Appendix C

View the file

Other files

File Type Posted
ADD_I.docx DOCX document
ADD_I.docx DOCX document
FA8604-12-R-7955_0001.pdf PDF
DI DRPR 81003.pdf PDF
DI MGMT 80909 T.pdf PDF
APPENDIX D.docx DOCX document
BFR1B0-01.dwg DWG drawing
a002.doc DOC document
DI TMSS 80527.pdf PDF
APPENDIX A.docx DOCX document
APPENDIX B.docx DOCX document
Notification_of_Compliance_with_Contract_Insurance_Requirements_(Sols).docx DOCX document
DI MGMT 80227 T.pdf PDF
Contractor Information —
BFR1B0-03.dwg DWG drawing
BFR1B0-02.dwg DWG drawing
a003.doc DOC document
a004.doc DOC document
A001.doc DOC document
FA860412R7955_RFP.pdf PDF
a006.doc DOC document
Cover PD.docx DOCX document
a007.doc DOC document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL PROPOSAL QUESTIONNAIRE

FOR

Offeror: _ Solicitation No. F33600- -R- _

Offeror:

Solicitation Number:
FA8604-

-R-

APPENDIX C

FOR A

MEZZANINE

AT

FAIRCHILD AIR FORCE BASE, WASHINGTON

BUILDING 2163

CSN: BFR1B0

DATE: 31 August 2011

PREPARED BY:

SHANE M. LEGGE

PROJECT ENGINEER

403 SCMS/GUEC

DONNA L. HARTMAN

REVIEWER

403 SCMS/GUEC

Table of Contents

1. SCOPE1
1.1. General scope1
1.2. Definitions1
2. APPLICABLE DOCUMENTS1
3. REQUIREMENTS2
3.1. System Description2
3.2. Characteristics3
3.2.1. Performance and Physical characteristics3
3.2.1.1. Load capacity3
3.2.1.2. Freestanding structure3
3.2.1.3. Deflection under load3
3.2.1.4. Dimension and clear height3
3.2.1.5. Seismic4
3.2.1.6. Columns4
3.2.1.6.1. Base plates4
3.2.1.7. Framing4
3.2.1.7.1. Beams4
3.2.1.7.2. Joists4
3.2.1.7.3. Bridging5
3.2.1.8. Decking5
3.2.1.8.1. Metal roof deck5
3.2.1.8.2. CompositE flooring5
3.2.1.9. Stairway systems5
3.2.1.9.1. Stair treads6
3.2.1.9.2. Stringers6
3.2.1.9.3. Railing6
3.2.1.9.4. Platforms6
3.2.1.10. Fixed ladders6
3.2.1.11. Mezzanine Railing6
3.2.1.12. Kickplate7
3.2.1.13. Pallet gate7
3.2.1.14. Fire suppression system.7
3.2.2. Electrical characteristics8
3.2.2.1. Lighting8
3.2.2.1.1. Fixtures8
3.2.2.1.2. Motion Sensor On/Off8
3.2.3. Safety features8
3.2.3.1. Capacity markings8
3.2.3.2. No-Step markings8
3.2.3.3. Safety factor9
4. QUALITY CONFORMANCE9
4.1. Inspections9
4.2. Test9
4.3. Certifications10

Fairchild AFB App C - Page 10

SCOPE

General scope This appendix establishes the minimum performance, design, fabrication, installation, and test requirements for a mezzanine for the 92ND LRS, Bldg. 2163, at Fairchild Air Force Base (AFB), WA. The work shall be completed in accordance with this appendix, the Cover Purchase Description (PD), and Air Force (AF) Drawings BFR1B0-01 and BFR1B0-03. This appendix covers all equipment, materials, and labor necessary to complete installation of the system.

Definitions Beams - Structural steel supporting member which connect the columns.

Bridging - Steel channels used to provide lateral stability and prevent joists from twisting.

Column - Structural steel that supports beams and joist.

Framing - Consists of beams, joists, and bridging.

Joists - Structural steel member supporting the decking.

