Questions and Answers 1 - DLA Furniture_11August25.pdf
PDF 1 MB Posted
- Attached to
- DLA Bldg 30207 (Area A) Furniture
- Solicitation number
- FA860125Q0064
About this file
This document is a Questions and Answers (Q&A) file for a Department of the Air Force furniture procurement solicitation (FA8601-25-Q-0064) for DLA Building 30207 Area A Furniture. The document contains 56 detailed questions and answers covering various aspects of the furniture installation, including specific requirements for workstations, panel configurations, power locations, shelving, door heights, and finish specifications. Key details include:
Procurement Specifics:
- Solicitation Number: FA8601-25-Q-0064
- Agency: Air Force Life Cycle Management Center (AFLCMC)
- Location: Wright-Patterson Air Force Base, Ohio
- Anticipated Start Date: October 15th
- Phased Implementation (Phases 1, 2, 3, and 5)
- Buy American Act compliance required
- Open market items allowed with no percentage limit
Technical Requirements:
- Modular system panels with specific technical requirements
- Multiple workstation typicals (E, F6, F7, H, H4.1, IT-1/IT-2)
- Specific furniture configurations with detailed specifications for worksurfaces, storage, overhead compartments, and power/communication infrastructure
- Custom logo implementation
- Specific finish requirements (veneer, HPL, laminate)
View the file
Other files
Show 40 more
Latest 50 of 130 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
AIR FORCE LIFE CYCLE MANAGEMENT CENTER (AFLCMC) WRIGHT-
PATTERSON AIR FORCE BASE OHIO
11 August 2025
FROM: AFLCMC/PZIBA
2275 D Street, Building 16, Room 128 Wright-Patterson AFB, OH 45433
SUBJECT: Response to Inquiries regarding FA8601-25-Q-0064, DLA Bldg 30207 Area A Furniture – Document 1
QUESTIONS
1. QUESTION: Are notches in the worksurfaces okay or are grommets required? Grommets will be placed in the HATs.
ANSWER: Yes, I can accept notches.
2. QUESTION: Spec Sheet calls out for each station “BBF Mobile with Cushion”. Confirming you mean BF Mobile with Cushion? BBF will not fit under the worksurfaces with a cushion.
ANSWER: Mobile BF is correct.
3. QUESTION: Are Metal Markerboard tiles acceptable instead of the exterior mounted marker boards?
ANSWER: Yes, as long as they are magnetic and whiteboard combination.
4. QUESTION: If the panel tiles are already tackable is an exterior mounted tackboard required?
ANSWER: No tackable panels are acceptable.
5. QUESTION: Is (1) 72” W Overhead with 2 doors acceptable V.S. (2) 36” W Overheads?
ANSWER: No, 2 please for flexibility.
6. QUESTION: In areas where there are (2) panels with frameless glass are we allowed to span a single piece across both panels?
ANSWER: No, again 2 please.
7. QUESTION: In Typical H, our wardrobe has only 1 fixed shelf, but I am able to add 3 adjustable shelves.
Is this acceptable?
ANSWER: Yes.
8. QUESTION: In Typical H4.1, would any support leg be accepted for the worksurfaces? Post or dual leg?
ANSWER: Prefer an Open Leg, but as long as the space has opening – acceptable.
9. QUESTION: In Typical IT-1 / IT-2, there is no call out for amount of receptacles. Panels are asked to be powered, and you have a power strip as part of the typical. How many receptacles and in what locations would you like them?
