WPAFB Questions v4.pdf

PDF 216 KB Posted

Attached to
Base Refuse Federal contract opportunity
Solicitation number
FA860122R0021
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to Base Refuse, newest first.
File Type Posted
Solicitation Amendment FA860122R00210008 SF 30 (1).pdf PDF
WPAFB Questions v3.pdf PDF
Attachment 5- Pricing Bid Schedule FA8601-22-R-0021 Rev III.xlsx XLSX spreadsheet
WPAFB Questions.pdf PDF
Solicitation Amendment FA860122R00210007 SF 30.pdf PDF
Solicitation Amendment - FA860122R00210006.pdf PDF
Solicitation Amendment FA860122R00210006 SF 30.pdf PDF
RFI 29 Sept 2022.pdf PDF
Solicitation Amendment FA860122R00210005 SF 30 (1).pdf PDF
Attachment 2- 52-212-2 Addendum to Evaluation Factors.pdf PDF
Solicitation Amendment - FA860122R00210004.pdf PDF
Attachment 3- Performance Work Statement (PWS) REV 4.pdf PDF
Solicitation Amendment FA860122R00210004 SF 30.pdf PDF
RFI 22 Sept 2022.pdf PDF
Attachment 4- Wage Determination.pdf PDF
Solicitation Amendment FA860122R00210003 SF 30.pdf PDF
Attachment 2- 52-212-2 Addendum to Evaluation Factors.pdf PDF
Attachment 3 - Performance Work Statement (PWS) Rev 3.pdf PDF
Attachment 5 - Pricing Bid Schedule FA8601-22-R-0021 Rev II.xlsx XLSX spreadsheet
Solicitation Amendment - FA860122R00210003.pdf PDF
Attachment 1 - Instruction to Offerors.pdf PDF
Attachment 6 - Mission Essential Services Memo.pdf PDF
Solicitation Amendment FA860122R00210002 SF 30 (1).pdf PDF
FA860122R0021 10 June 2022 RFI Responses.xlsx XLSX spreadsheet
Attachment 3 - PWS Refuse 10 Jun 2022.pdf PDF
Response to Refuse RFIs - Consolidated.xlsx XLSX spreadsheet
Attachment 3 - PWS Refuse 31 May 2022 Revision.pdf PDF
Solicitation Amendment - FA860122R00210001.pdf PDF
Attachment 2 - 52-212-2 Addendum to Evaluation Factors 26 May 2022.pdf PDF
Solicitation Amendment FA860122R00210001 SF 30.pdf PDF
Solicitation Amendment FA860122R00210001 SF 30.pdf PDF
Attachment 3 - PWS Refuse Rev 2 23 May 2022.pdf PDF
Attachment 2 - 52-212-2 Addendum to Evaluation Factors.pdf PDF
Attachment 5 - Pricing Bid Schedule Base Refuse FA8601-22-R-0021.xlsx XLSX spreadsheet
Performance Work Statement.pdf PDF
Solicitation - FA860122R0021.pdf PDF
Attachment 1 - Instruction To Offerors.pdf PDF
Attachment 6 - Mission Essential Services Memo.pdf PDF
Attachment 4 - Wage Determination.pdf PDF
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI Responses 5 Oct 2022

1. PWS 1.3.1 Sanitary Disposal Fees – CE, Med. Cntr., AF Museum

CLIN xx11 has listed 5,990 tons for sanitary Disposal Fees and Appendix A, Table 1 lists 2,946 tons for Industrial Solid Waste.

a. What work in the PWS does the 2,946 tons specifically represent? Industrial Solid Waste Are the 2,946 tons in addition to or part of the 5,990 tons estimated on CLIN xx11? Part of the total estimates. Again, With WPAB Covid stance we cannot go by these numbers and that this is why we have those CLINS marked with an * which is detailed as "The quantities of all CLINs marked with an * are estimates based off of historical data. These are estimates.

b. If the 2,946 are part of the total 5,990, what work accounts for the difference of 3,044 tons? Again, With WPAB Covid stance we cannot go by these numbers and that this is why we have those CLINS marked with an * which is detailed as "The quantities of all CLINs marked with an * are estimates based off of historical data. These are estimates.

