Attachment 4 - Bid Sheet.xlsx

XLSX spreadsheet 44 KB Posted

Attached to
Base-wide Flooring at WPAFB Federal contract opportunity
Solicitation number
FA860121R0014
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to Base-wide Flooring at WPAFB, newest first.
File Type Posted
Attachment 7 - Question and Answer.docx DOCX document
Attachment 7 - Question and Answer.docx DOCX document
Attachment 7 - Question and Answer.docx DOCX document
Attachment 7 - Question and Answer.docx DOCX document
Attachment 7 - Question and Answer.docx DOCX document
Attachment 7 - Question and Answer.docx DOCX document
Attachment 7 - Question and Answer.docx DOCX document
Attachment 4 - Bid Sheet.xlsx XLSX spreadsheet
Attachment 6 - Solicitation FA860121R0014.pdf PDF
Attachment 2 - Instructions To Offerors.pdf PDF
Attachment 3 - 52.212-2 Addendum to Evaluation Factors.pdf PDF
Attachment 5 - USAF Carpet Program Ordering Guide.pdf PDF
Attachment 1 - Statement of Work (SOW).pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AFICA Year One Price Estimat

Item NumberProduct or Service DescriptionUnit of MeasureEstimated QuantityPrice per UnitTotal Evaluated Price
Porcelain Tile Descriptions
1-DQDemo Existing Porcelain / Ceramic TileSF2,020$ - 0
1-DRInstall New Porcelain /Ceramic Tile ( Includes Thinset & Grout_ Non Epoxy)SF2,630$ - 0
1-DSInstall New Porcelain/ Ceramic BaseLF373$ - 0
1-DTDemo Existing Porcelain /Ceramic BaseLF65$ - 0
1-DUDaltile Porcelain Tile- Veranda or Iron CraftLF390$ - 0
1-DWPorcelain / Ceramic Accessories ( Schluter _ Includes Installation)LF60$ - 0
Resilient Flooring.
1-BResilient flooring and accessories, prices shall include delivery, setup, equipment and installation, including adhesive costs.
1-BANew 4" Rubber Base (includes removal of existing base)LF30,000$ - 0
1-BBNew 6" Rubber Base (includes removal of existing base)LF500$ - 0
1-BCVinyl Composition Tile 3 Tone Highlights & Shadows 12" x 12"SF750$ - 0
1-BDVinyl Composition Tile Contemporary 12" x 24"SF250$ - 0
1-BEStatic Dissipative TileSF200$ - 0
1-BFLuxury Vilny Tile Type I -SF1,000$ - 0
1-BGLuxury Vilny Tile Type 2 - Textured SurfaceSF1,000$ - 0
1-BHSheet Vinyl Heat-weld Monolithic Visual with Border (minimum 40 SF)SF100$ - 0