APPLICABLE DOCUMENTS

Applicable documents shall be in accordance with Section 2 of the Cover PD and the following:

AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)

ASTM A36/A36M-97A
Standard Specification for Structural

Steel

ASTM A366/A366M-91
Standard Specification for Steel Sheet, Carbon Cold-Rolled, Commercial Quality
ASTM 446/A446M-89
Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) by the Hot-Dip Process, Structural (Physical) Quality
ASTM A500-98
Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes
ASTM A570
Standard Specification for Steel, Sheet and Strip, Carbon, Hot-Rolled, Structural Quality
ASTM A611
Standard Specification for Steel, Sheet, Carbon, Cold-Rolled, Structural Quality

(Applications for copies should be addressed to the American Society for Testing and Materials, 1916 Race Street, Philadelphia PA 19103)

US PRODUCT STANDARDS

USPS 1-95
For Construction and Industrial Plywood with Typical APA Trademark

(Applications for copies should be addressed to the American Plywood Association, PO Box 11700, Tacoma WA 98411-0700).

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 13-99
Standard for the Installation of Sprinkler Systems
NFPA 255-90
Standard Method of Test of Surface Burning Characteristics of Building Materials

Applications for copies shall be addressed to the National Fire Protection Association, One Batterymarch Park, P. O. Box 9101, Quincy MA 02269-9101)

REQUIREMENTS

System Description The mezzanine shall be located in Area A of building 2163 key plan as shown on AF Drawing BFR1B0-01. The mezzanine shall be used to store medium and bulk items. The mezzanine system shall consist of the following components:

a. Freestanding, structural steel mezzanine with columns, beams, joists, decking, and bridging.

b. Stairs, platforms, handrails, midrails, and kickplates.

c. Fixed ladder.

c. Lighting.

d. Fire suppression system.

e. Pallet gate(s).

h. Conduit, wiring, mechanical fasteners, and all other items required to install a functional mezzanine system.

Characteristics Performance and Physical characteristics Load capacity All components of the mezzanine shall be designed to support a minimum capacity of 125 pounds per square foot. The mezzanine shall be capable of sustaining the capacity without permanent deflection or deformation.

Freestanding structure The mezzanine shall not be attached to any existing building wall or column and shall not require cross bracing between columns.

PRE-ENGINEERED

All components of the mezzanine shall be pre-engineered so that on-site welding is eliminated.

Deflection under load No component of the mezzanine shall exhibit deflections greater than the length of the component divided by 360 (L/360) under uniformly loaded conditions.

Dimension and clear height The mezzanine shall be a nominal 60 feet long X 30 feet wide. The mezzanine shall have a nominal clear height of 10 feet underneath all components of the mezzanine. The top of the decking shall be a maximum of 12 feet above the existing floor.

Seismic The system shall be designed to withstand seismic conditions in accordance with IBC Section 1613. Certified engineer load calculations are required for the mezzanine.

Columns Columns shall be cold formed, structural steel tubing and shall meet or exceed the requirements of ASTM A500, Grade B, FY-46KSI. Columns shall be spaced on minimum 12 foot X 15 foot centers as shown on AF Drawings BFR1B0-01 and BFR1B0-03. The columns shall be pre-punched at the top to provide a secure connection to beams and joists. Columns shall be a minimum of 5 inches X 5 inches X 3/16 inch thick.

Base plates Base plates shall be used under each column to distribute the load. The base plates shall be factory welded to the columns and prepunched to provide a secure connection to the floor. The base plates shall be anchored in accordance with the manufacturers recommended procedure. The base plates shall meet or exceed the requirements of ASTM A36 and shall be a minimum of 10 inches X 10 inches X 5/8 inch. Base plate grout shall be used as required. The concrete slab is 6" thick with 6 X 6 6/6 wire fabric for reinforcement.

Framing Hot rolled structural steel members shall meet or exceed the requirements of ASTM A570. Cold-formed structural steel members shall meet or exceed the requirements of ASTM A500 or ASTM A611. Framing shall consist of beams, joists and bridging as defined in 1.2. The framing shall be designed to support the full rated load and the decking.

Beams All beams shall be structural steel and shall be prepunched for secure connection to the columns and joists with A325 bolts.

Joists All joists shall be structural steel and shall be prepunched for secure connection to the beams with A325 bolts.

Bridging Structural steel bridging channels shall be minimum 18-gauge steel.

