Current Status of CMC/WxR:

Design

Engineering and Manufacturing Development (EMD) Phase nearly complete (Jan 2018) Developmental Test & Evaluation (DT&E) is complete Preparing for Operational Test and Evaluation (OT&E) Technical Data Package is updated and will be included in the upcoming bidders library Record Time Compliance Technical Order (TCTO) Completed and will be included in the upcoming bidders library Technical Order Updates tracking for Jan 2018 delivery

CMC/WxR Design is established, successfully integrated and through initial testing Changes to the design at this time would result in increased cost to the

Government and critical schedule impacts

CMC/WxR Group B LRUs

VIA/AIU

Video Distribution UnitRadar Control Panel

Receiver/ Transmitter

Bunk Panel

Antenna Pedestal

Antenna Array

Waveguide

Bunk Panel: FTG Aerospace

Radar Control Panel: Rockwell Collins

Video Distribution Unit: Ballard

VIA/AIU: Honeywell

Radar Receiver/Transmitter:

Rockwell Collins

Waveguide: Mega Industries

Antenna Array: Rockwell

Prime Contractor Responsibility

Contract for, and/or manufacture as applicable, all components identified in the Record TCTO Integrate all components into kits assembled and organized by installation steps Kits shall be easy for the Depot Personnel to inventory upon receipt Expedite delivery of new components when requested to replace kit components damaged during installation Deliver Initial Spares

Planned Scope for Competition

Task Responsibility 50 aircraft mod kits Mix of GFP/Competition VIA/AIU Modification GFP provided to Prime Rockwell WxR-2100 Prime Responsibility Mega Waveguide Prime Responsibility FTG Aero Bunk Panel Prime Responsibility Ballard VDU Prime Responsibility Group A Wiring, Harnesses, Brackets, etc.

Prime Responsibility

Transportation of Kits and Spares to delivery locations

TBD

Class Justification and Approval (J&A) will be in place for Directed Subcontractors

Planned Scope cont’d

Replacement of Components to support installation

Prime Responsibility (Exception—

VIA/AIU)

DMSMS Plan and Obsolescence Reporting of all Kit Components

Prime Responsibility (Exception—

VIA/AIU)

Attendance and Support for biannual EPMRs, biannual Program Reviews, C-5 Enterprise Telecoms, Weekly IPT Telecoms

Prime Responsibility

Planned Scope cont’d

Associate Contractor Agreements Prime Responsibility (Includes—

Honeywell) Warranty Pass Through Prime Responsibility Technical Data Package Updates Prime Responsibility

Notional Acquisition Schedule

Pre-Solicitation Industry Days Oct 17 RFP Release by 20 Dec 17 Proposals Due 18 Feb 18 Contract Award Nov 18 First Kits Required at Depot Oct 19 Period of Performance End Dec 23

Notional Kit Deliveries

Lot Quantity Delivery Period Lot 1 11 kits Oct 19-Sep 20 Lot 2 21 kits Oct 20-Sep 21 Lot 3 16 kits Oct-21-Sep 22 Lot 4 2 kits Oct 22

Deliveries will be batched every three months and quantities per delivery will be presented in the Draft Request for Proposal (Oct 17)

Lot Deliveries will be front loaded (e.g. Lot 2 may deliver as (8/6/5/2)

Notional Contract Type

Continue to research FAR Part 12 or FAR Part 15 for competition Anticipate a predominantly Firm Fixed Price (FFP) contract for Kits, Initial Spares, and Support Equipment Travel will be Cost Reimbursable, No Fee (CRNF) If determined applicable, Over & Above (O&A) will be

Cost-Plus-Fixed Fee (CPFF) (Dollar Value will be provided by the Government)

Incentives and Disincentives for schedule and kit deliveries are being considered—industry feedback is welcomed

Key Suppliers

Rockwell Collins Mega Industries Ballard FTG Aerospace Honeywell

Core Mission Computer / Weather Radar (CMC/WxR) �Production Program
Rules of Engagement
CMC/WxR Agenda
CMC/WxR Program Overview
Current Status of CMC/WxR: Design
CMC/WxR Group B LRUs
Prime Contractor Responsibility
Planned Scope for Competition
Planned Scope cont’d
Planned Scope cont’d
Notional Acquisition Schedule
Notional Kit Deliveries
Notional Contract Type
Key Suppliers

File details come from the government source that posted it. Updated .