1-BISheet Vinyl Heat-weld Monolithic Visual (minimum 40 SF)SF100$ - 0
1-BJHammered Textured Rubber Flooring (minimum 40 SF)SF1,000$ - 0
1-BKHammered Textured Stair Tread and RisersLF300$ - 0
1-BLStair StringerLF50$ - 0
1-BM1/2" Vinyl Reducer StripLF1,000$ - 0
1-BNRubber Stair Nosing, Full Width of TreadLF100$ - 0
Removal
1-CRemoval prices shall include all transportation, setup, labor, material and equipment, necessary to accomplish removals
1-CARemoval and Disposal of Carpet & Floor Tile Containing AsbestosSF250$ - 0
1-CBRemoval and Disposal of Asbestos Floor TileSF300$ - 0
1-CCRemoval and Disposal of Asbestos MasticSF230$ - 0
1-CDRemove Old AdhesiveSF100$ - 0
1-CERemoval of Vinyl Composition Tile, to include Remaining AdhesiveSF200$ - 0
1-CFRemove Rubber Tile or Flooring to include Remaining AdhesiveSF200$ - 0
1-CGRemove Rubber Stair Tread and Riser, to include Remaining AdhesiveLF300$ - 0
1-CHRemove Rubber Stair Stringer, to include Remaining AdhesiveLF80$ - 0
1-CJRemove Sheet Vinyl, to include Remaining AdhesiveSF100$ - 0
1-CKRemove Glued Jute-back Broadloom CarpetSY5,350$ - 0
1-CLRemove Rubber-backed Carpet TileSY15,150$ - 0
1-CMRemove Carpet on StairsSY10$ - 0
1-CNCut Wood Doors (Max. 4' 6" Width)EA3$ - 0
1-CPRefill Bottom Rail on DoorEA1$ - 0
1-CQCut Metal Door (Max. 4' 6" Width)EA1$ - 0
Installation Descriptions
1-DInstallation prices shall include all transportation, setup, labor, material and equipment, necessary to accomplish installation
1-DAPrime Floor SurfaceSY50$ - 0
1-DBPrep of Unlevel Floor, including 1 Scratch Coat & 1 Skim CoatSY100$ - 0
1-DCSpot Prep/Repair FloorHR380$ - 0
1-DDInstall Broadloom CarpetSY500$ - 0
1-DEInstall Broadloom Carpet on StairsSY20$ - 0
1-DFInstall Carpet TileSY16,700$ - 0
1-DGInstall Border CarpetLF50$ - 0
1-DHMiscellaneous Labor: Repair/Reglue Carpet, Install User Provided MaterialsHR15$ - 0
1-DJInfection Control Type IISF500$ - 0
1-DKLift Modular Furniture/wall PanelsSY10,000$ - 0
1-DLMove Furniture and Portable PartitionsSY6,000$ - 0
1-DMLabor Increase to Work Evening/Night HoursHR100$ - 0
1-DNLabor Increase to Work Saturday and/or SundayHR80$ - 0
1-DPLabor Increase to Work HolidaysHR8$ - 0
1-DXMaterial FreightLS94,440$ - 0
$ - 0