Decking The decking shall consist of a metal roof deck and a composite flooring with a minimum density of 45 pounds per cubic foot. The decking shall sustain the load specified in 3.2.1.1.

Metal roof deck The metal roof deck shall be galvanized or painted on both sides and consist of minimum 20-gauge, type-B roof deck meeting the requirements of ASTM A611, Grade C, or minimum 18 gauge, type-B roof deck meeting the requirements of ASTM A446, Grade A. If the roof deck is painted, the bottom of the roof deck shall be painted white and the top shall be painted the manufacturer's standard color. The roof deck shall be securely fastened to the framing with plated, self-tapping, steel screws or equivalent as approved by the Contracting Officer’s Technical Representative (COTR).

CompositE flooring The composite flooring shall be resindek or equivalent. Resindek flooring is a special blend of phenolic resin, wax emulsion, and wood fibers combined under heat and pressure. The flooring shall be minimum 3/4-inch thick. The flooring shall have an exterior sealant. The sealant shall be Acryseal or equivalent. A sealant color chart shall be provided with the shop drawings for selection by the COTR. The flooring sheets shall be tongue and groove on long sides forming an integral surface. The flooring sheets shall be securely fastened to the framing with resindek type drill screws or equivalent. All exposed sides of the composite flooring shall be covered.

Stairway systems A stairway system shall be provided at the location shown on AF Drawing BFR1B0-01 and BFR1B0-03. The stairway system shall include stairs, structural steel stringers, railing, platforms, and all necessary hardware to install the stairway. The Stairway shall be 40 inches wide, with 36-inch tread. The sStairway shall be designed and constructed in accordance with IBC. The stairway system shall be painted safety yellow.

Stair treads Stairs shall be open tread type with bar grating or closed tread with diamond plate.

Stringers Stringers shall meet or exceed the requirements of ASTM A36.

Railing Railing shall be provided on the open sides of all exposed stairways and platforms. Rails shall be designed and constructed in accordance with OSHA 1910.23 and shall be of either the 2-rail or 3-rail type. The top rail surface shall be between 30-34 inches above the stair tread surface. Railing shall be minimum 1-1/4 inch, schedule 40 steel tubing. Rail sections shall be joined together with either galvanized fittings or a pre-engineered union. Railing for the stairway shall be bolt connected or factory welded to the stringer such that it is capable of withstanding a load of at least 200 pounds applied in any direction at any point on the top rail.

Platforms Platforms, if used, shall be the same width as the stairway and minimum 40 inches in length (measured in the direction of travel). Platforms shall be even and level with the mezzanine floor.

Fixed ladders One steel fixed ladder shall be provided at the locations shown on AF Drawing BFR1B0-01 and BFR1B0-03. All components of the fixed ladders shall be in compliance with IBC as well as the following requirements. Fixed ladders shall have walk-through handrails and safety cages. The walk-through handrails shall have a safety chain attached, which prevents accidental exit from the top-landing surface.

Mezzanine Railing Railing shall be provided on the open sides of all exposed mezzanine floor. Rails shall be designed and constructed in accordance with IBC and shall be of either the 2-rail or 3-rail type. The top rail surface shall be 42-inches above the mezzanine decking. Railing shall be minimum 1-1/2 inch diameter, schedule 40 steel, round or square tubing. Rail sections shall be joined together with either galvanized fittings or a pre-engineered union. Railing for the mezzanine shall be bolt-connected to a structural framing beam such that it is capable of withstanding a load of at least 200 pounds applied in any direction at any point on the top rail. Support posts shall be spaced on a maximum of 8-foot centers.

Kickplate A kickplate shall be provided on all open sides of the mezzanine and platforms. The kickplate shall be a minimum 4-inches high with no more than 1/4-inch clearance between the floor and the bottom of the kickplate. The kickplate shall be minimum 14-gauge steel and shall be securely fastened to the mezzanine or railings.

Pallet gate Two pallet gates shall be provided at the locations shown on AF Drawings BFR1B07-01 and BFR1B0-03. One gate shall be used to load/unload material from the mezzanine using a standard forklift. The pallet gate shall be constructed of steel tubing matching the railing and shall provide a minimum opening of 72 inches. The pallet gate shall be the sliding type. One pallet gate shall be hinged to swing inward to allow large bulk items to be placed on the top of the mezzanine. The hinged pallet gate shall be approx 10-ft wide with two five-foot sections swinging inward.