2. CLIN xx12 and CLIN xx13

These CLIN lines are for Generation Fees for Greene and Montgomery County. The estimates for both CLINs equals 6,571 tons. However, the total number of Sanitary Disposal Fees tons in CLIN xx11 is 5,990. Where are the 581 additional tons accounted for in the PWS? Again, With WPAB Covid stance we cannot go by these numbers and that this is why we have those CLINS marked with an * which is detailed as "The quantities of all CLINs marked with an * are estimates based off of historical data. These are estimates.

3. Attachment 2 – 52-212-2 Addendum to Evaluation Factors

Subfactor 1 references providing a sample of reports required by Appendix D. However, there is no Appendix D posted and this section is marked as “RESERVED. Will the Government supply Appendix D to provide bidders with a reference for the sample reports required by this evaluation factor? Should Read - Measure of Merit: An acceptable rating is met when the offeror's proposal has provided a detailed method of inspections including frequency and corrective action and describe a methodology to mitigate future defects. Proposal shall demonstrate an adequate understanding of the PWS requirements, scope of the operation, and the ability to maintain records, and demonstrate their knowledge by providing a sample record, and a sample report IAW PWS Section 2.1.

4. Please reference the posting of 29 Sept 2020 relating to new questions and government responses. According to our understanding of the PWS, the disposal related to tipping fees and generation fees are all reimbursable. Can you please confirm this? If this is correct, why is there a need for the contractor to insert pricing for those unit prices? It seems a contractor could simply insert $1.00 for each of these, in order to keep the total cost low, since the government will be required to reimburse according to invoice dollar values.

The potential offeror is responsible for bidding appropriate numbers based on all fees associated with refuse removal to include but not limited to price per ton, generation fee, EPA fees, labor etc.

The government doesn’t know what the counties will charge potential offerors on these fees and cannot tell the potential offeror how to bid.

5. Please reference Attachment 5, Pricing Bid Schedule (Excel). The 6-month extension for CLINS

5009 and 5010 does not appear to be in concert with the Seasonal months noted. Since this extended period will cover March through August, this will cover only 1 month of the Winter season and 5 months of the Summer season. Should the unit quantities be adjusted for those two line items?

Depending on when the contract is awarded. It could be 2 months of winter and 4 months of summer.

It will be adjusted accordingly when awarded.

6. Please reference CLIN 5005, relating to Monthly Rental of the Wheeled -Curbside Recycling Toters. The quantity listed is 12. Should this be adjusted to 6 months, which is the length of the 6-month extension?

Yes, this should be 6 months. (Error on Excel doc.)

7. Consider the fact that the quantity of 788 on that line remains unchanged from the solicitation posted in 2017. If the Government won’t provide historical data for COVID years, then we ask that the following is provided:

How many hauls were performed out of the 788 estimated during the base year of the current contract (2017)?

How many hauls were performed out of the 788 estimated for Option Year 1 of the current contract (2018)?

Data reports from 2017 to today and the average of 788 is a good average. Saying that, we had some months that were above average and some below average, but the yearly average remains good. Also WPAFB can at anytime can declare a state of emergency, or during an act of war etc. have an increased amount of refuse.

8. Please reference Attachment 5 - Pricing Bid Schedule FA8601-22-R-0021, Rev ll. Concerning the 6-

Month Extension, should the contractor use the exact unit prices used in the 4th Option Year?

Since the quantities are not exactly 50% of the quantities used in the 4th Option Year, the 6- Month Option extended totals will not equate to exactly 50% of the extended totals of the 4th Option Year which is noted in Attachment 02, Addendum 52-212-2 - Evaluation Factors for Award, Section 3.a.(4)ii. Please clarify.

The quantity estimates are provided in the bid schedule. Per FAR 52.217-8, the previous years rates are to be used to determine the price.

9. Since Attachment 5 - Pricing Bid Schedule, requires pricing entries to include the 6-Month Option, should the extension of the 1449 contain fill in priding blocks for the 6-Month Option fees? It does not appear to do so.