&"Arial,Bold"EXHIBIT A

PRICE LIST OF FLOORING

1 DECEMBER 2021 - 1 DECEMBER 2022

FA8601-11-D-0008 Page &P of &N Updated: 22- Jan 2020

AFICA Year Two Price Estimate

Item NumberProduct or Service DescriptionUnit of MeasureEstimated QuantityPrice per UnitTotal Evaluated Price
Porcelain Tile Descriptions
2-DQDemo Existing Porcelain / Ceramic TileSF2,020$ - 0
2-DRInstall New Porcelain /Ceramic Tile ( Includes Thinset & Grout_ Non Epoxy)SF2,630$ - 0
2-DSInstall New Porcelain/ Ceramic BaseLF373$ - 0
2-DTDemo Existing Porcelain /Ceramic BaseLF65$ - 0
2-DUDaltile Porcelain Tile- Veranda or Iron CraftLF390$ - 0
2-DWPorcelain / Ceramic Accessories ( Schluter _ Includes Installation)LF60$ - 0
Resilient Flooring.
Resilient flooring and accessories, prices shall include delivery, setup, equipment and installation, including adhesive costs.
2-BNew 4" Rubber Base (includes removal of existing base)LF30,000$ - 0
2-BANew 6" Rubber Base (includes removal of existing base)LF500$ - 0
2-BBVinyl Composition Tile 3 Tone Highlights & Shadows 12" x 12"SF750$ - 0
2-BCVinyl Composition Tile Contemporary 12" x 24"SF250$ - 0
2-BDStatic Dissipative TileSF200$ - 0
2-BELuxury Vilny Tile Type I -SF1,000$ - 0
2-BFLuxury Vilny Tile Type 2 - Textured SurfaceSF1,000$ - 0
2-BGSheet Vinyl Heat-weld Monolithic Visual with Border (minimum 40 SF)SF100$ - 0
2-BHSheet Vinyl Heat-weld Monolithic Visual (minimum 40 SF)SF100$ - 0
2-BKHammered Textured Rubber Flooring (minimum 40 SF)SF500$ - 0
2-BLHammered Textured Stair Tread and RisersLF150$ - 0
2-BMStair StringerLF50$ - 0
2-BN1/2" Vinyl Reducer StripLF1,000$ - 0
2-BNRubber Stair Nosing, Full Width of TreadLF100$ - 0
Removal
2-CRemoval prices shall include all transportation, setup, labor, material and equipment, necessary to accomplish removals
2-CARemoval and Disposal of Carpet & Floor Tile Containing AsbestosSF250$ - 0
2-CBRemoval and Disposal of Asbestos Floor TileSF300$ - 0
2-CCRemoval and Disposal of Asbestos MasticSF230$ - 0
2-CDRemove Old AdhesiveSF100$ - 0
2-CERemoval of Vinyl Composition Tile, to include Remaining AdhesiveSF200$ - 0
2-CFRemove Rubber Tile or Flooring to include Remaining AdhesiveSF200$ - 0
2-CGRemove Rubber Stair Tread and Riser, to include Remaining AdhesiveLF300$ - 0
2-CHRemove Rubber Stair Stringer, to include Remaining AdhesiveLF80$ - 0
2-CJRemove Sheet Vinyl, to include Remaining AdhesiveSF100$ - 0
2-CKRemove Glued Jute-back Broadloom CarpetSY5,350$ - 0
2-CLRemove Rubber-backed Carpet TileSY15,150$ - 0
2-CMRemove Carpet on StairsSY10$ - 0
2-CNCut Wood Doors (Max. 4' 6" Width)EA3$ - 0
2-CPRefill Bottom Rail on DoorEA1$ - 0
2-CQCut Metal Door (Max. 4' 6" Width)EA1$ - 0
Installation Descriptions
2-DInstallation prices shall include all transportation, setup, labor, material and equipment, necessary to accomplish installation
2-DAPrime Floor SurfaceSY50$ - 0
2-DBPrep of Unlevel Floor, including 1 Scratch Coat & 1 Skim CoatSY100$ - 0
2-DCSpot Prep/Repair FloorHR380$ - 0
2-DDInstall Broadloom CarpetSY500$ - 0
2-DEInstall Broadloom Carpet on StairsSY20$ - 0
2-DFInstall Carpet TileSY16,700$ - 0
2-DGInstall Border CarpetLF50$ - 0
2-DHMiscellaneous Labor: Repair/Reglue Carpet, Install User Provided MaterialsHR15$ - 0
2-DJInfection Control Type IISF500$ - 0
2-DKLift Modular Furniture/wall PanelsSY10,000$ - 0
2-DLMove Furniture and Portable PartitionsSY6,000$ - 0
2-DMLabor Increase to Work Evening/Night HoursHR100$ - 0
2-DNLabor Increase to Work Saturday and/or SundayHR80$ - 0
2-DPLabor Increase to Work HolidaysHR8$ - 0
2-DXMaterial FreightLS94,440$ - 0
$ - 0

