This is a Questions and Answers document for federal contract opportunity FA8601-26-Q-0036, dated May 19, 2026. The document addresses a single clarification question regarding the use of subcontractors to meet project requirements.

The response clarifies that subcontractors may be used without limitation to satisfy high-level security clearance and Genetek requirements. However, both the prime contractor and any subcontractor must maintain Genetek certification. This guidance applies to contract FA8601-26-Q-0036 and establishes a key compliance requirement for bidders planning to use subcontracted support on this Air Force acquisition.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

FA8601-26-Q-0036

May 19, 2026

1. Could you please clarify if a subcontractor can be used to meet the high-level security clearance and Genetek requirements for this project?

a. There are no limitations on using a subcontractor. However, the contractor and subcontractor are required to be Genetek certified.