Fire suppression system.

The Contractor shall design and install a wet-pipe fire suppression system under the mezzanine in accordance with NFPA 13 and applicable fire codes at Fairchild AFB WA. All appendices of NFPA 13 will be considered to be a part of the main body of the standard; all "shoulds" will be considered "shalls" in this project. Sprinkler size, spacing and location shall be in accordance with NFPA 13, Chapter 4 and designed for non-encapsulated Class IV commodity as defined in NFPA 13, Section 1-7. The Contractor shall coordinate connection of the sprinkler system with the Fire Chief at Fairchild AFB WA. Sprinkler heads and piping shall be located so not to be susceptible to damage or interfere with normal operations under the mezzanine. The clear height specified in 3.2.1.4 shall be maintained. The Contractor shall connect the fire suppression system to the existing system piping at the most economical point permitted by NFPA 13 criteria and approved by the COTR. All pipe shall be painted red or stickers added as approved by Fairchild AFB Fire Department.

The available water supply at the base of the riser is:

Static Pressure: 56 psi Residual Pressure: 51 psi at 1500 gallons per minute (gpm) flow.

The fire suppression design and hydraulic calculations shall be sealed by a qualified registered Professional Engineer or a R.M.E. (NICET Level IV) technician.

Electrical characteristics Lighting The Contractor shall provide fluorescent lighting underneath the mezzanine with a minimum illuminance level of 20 foot-candles measured at 30 inches above the floor. Lighting shall be supported by the mezzanine.

Fixtures Lighting fixture boxes shall not be smaller than 4 inches (octagonal), except where required by fixture configuration and approved by the COTR. Fixtures shall provide rapid start lighting. Fixtures shall not be suspended. T-8 fluorescent light fixtures and lights shall be utilized. Fluorescent lighting using 4-foot tubes shall be utilized to light the mezzanine area. Lenses shall be provided for all lights.

Motion Sensor On/Off Lighting shall come on via motion sensors. Lighting shall stay on for 5 minutes without any motion detection.

Safety features Capacity markings Live load capacity metal signs shall be displayed on all sides of the mezzanine.

No-Step markings Signs shall be posted on the railings indicating that the rails are not steps. Signs shall be posted on a maximum of 20-foot centers.

Safety factor All vertical members of the mezzanine shall have a minimum safety factor of 1.92 to 1 and all horizontal members shall have a minimum safety factor of 1.67 to 1.

QUALITY CONFORMANCE

Inspections The system shall be inspected to verify that it meets all the requirements of sections 1, 2, and 3 of this appendix and the Cover Purchase Description. These inspections shall be completed as part of the system checkout test and again as a part of the quality conformance test.

Test The following test shall be performed on the system as part of the system checkout test and again as a part of the quality conformance test.

No.
Description
1.
The COTR shall select three joists. At the midpoint of the joists, the distance from the bottom of the joist to the floor will be measured in inches and recorded as M1. A minimum of three pallets weighing 125 pounds per square foot shall be placed over the joists. After a continuous 4 hours, the distance from the midpoint of the joist to the floor will be measured in inches and recorded as M2. The deflection shall be calculated by using the following formula:

(M1 - M2) / (Span of joist in inches) = Deflection

If the deflection is greater than (Span of joist in inches)/360 or any permanent deformation has occurred, the mezzanine shall fail the test.

2.
The lighting under the mezzanine shall be turned on. Test the lighting with a light meter 30 inches from the floor. If the lighting is not a minimum of 20 foot-candles then the system shall fail the test.

Certifications The Contractor shall provide certification that the following requirements have been met. All certifications shall be provided in accordance with the Contract Data Requirements List.

No.
Paragraph
Certification
1.
3.2.1.1.
All components of the mezzanine shall be designed to support a minimum capacity of 125 pounds per square foot.

2.

3.

3.2.3.3.

3.2.1.14.1.

All vertical members of the mezzanine shall have a minimum safety factor of 1.92 to 1 and all horizontal members shall have a minimum safety factor of 1.67 to 1.