1 DECEMBER 2022 - 1 DECEMBER 2023

FA8601-11-D-0008 Page &P of &N Updated: 22- Jan 2020

AFICA Year Three Price Estimate

Item NumberProduct or Service DescriptionUnit of MeasureEstimated QuantityPrice per UnitTotal Evaluated Price
Porcelain Tile Descriptions
3-DQDemo Existing Porcelain / Ceramic TileSF2,020$ - 0
3-DRInstall New Porcelain /Ceramic Tile ( Includes Thinset & Grout_ Non Epoxy)SF2,630$ - 0
3-DSInstall New Porcelain/ Ceramic BaseLF373$ - 0
3-DTDemo Existing Porcelain /Ceramic BaseLF65$ - 0
3-DUDaltile Porcelain Tile- Veranda or Iron CraftLF390$ - 0
3-DWPorcelain / Ceramic Accessories ( Schluter _ Includes Installation)LF60$ - 0
Resilient Flooring.
Resilient flooring and accessories, prices shall include delivery, setup, equipment and installation, including adhesive costs.
3-BNew 4" Rubber Base (includes removal of existing base)LF30,000$ - 0
3-BANew 6" Rubber Base (includes removal of existing base)LF500$ - 0
3-BBVinyl Composition Tile 3 Tone Highlights & Shadows 12" x 12"SF750$ - 0
3-BCVinyl Composition Tile Contemporary 12" x 24"SF250$ - 0
3-BDStatic Dissipative TileSF200$ - 0
3-BELuxury Vilny Tile Type I -SF1,000$ - 0
3-BFLuxury Vilny Tile Type 2 - Textured SurfaceSF1,000$ - 0
3-BGSheet Vinyl Heat-weld Monolithic Visual with Border (minimum 40 SF)SF100$ - 0
3-BHSheet Vinyl Heat-weld Monolithic Visual (minimum 40 SF)SF100$ - 0
3-BKHammered Textured Rubber Flooring (minimum 40 SF)SF1,000$ - 0
3-BLHammered Textured Stair Tread and RisersLF300$ - 0
3-BMStair StringerLF50$ - 0
3-BN1/2" Vinyl Reducer StripLF1,000$ - 0
3-BNRubber Stair Nosing, Full Width of TreadLF100$ - 0
Removal
3-CRemoval prices shall include all transportation, setup, labor, material and equipment, necessary to accomplish removals
3-CARemoval and Disposal of Carpet & Floor Tile Containing AsbestosSF250$ - 0
3-CBRemoval and Disposal of Asbestos Floor TileSF300$ - 0
3-CCRemoval and Disposal of Asbestos MasticSF230$ - 0
3-CDRemove Old AdhesiveSF100$ - 0
3-CERemoval of Vinyl Composition Tile, to include Remaining AdhesiveSF200$ - 0
3-CFRemove Rubber Tile or Flooring to include Remaining AdhesiveSF200$ - 0
3-CGRemove Rubber Stair Tread and Riser, to include Remaining AdhesiveLF300$ - 0
3-CHRemove Rubber Stair Stringer, to include Remaining AdhesiveLF80$ - 0
3-CJRemove Sheet Vinyl, to include Remaining AdhesiveSF100$ - 0
3-CKRemove Glued Jute-back Broadloom CarpetSY5,350$ - 0
3-CLRemove Rubber-backed Carpet TileSY15,150$ - 0
3-CMRemove Carpet on StairsSY10$ - 0
3-CNCut Wood Doors (Max. 4' 6" Width)EA3$ - 0
3-CPRefill Bottom Rail on DoorEA1$ - 0
3-CQCut Metal Door (Max. 4' 6" Width)EA1$ - 0
Installation Descriptions
3-DInstallation prices shall include all transportation, setup, labor, material and equipment, necessary to accomplish installation
3-DAPrime Floor SurfaceSY50$ - 0
3-DBPrep of Unlevel Floor, including 1 Scratch Coat & 1 Skim CoatSY100$ - 0
3-DCSpot Prep/Repair FloorHR380$ - 0
3-DDInstall Broadloom CarpetSY500$ - 0
3-DEInstall Broadloom Carpet on StairsSY20$ - 0
3-DFInstall Carpet TileSY16,700$ - 0
3-DGInstall Border CarpetLF50$ - 0
3-DHMiscellaneous Labor: Repair/Reglue Carpet, Install User Provided MaterialsHR15$ - 0
3-DJInfection Control Type IISF500$ - 0
3-DKLift Modular Furniture/wall PanelsSY10,000$ - 0
3-DLMove Furniture and Portable PartitionsSY6,000$ - 0
3-DMLabor Increase to Work Evening/Night HoursHR100$ - 0
3-DNLabor Increase to Work Saturday and/or SundayHR80$ - 0
3-DPLabor Increase to Work HolidaysHR8$ - 0
3-DXMaterial FreightLS94,440$ - 0
$ - 0