ANSWER: The standard per the MTR, MODULAR SYSTEM PANEL, Minimum Technical Requirements, Basis of Design - HAWORTH (Compose) or Equal, Panel Mounted Components, Laminate Worksurface with Vinyl Edge, Metal Storage, Locking Storage, Taper Pulls, Computer Accessories (monitor arms, power modules, keyboard pull out, etc). 3" Thick Welded Cold-Rolled Steel Stack Panel Frame, Stack Panel Permits Stacking Modules In-Field, STC Panel Rating -20, Metal to Metal Interlocking Panel Connectors, 3" Adjustment Range on Base Levelers, Combination of Interchangeable Segmented Tiles to Include: Acoustical Fabric/Tackable/Glass/WhiteBoard/Laminate/Open Tiles, Sliding and Hinge Door Available for 81" +/- Panel Height, Power and Non-Power Panels, Power/Communication Shielded Distribution, Capable of Running Max 30 Data Cables (horizontal and vertical), Power Panels to Include 3 Duplex Receptacles, 2 Knock-Out Voice Data Port Per Cubicle, Base/Ceiling Power Input, All Connectors, Finish Trim, Hardware and Supports for a Complete Install to be included for Full Installation. Furniture Contractor to Provide Certified Electrician to Make connections from Building Power to Modular Panels. See Plan for Panel Elevation and Power Input locations.
10. QUESTION: Could you provide some clarity on the power location of each typical? Does every panel truly need to be powered.
ANSWER: No, I will mark up the typicals with power to post later today.
11. QUESTION: Are the red dots on the floor plan marking power poles for the stations? Does each station get their own dedicated power?
ANSWER: No (printer is doing that -sorry), I will post the comm pole locations later today.
12. QUESTION: In Typical E the panel the door will be attached to has to be a full height with a fabric stack for the door to connect. Is this acceptable?
ANSWER: Will accept stack frame glass instead.
13. QUESTION: In Typical E an end panel is called out in the drawing but not in the spec. Is an End panel required? If yes, how do you want it to be attached?
ANSWER: I would like a small privacy space on end, even a modesty panel. I will add details to send out.
14. QUESTION: In Typical E again, the lower storage takes up most of the room again the panels. Only one panel outlet location will be open on the side RED. Can we put other outlets on the back area GREEN to meet the required 6?
ANSWER: I will mark this up and send later today.
15. QUESTION: Can we leave the existing Reception Desk? If so, will the exterior panels be replaced? What type of material should we specify? Please provide additional details.
ANSWER: See cutsheet 05b-CTS24-RF1-F30207 DLA New Furniture-2025tp079-NotOWF-rv1.pdf for clarification on the RF1 for the Reception Desk Refacing, this also shows the finishes.
16. QUESTION: Existing signage is on the doors. If signage is removed (we assume it’s taped) if removal damages the doors, do we need to sand and stain the entire door? A simple touch-up may be noticeable.
ANSWER: As for the signage repair, yes if the removal requires a full touch up – please match existing stain.
17. QUESTION: Power Locations on all Systems Furniture Typicals.
ANSWER: See the revised plan.
18. QUESTION: Details for Typical E, sliding door and H/A end panel.
ANSWER: See the revised cutsheet.
19. QUESTION: Plan with existing fans/power poles.
ANSWER: See the revised plan.
20. QUESTION: COMM pole plan.
ANSWER: See Revised plan.
21. QUESTION: Details on Moveable Wall.
ANSWER: Remove wall and track (noted on R1).
22. QUESTION: Will there be an Image File supplied for Custom Logo’s?
ANSWER: Yes, an Image File will be supplied for Custom Logo’s at award.
23. QUESTION: Elevator Interior Dimensions.
ANSWER: Couldn’t measure it is locked down and waiting for repair but stated fits a 40x48 skid and is 7’-0” tall.
24. QUESTION: Additional qty’s for certain typicals.
ANSWER: See revised cutsheets/SOW.
25. QUESTION: Adobe stock picture referenced in original cutsheet is discontinued.
ANSWER: Yes, this has been discontinued. Use Adobe Stock 194588220. Refer to new cutsheet AWP-3 revision.
26. QUESTION: Most of this spec will be specials due to non-standard selections and elevations. Can do all of this, but would let them know that this will add cost as opposed to standards. If they don’t want specials, see questions below.
