Pre-Proposal RFI 1 Responses.pdf

PDF 142 KB Posted

Attached to
Maintain Finishes, Facility 34010 Federal contract opportunity
Solicitation number
FA8601-11-B-0005
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

About this file

Request for Information (RFI) 1

View the file

Other files for this federal contract opportunity

Other files attached to Maintain Finishes, Facility 34010, newest first.
File Type Posted
Pre-Proposal RFI 4.pdf PDF
Pre-Proposal RFI 1 Updated response.pdf PDF
Pre-Proposal RFI 3.pdf PDF
Pre-Proposal RFI 2 Response .pdf PDF
Wage Decision OH29 4 Aug 11.pdf PDF
Amendment 0001.pdf PDF
I-001 ADDENDUM NO-1.pdf PDF
FFP Addendum 1.pdf PDF
I-100 ADDENDUM NO-1.pdf PDF
01 02 20 Addendum 1 Update.pdf PDF
I-110 ADDENDUM NO-1.pdf PDF
Sign In Sheet FA8601-11-B-005.pdf PDF
ZHTV109012 DRAWINGS.pdf PDF
Solicitation FA8601-11-B-0005.pdf PDF
DBA Wage Determination OH29 8 Jul 11.pdf PDF
ZHTV109012 SPECIFICATIONS.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5 Aug 2011

FA8601-11-B-0005

Maintain Finishes, F/34010 / Project Number: 109012

Pre-Proposal RFI W/ Responses

1. There is military equipment in room 132, will this be removed by the owner? GOV TO

RELOCATE.

2. The prints state that a graphic timeline is to be removed, stored and replaced. What about the rest of the memorabilia on the walls throughout the facility? REFER TO GENERAL NOTES ON

SHEET G-O.

3. There is stain on the carpet flooring in the vault that the user commented has been bleeding through from underneath. Is the cause of this stain known? STAIN PRESENCE HAS NOT BEEN CONFIRMED AS ALLEGED. BID PROJECT ACCORIDNG TO PROJECT DOCUMENTS. Are there any special prepping requirements for this particular area? SEE RESPONSE IN QUESTION NO. 3

(ABOVE).

4. Will the safes in the vault be removed and replaced by the owner? GOV TO RELOCATE SAFES.

5. Will all of the asbestos containing debris noted above the ceiling need to be abated or just the areas where the ceiling is going to be disturbed due to other scopes of this project? REFER TO

HAZARDOUS MATERIALS PLAN GENERAL NOTES, HAZARDOUS MATERIALS PLAN,

SPECIFICATIONS, ETC.

6. Is there a hazardous material survey for this project? YES.

7. Are there offsite storage areas available if the rooms planned cannot hold all of the staged furniture? NO.

8. How will abatement of the floor tile be able to be performed in the rooms that will be occupied

100% of the time? REFER TO DEMOLITION PLAN & NOTES ON DRAWING SHEET #I-001 AND

HAZARDOUS MATERIAL PLAN & NOTES DRAWING SHEET #G-3 AS WELL AS SPECIFICATIONS.

9. Shaw carpet tiles are specified and will you accept equals to the carpets. I’m a rep with a mill and we would like you to consider our carpet products. Please let me know what I need to do- SPECIFIED

CARPET IS BASIS OF DESIGN OR APPROVED EQUAL. SUBMIT EQUAL FOR APPROVAL FOLLOWING

CONTRACT DOCUMENTATION GUIDELINES/PROCEDURES.

The following two questions were submitted via email from PK dated 8/3/2011.

10. (Email Question #9.) Are there any coatings in the facility that are known to contain lead? REFER TO CONTRACT DOCUMENTS AND SPECIFICATION SECTION 02 09 00 (REMOVAL AND DISPOSAL OF LEAD

CONTAINING MATERIALS INCLUDING LEAD BASED PAINT)/ PARAGRAPH 1.05.10.

11. (Email Question #10.)If no survey is available, are we to test the areas ourselves for the presence of lead paint? REFER TO CONTRACT DOCUMENTS AND SPECIFICATION SECTION 02 09 00 (REMOVAL AND

DISPOSAL OF LEAD CONTAINING MATERIALS INCLUDING LEAD BASED PAINT).