No. The only options to be included in the SF 1449 are option years that the government intends to exercise (OY1-OY4). OY5 is for the option to extend services should the government find it necessary to extend services due to unforeseeable events. However, this option will not be included in the award of the contract rather it is covered by FAR 52.217-8

10. The government amendment posting for 3 Oct 2022 indicates many disposal related fees, including those in line items x011, x012, x013, x014, x016, and x018, will now need to be priced by the contractor.

Throughout the PWS it states these fees will be reimbursable.

Examples:

PWS 1.1.1.4

The contractor shall be responsible for any permit or fees associated with the use of off-base disposal locations and invoice for reimbursement.

PWS 1.1.9.2

The Contractor shall be reimbursed for tipping fees according to submitted invoices.

PWS 1.1.1.5

PWS 1.1.3.2

disposal location and invoice for reimbursement

PWS 1.1.3.5

In all of these cases, we understood this to mean we would pay the all associated landfill fees and submit the invoices to the government for a direct reimbursement at exactly the totals of the invoices. This would factor out disposal fees and basically they would amount to a "pass through" to the government.

Since the generation fees, and other fees relating to disposal are included in the landfill invoice, we assumed these fees are all inclusive for reimbursement. If they are not reimbursable, we will need to obtain pricing from landfills for items relating to these, including recycle processing fees for the MFH.

This is a Firm Fixed Price effort, meaning there are no cost reimbursable CLINs. To clarify on this matter – the fees in these specific CLINs will be reimbursed, however it is the responsibility of the bidder to obtain those fees for the purpose of pricing. Per the bid schedule, the estimates have been provided and each referenced CLIN contains a section for “unit price” in which indicates that the “unit price” and total price must be determined by the offeror. These specific CLINs are also noted by the asterisks which indicate that these are estimates and future contract modifications may occur due to increases/decreases to these estimates. Additionally, the government understands that these fees may change over time due to inflation, etc. and should the fee increase/decrease, the contract will be modified to adjust as needed. As a result, when the invoices are submitted, the “reimbursement” will be reflected at the contract fixed price.

This is still not clear to us. “the fees in these specific CLINs will be reimbursed, however it is the responsibility of the bidder to obtain those fees for the purpose of pricing” Here is our concern, for example:

• Our C & D Roll Off load weighs 2.00 tons.

• The disposal site charges us ($60.00 tipping and $4.75 EPA fee) for a total of $64.75 per ton for C & D Tipping Fees. This amounts to a total of $129.50.

• The disposal site also has a 3.00 ton minimal load fee and charges us an additional 1.00 ton to meet the minimal, which adds more cost. (example only)

• The landfill surcharges us another $200.00 in other fees (minimal tons per load fee, or dig out fee if the load gets stuck in the container and has to be dug out at the disposal site).

• Of course, the generation fee is invoiced on another line item.

• The landfill invoice is now totaling $129.50, plus an additional $60.00 (for the additional ton to meet the minimal 3 tons) plus $200.00 to dig out a jammed load, for a total invoice of $389.50.

1. If we bid $64.75 per ton for this line item, what is the amount the government will reimburse, or pay us for the disposal of this load? Will the government actually reimburse us for all fees excluding the generation fee which will be invoiced on a different CLIN? Please Clarify.

2. What if we bid only $54.75 per ton on this line item, which is $10.00 per ton less than the disposal facility’s tipping and EPA fee, will the government pay us at the $54.75 per ton per our unit price bid, or will we be paid at the landfill’s standard rate of $64.75 for tipping and EPA fee, per the total landfill invoice?

3. If we bid $70.00 per ton for this line item, will we be compensated/paid using the $70.00 rate, or the landfill’s lower fee of $64.75 per tons (tipping and EPA fee)?

Offerors need to research what all of the fees will be, so that they can include them in their calculation of costs and in their offered price. Again, per the bid schedule note, the quantity provided is an estimate and may be adjusted as needed. However, offerors must research the fee to determine the price in their offer. Additionally, per the PWS, tickets must be provided which reflect the tonnage and the fee in which the offeror will be reimbursed. If a landfill fee is $64.75, this will be reflected on the ticket and will be reimbursed. The dig out fee would depend on the equipment. If a contractor’s equipment is jammed, this would be the responsibly of the contractor.