1 DECEMBER 2023 - 1 DECEMBER 2024

FA8601-11-D-0008 Page &P of &N Updated: 22- Jan 2020

AFICA Year Four Price Esti

Item NumberProduct or Service DescriptionUnit of MeasureEstimated QuantityPrice per UnitTotal Evaluated Price
Porcelain Tile Descriptions
4-DQDemo Existing Porcelain / Ceramic TileSF2,020$ - 0
4-DRInstall New Porcelain /Ceramic Tile ( Includes Thinset & Grout_ Non Epoxy)SF2,630$ - 0
4-DSInstall New Porcelain/ Ceramic BaseLF373$ - 0
4-DTDemo Existing Porcelain /Ceramic BaseLF65$ - 0
4-DUDaltile Porcelain Tile- Veranda or Iron CraftLF390$ - 0
4-DWPorcelain / Ceramic Accessories ( Schluter _ Includes Installation)LF60$ - 0
Resilient Flooring.
Resilient flooring and accessories, prices shall include delivery, setup, equipment and installation, including adhesive costs.
4-BNew 4" Rubber Base (includes removal of existing base)LF30,000$ - 0
4-BANew 6" Rubber Base (includes removal of existing base)LF500$ - 0
4-BBVinyl Composition Tile 3 Tone Highlights & Shadows 12" x 12"SF750$ - 0
4-BCVinyl Composition Tile Contemporary 12" x 24"SF250$ - 0
4-BDStatic Dissipative TileSF200$ - 0
4-BELuxury Vilny Tile Type I -SF1,000$ - 0
4-BFLuxury Vilny Tile Type 2 - Textured SurfaceSF1,000$ - 0
4-BGSheet Vinyl Heat-weld Monolithic Visual with Border (minimum 40 SF)SF100$ - 0
4-BHSheet Vinyl Heat-weld Monolithic Visual (minimum 40 SF)SF100$ - 0
4-BKHammered Textured Rubber Flooring (minimum 40 SF)SF500$ - 0
4-BLHammered Textured Stair Tread and RisersLF150$ - 0
4-BMStair StringerLF50$ - 0
4-BN1/2" Vinyl Reducer StripLF1,000$ - 0
4-BNRubber Stair Nosing, Full Width of TreadLF100$ - 0
Removal
4-CRemoval prices shall include all transportation, setup, labor, material and equipment, necessary to accomplish removals
4-CARemoval and Disposal of Carpet & Floor Tile Containing AsbestosSF250$ - 0
4-CBRemoval and Disposal of Asbestos Floor TileSF300$ - 0
4-CCRemoval and Disposal of Asbestos MasticSF230$ - 0
4-CDRemove Old AdhesiveSF100$ - 0
4-CERemoval of Vinyl Composition Tile, to include Remaining AdhesiveSF200$ - 0
4-CFRemove Rubber Tile or Flooring to include Remaining AdhesiveSF200$ - 0
4-CGRemove Rubber Stair Tread and Riser, to include Remaining AdhesiveLF300$ - 0
4-CHRemove Rubber Stair Stringer, to include Remaining AdhesiveLF80$ - 0
4-CJRemove Sheet Vinyl, to include Remaining AdhesiveSF100$ - 0
4-CKRemove Glued Jute-back Broadloom CarpetSY5,350$ - 0
4-CLRemove Rubber-backed Carpet TileSY15,150$ - 0
4-CMRemove Carpet on StairsSY10$ - 0
4-CNCut Wood Doors (Max. 4' 6" Width)EA3$ - 0
4-CPRefill Bottom Rail on DoorEA1$ - 0
4-CQCut Metal Door (Max. 4' 6" Width)EA1$ - 0
Installation Descriptions
4-DInstallation prices shall include all transportation, setup, labor, material and equipment, necessary to accomplish installation
4-DAPrime Floor SurfaceSY50$ - 0
4-DBPrep of Unlevel Floor, including 1 Scratch Coat & 1 Skim CoatSY100$ - 0
4-DCSpot Prep/Repair FloorHR380$ - 0
4-DDInstall Broadloom CarpetSY500$ - 0
4-DEInstall Broadloom Carpet on StairsSY20$ - 0
4-DFInstall Carpet TileSY16,700$ - 0
4-DGInstall Border CarpetLF50$ - 0
4-DHMiscellaneous Labor: Repair/Reglue Carpet, Install User Provided MaterialsHR15$ - 0
4-DJInfection Control Type IISF500$ - 0
4-DKLift Modular Furniture/wall PanelsSY10,000$ - 0
4-DLMove Furniture and Portable PartitionsSY6,000$ - 0
4-DMLabor Increase to Work Evening/Night HoursHR100$ - 0
4-DNLabor Increase to Work Saturday and/or SundayHR80$ - 0
4-DPLabor Increase to Work HolidaysHR8$ - 0
4-DXMaterial FreightLS94,440$ - 0
$ - 0