The design and installation of the in-rack sprinkler system meets the requirements of NFPA 13, and any local codes and standards at Fairchild Air Force Base, WA.

MEZZANINE SYSTEM

Offeror:

Solicitation Number:
FA8604-

-R-

Project Title:
Storage Aid System
Base:
Fairchild AFB WA
CSN:
BFR1B0

Appendix D, Mezzanine, 31 August 2011

The Offeror shall complete this questionnaire. All entries to this questionnaire shall be typed. The questionnaire will be used to determine the Offeror's understanding of the requirements and acceptability of the proposed equipment. Please attach product literature/cut sheets for all equipment detailed in this questionnaire and attach any exceptions to the Purchase Description Appendix or recommendations/design alternatives as detailed below.

Mezzanine Manufacturer: ________________________________________ Model Number: __________________________________________________

Paragraph
Characteristics
3.2.1.1.
All components are designed to support a minimum of __________________________________________ psf
3.2.1.2.
Is the mezzanine freestanding?

Are all components pre-engineered so that on site welding is eliminated?

3.2.1.3.
All components are designed so that deflection is not greater than _______________________________.
3.2.1.4.
The clear height underneath the mezzanine is ______feet.

The height of the decking surface above the finished floor is ____ feet.

What are the dimensions of the mezzanine? ______ feet long X ______ feet wide.

3.2.1.5.
The mezzanine is designed for seismic zone _____.
3.2.1.6.
The columns are on _______ foot centers.

The dimensions of the columns are ______ inches X ______ inches.

Are the columns structural steel tubing?

3.2.1.6.1.
The dimensions of the base plates are ______ inches X ______ inches
3.2.1.7.
What type of framing are you proposing?___________ __________________________________________________ __________________________________________________ __________________________________________________
3.2.1.7.1.
Will all beams and joists be structural steel and pre-punched for connection?

Will A325 bolts be used for connection?

3.2.1.8.
What type of decking are you proposing? ____________________________________________________________________________________________________ __________________________________________________ __________________________________________________ __________________________________________________ __________________________________________________ __________________________________________________

What is the brand name of the decking? ___________ __________________________________________________

3.2.1.12.
How many sets of stairs are you providing? ______

What is the width of the stairs? ______ inches

3.2.1.12.1.
Are stairs open tread type with bar grating or closed tread with diamond plate? _________________
3.2.1.12.3.
Are the handrails in accordance with IBC?

Are rail sections joined with galvanized fittings or are they a pre-engineered union? ______________

3.2.1.12.4.
Are the platforms the same width as the stairs?

What is the length of the platform? _____ inches

3.2.1.13.
Are the railings in accordance with IBC?
3.2.1.19.
The kickplate is ____ inches high.
3.2.1.16.
The pallet gate provides an opening of ___ inches
3.2.1.19.
Will the fire sprinkler system meet all the requirements specified in this appendix?
3.2.2.1.
The lighting will provide a minimum illumination level of ___ foot-candles measured at 30 inches above the floor.

3.2.3.1.

Are capacity markings provided?

3.2.3.2.

Are no-step markings provided?

3.2.3.3.
Vertical members have a minimum safety factor of _____ to __.

Horizontal members have a minimum safety factor of______ to ___.

EXCEPTIONS/RECOMMENDATIONS/DESIGN ALTERNATIVES

Attach any exceptions taken to the Purchase Description Appendix. Please outline those concerns in detail. Your exceptions will be reviewed to determine acceptability.

Are exceptions taken?

Number of pages attached: ____________________________________

Attach any recommendations or design alternatives you feel may enhance operation, maintainability, or reduce system cost. Your recommendations and design alternatives will be reviewed to determine acceptability.

Are recommendations/design alternatives attached?

Number of pages attached: ____________________________________

We have read the requirements of the Purchase Description Appendix and will comply with all paragraphs as written, with exceptions taken only to those items indicated on the attached exception sheet.

_____________________________________________________
Offeror's SignatureDate

TYPED NAME:

COMPANY NAME:

ADDRESS:

PHONE:

FAX:

TPQ, Appendix C – Page 1 of 4

In-Checking Modular Office - Page 3 of TPQ, Appendix C - Page 4 of 4 image1.wmf

File details come from the government source that posted it. Updated .