Amendment 0001.pdf

PDF 23 KB Posted

Attached to
Maintain Finishes, Facility 34010 Federal contract opportunity
Solicitation number
FA8601-11-B-0005
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

About this file

Amendment to the Solicitation FA8601-11-B-0005

View the file

Other files for this federal contract opportunity

Other files attached to Maintain Finishes, Facility 34010, newest first.
File Type Posted
Pre-Proposal RFI 4.pdf PDF
Pre-Proposal RFI 1 Updated response.pdf PDF
Pre-Proposal RFI 3.pdf PDF
Pre-Proposal RFI 1 Responses.pdf PDF
Pre-Proposal RFI 2 Response .pdf PDF
01 02 20 Addendum 1 Update.pdf PDF
Wage Decision OH29 4 Aug 11.pdf PDF
I-001 ADDENDUM NO-1.pdf PDF
FFP Addendum 1.pdf PDF
I-100 ADDENDUM NO-1.pdf PDF
I-110 ADDENDUM NO-1.pdf PDF
Sign In Sheet FA8601-11-B-005.pdf PDF
ZHTV109012 SPECIFICATIONS.pdf PDF
ZHTV109012 DRAWINGS.pdf PDF
Solicitation FA8601-11-B-0005.pdf PDF
DBA Wage Determination OH29 8 Jul 11.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

109012

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The reasons for this Amendment are as follow s:

1) To add Addendum #1

2) To update Wage Determinations

3) To update Clause 252.236-7001; Contract Draw ings, and Specifications

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Aug-2011

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA8601-11-B-0005

X 9B. DATED (SEE ITEM 11)

13-Jul-2011

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item14. The hour and date specified for receipt ofOffer is extended, X is not extended.

Offer must acknowledge receipt ofthis amendment prior to the hour and date specified in the solicitation or as amended by one ofthe following methods:

(a) By completing Items 8 and 15, and returning copies ofthe amendment; (b) By acknowledging receipt of this amendment on each copy ofthe offer submitted;

or (c) By separate letter or telegramwhich includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. Ifby virtue ofthis amendment you desire to change an offer already submitted, such change may be made by telegramor letter, provided each telegramor letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriat ion date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not , is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(Ifapplicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Aug-2011

CODE

ASC/PKOC - CONSTRUCTION BRANCH

POC: ASHLEE J. REYNOLDS

1940 ALLBROOK DRIVE, ROOM 109

WRIGHT-PATTERSON AFB OH 45433-5309

FA8601 7. ADMINISTERED BY (Ifother than item6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

FA8601-11-B-0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The purpose of this amendment is as follows:

a. To update Attachments (See Section J) to include Addendum #1

b. To update Attachments (See Section J) to include the newest Davis Bacon Wage Determination

c. The update Clause 252.236-7001, Contract Drawings, and Specifications

d. All other terms and conditions remain unchanged.

SECTION I - CONTRACT CLAUSES

The following have been modified:

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

FA8601-11-B-0005

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

TITLE DRAWING

NO.

Drawing Date

Cover Sheet G-0 29-Apr-11 Abbreviations Sheet G-1 29-Apr-11 Phasing Plan G-2 29-Apr-11 Hazardois Materials Plan G-3 29-Apr-11 Demolition Plan I-001 29-Apr-11 Finish Schedule and Legend I-100 29-Apr-11 Finish Plan I-110 29-Apr-11 Furniture Plan 1-120 29-Apr-11

Addendum #1 Demolition Plan I-001 27-Jul-11 Finish Schedule and Legend I-100 27-Jul-11 Finish Plan I-110 27-Jul-11

(End of clause)

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Specifications 190 02-MAY-2011 Attachment 2 Drawings 8 29-APR-2011 Attachment 3 DBA Wage Decision

OH100029, Mod 39

60 08-JUL-2011

to: Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 3 Wage Determination 60 04-AUG-2011 Attachment 4 Addendum #1 Memo 1 27-JUL-2011 Attachment 5 Addendum #1

Specification 01 02 20

20 31-DEC-2010

Attachment 6 Addendum #1 Drawing I-

1 27-JUL-2011

Attachment 7 Addendum #1 Drawing I-

1 27-JUL-2011

Attachment 8 Addendum #1 Drawing I-

1 27-JUL-2011

(End of Summary of Changes)