ANSWER: Specials are acceptable to meet specified requirements and standard finishes for bidding purposes, final selection to happen upon award.
27. QUESTION: Are they ok with a 7’ door? That is our standard door height. This would be implemented across the entire wall so that the horizontal line where the glass starts is at 7’.
ANSWER: 7’0” height door is acceptable.
28. QUESTION: Standard whiteboards from Altos are 4’ H so they would go up to the glass and eliminate the laminate above it. Is this ok as well?
ANSWER: That is acceptable.
29. QUESTION: Frosting will have to be an aftermarket 3rd party installation. Confirm they are ok with that.
ANSWER: That is acceptable.
30. QUESTION: Arctic paint is discontinued, can do Anodized Aluminum or Platinum paint as closest available options. Please confirm with them. Link to standard finishes -https://assets.teknion.com/m/33915ac848f1f764/original/Architectural-Frame-Finishes-Sample-Card-.pdf.
ANSWER: Final selection to happen upon award.
31. QUESTION: Mercurial Walnut is non-standard Architectural walls fascia laminate. Here is link for standard options - https://d2r72yk5wmppdj.cloudfront.net/m/3556a74e095d1d00/-Laminate-Fascia---card.pdf.
ANSWER: Final selection to happen upon award.
32. QUESTION: What would be the ideal install date for this project? We know it’s phased, and such, however I was hoping for a date to plug into my notes.
ANSWER: Let’s assume an October 15th start date currently until solicitation is awarded.
33. QUESTION: Is the accordion partition between offices 212.01 & 212.02 remaining or to be removed?
ANSWER: Yes, to be removed, see note on plan revision sent after walk through.
34. QUESTION: The total qty. for CR2 cut sheet states 2, but the updated SOW qty. list states 8 for the total.
Is this a typo?
ANSWER: Apologize, qty 8 is correct.
35. QUESTION: Does the desk chair for the PO1 EXLL Qty. 2 need to priced out as separate Clin? There is not a cut sheet and it is not on the SOW Phase listing.
ANSWER: It should be included with the PO1 CLIN.
36. QUESTION: What percentage of the product is allowed to be open market items?
ANSWER: No limit.
37. QUESTION: Do the products need to follow the Buy American Act?
ANSWER: Yes.
38. QUESTION: Can you make the site walk thru attendee list public?
https://assets.teknion.com/m/33915ac848f1f764/original/Architectural-Frame-Finishes-Sample-Card-.pdf https://d2r72yk5wmppdj.cloudfront.net/m/3556a74e095d1d00/-Laminate-Fascia---card.pdf https://d2r72yk5wmppdj.cloudfront.net/m/3556a74e095d1d00/-Laminate-Fascia---card.pdf
ANSWER: No.
39. QUESTION: For the manufacturer that was rendered in typical P01 the height adjustable table only comes in a depth of 30”. Are you ok with a 30” depth vs. the 36” that was specified?
ANSWER: 36” is preferred but 30” is acceptable.
40. QUESTION: For PO1 can you clarify the finishes more, it has listed wood/veneer/laminate? Hutch = wood door? Open shelving veneer backer with wood shelf? Locker all wood? Are surfaces and fronts/sides all wood, or is veneer acceptable?
ANSWER: Veneer is acceptable in PO1.
41. QUESTION: In PO4 is lists the finishes as laminate, is HPL required?
ANSWER: Yes, HPL for all horizontal surfaces min.
42. QUESTION: In PO5 is lists the finishes as laminate, is HPL required?
ANSWER: Yes, HPL for all horizontal surfaces min.
43. QUESTION: Typical E seems to be missing from the updated cut sheets. Question answers stated you would be sending out notes on this typical? ANSWER: I reattached the typical E updated cutsheet again.
44. QUESTION: TYP F6 calls for 2 LED task lights, but only calls for one overhead. Is this a typo and you only want 1 LED task light?