1 DECEMBER 2024 - 1 DECEMBER 2025

FA8601-11-D-0008 Page &P of &N Updated: 22- Jan 2020

AFICA Year Five Price

Item NumberProduct or Service DescriptionUnit of MeasureEstimated QuantityPrice per UnitTotal Evaluated Price
Porcelain Tile Descriptions
5-DQDemo Existing Porcelain / Ceramic TileSF2,020$ - 0
5-DRInstall New Porcelain /Ceramic Tile ( Includes Thinset & Grout_ Non Epoxy)SF2,630$ - 0
5-DSInstall New Porcelain/ Ceramic BaseLF373$ - 0
5-DTDemo Existing Porcelain /Ceramic BaseLF65$ - 0
5-DUDaltile Porcelain Tile- Veranda or Iron CraftLF390$ - 0
5-DWPorcelain / Ceramic Accessories ( Schluter _ Includes Installation)LF60$ - 0
Resilient Flooring.
Resilient flooring and accessories, prices shall include delivery, setup, equipment and installation, including adhesive costs.
5-BNew 4" Rubber Base (includes removal of existing base)LF30,000$ - 0
5-BANew 6" Rubber Base (includes removal of existing base)LF500$ - 0
5-BBVinyl Composition Tile 3 Tone Highlights & Shadows 12" x 12"SF750$ - 0
5-BCVinyl Composition Tile Contemporary 12" x 24"SF250$ - 0
5-BDStatic Dissipative TileSF200$ - 0
5-BELuxury Vilny Tile Type I -SF1,000$ - 0
5-BFLuxury Vilny Tile Type 2 - Textured SurfaceSF1,000$ - 0
5-BGSheet Vinyl Heat-weld Monolithic Visual with Border (minimum 40 SF)SF100$ - 0
5-BHSheet Vinyl Heat-weld Monolithic Visual (minimum 40 SF)SF100$ - 0
5-BKHammered Textured Rubber Flooring (minimum 40 SF)SF500$ - 0
5-BLHammered Textured Stair Tread and RisersLF150$ - 0
5-BMStair StringerLF50$ - 0
5-BN1/2" Vinyl Reducer StripLF1,000$ - 0
5-BNRubber Stair Nosing, Full Width of TreadLF100$ - 0
Removal
5-CRemoval prices shall include all transportation, setup, labor, material and equipment, necessary to accomplish removals
5-CARemoval and Disposal of Carpet & Floor Tile Containing AsbestosSF250$ - 0
5-CBRemoval and Disposal of Asbestos Floor TileSF300$ - 0
5-CCRemoval and Disposal of Asbestos MasticSF230$ - 0
5-CDRemove Old AdhesiveSF100$ - 0
5-CERemoval of Vinyl Composition Tile, to include Remaining AdhesiveSF200$ - 0
5-CFRemove Rubber Tile or Flooring to include Remaining AdhesiveSF200$ - 0
5-CGRemove Rubber Stair Tread and Riser, to include Remaining AdhesiveLF300$ - 0
5-CHRemove Rubber Stair Stringer, to include Remaining AdhesiveLF80$ - 0
5-CJRemove Sheet Vinyl, to include Remaining AdhesiveSF100$ - 0
5-CKRemove Glued Jute-back Broadloom CarpetSY5,350$ - 0
5-CLRemove Rubber-backed Carpet TileSY15,150$ - 0
5-CMRemove Carpet on StairsSY10$ - 0
5-CNCut Wood Doors (Max. 4' 6" Width)EA3$ - 0
5-CPRefill Bottom Rail on DoorEA1$ - 0
5-CQCut Metal Door (Max. 4' 6" Width)EA1$ - 0
Installation Descriptions
5-DInstallation prices shall include all transportation, setup, labor, material and equipment, necessary to accomplish installation
5-DAPrime Floor SurfaceSY50$ - 0
5-DBPrep of Unlevel Floor, including 1 Scratch Coat & 1 Skim CoatSY100$ - 0
5-DCSpot Prep/Repair FloorHR380$ - 0
5-DDInstall Broadloom CarpetSY500$ - 0
5-DEInstall Broadloom Carpet on StairsSY20$ - 0
5-DFInstall Carpet TileSY16,700$ - 0
5-DGInstall Border CarpetLF50$ - 0
5-DHMiscellaneous Labor: Repair/Reglue Carpet, Install User Provided MaterialsHR15$ - 0
5-DJInfection Control Type IISF500$ - 0
5-DKLift Modular Furniture/wall PanelsSY10,000$ - 0
5-DLMove Furniture and Portable PartitionsSY6,000$ - 0
5-DMLabor Increase to Work Evening/Night HoursHR100$ - 0
5-DNLabor Increase to Work Saturday and/or SundayHR80$ - 0
5-DPLabor Increase to Work HolidaysHR8$ - 0
5-DXMaterial FreightLS94,440$ - 0
$ - 0

1 DECEMBER 2025 - 1 DECEMBER 2026

FA8601-11-D-0008 Page &P of &N Updated: 22- Jan 2020

AFICA Yearly Totals Year Total

10.00
20.00
30.00
40.00
50.00
Total$0.00

11 March 2020

FA8601-11-D-0008 Page &P of &N Updated: 22- Jan 2020