ANSWER: Yes, only task light under the overhead.
45. QUESTION: Regarding Typicals that are placed against each other. These typicals do not have the same modularity of panels. Are we doubling up panels to keep the typical the same or being made to adjust the typical to make these fit?
ANSWER: You can double that run show below, please indicate on your return plan where you doubled.
46. QUESTION: I do not see a power location for TYP F7 by room 109?
ANSWER: Add next to column.
47. QUESTION: I do not see a power location for TYP E4 in Asset Management
ANSWER: Add against wall.
48. QUESTION: I do not see a power location for TYP F2 in Room 208. Will it just be a top feed like the rest?
ANSWER: Yes, all power whips should be ceiling feeds. Add against wall.
49. Unclear of what materials go where within the facility. A flooring drawing/diagram would be helpful to clarify.
ANSWER: Flooring finish plans for the carpet (05a-PLN03 Finishes,05a-PLN04 Finishes) and updated the cutsheet 05b-CTS85-FL1 in red to reference them.
50. In the Q&A dated 1 August 2025, Question 15’s answer stated that cutsheet 05b-CTS24-RF1-F30207 DLA New Furniture-2025tp079-NotOWF-rv1.pdf for clarification on the RF1 for the Reception Desk Refacing would be uploaded to Sam.gov. File name 05b-CTS24-RF1-F30207 DLA New Furniture- 2025tp079-NotOWF-rv1.pdf appears to be mistakenly named and is the cutsheet for Typ E Workstation.
Could you please provide the cutsheet for RFI that clarifies the Reception Desk Refacing?
ANSWER: I am attaching the cutsheet to this email. All finishes have been stated on the cutsheet with the elevation and plan showing locations.
51. On the July 29th update on CLIN 0015 of the solicitation 1449 cutsheet CR3 Credenza (small 36x24) is no longer reflective of the Statement of Work Matrix-
ANSWER: Current documents do match, CR3, CLIN 0015 in SOW and 1449 are all total of 4, please see attached.
52. As in the example of CLIN 0015 there are three sub-CLINS for Phase 1 – CLIN 0015AA (Qty 2), Phase 3
– CLIN 00015AC (Qty of 1), and Phase 5 – CLIN 0015AE (Qty 1). This is a total quantity of 4, instead of a total quantity of 8 that was noted in the SOW.
ANSWER: I have attached the SOW, 1449 and cutsheet available on SAM.gov since 29 July updates.
CLIN 15 is a total of 4 and is correctly marked on all sheets.
Note: CLIN 14 was updated and is now 8 and the SOW and 1449 reflect that change. Including a marked up cutsheet showing qty 8.
Phasing:
Phase 1 – qty 2 Phase 2 – qty 1 Phase 3 – qty 2 Phase 5 – qty 3 Total – qty 8
53. On the matrix in the SOW the total was increased, but none of the phase totals were.
ANSWER: There was some oversight by the customer when updating the SOW and the new totals. Please review the posted and attached solicitation for correct totals that do match totals in SOW. For proposal clarity the solicitation has the updates to phase totals that will guide you in your proposal by phases.
54. To further exemplify, specification CR-3 now has a new phase based on the floor plans that isn’t in the
1449 and part of the sub CLIN structure.
ANSWER: Please provide more detail for review, see question 52.
55. Our question, is an updated 1449 with all of the CLINs and SubCLINS forthcoming-
ANSWER: Not at this time, as the need for updates has not been provided.
56. And as there are only a few days left to make these corrections we would also ask for the deadline to be extended to August 25th.
ANSWER: No, the contracting officer has not determined an extension is required at this time.
CANDICE L. SNOW
Contracting Officer
AFLCMC/PZIBA
| 2025-08-11T13:02:40-0400 | |
| SNOW.CANDICE.LYNN.1423542060 |
File details come from the government source that posted it. Updated .