090036_RFI 1.docx
DOCX document 14 KB Posted
- Attached to
- Reconfiguration of Visualization Laboratory Federal contract opportunity
- Solicitation number
- FA8601-10-B-0006
About this file
RFI 1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BID OPENING.docx | DOCX document | |
| Map of Twin Base Golf Course.pdf | ||
| RECONFIGURE VIZUALIZATION LAB- Site Visit Roster.docx | DOCX document | |
| 090036_RFI 2- Response.docx | DOCX document | |
| 090036_RFI 3 Response.docx | DOCX document | |
| General Wage Decision 30 July_OH 29.docx | DOCX document | |
| Project Specifications.pdf | ||
| FA8601-10-B-0006 Solicitation.pdf | ||
| FFP Addendum 2.docx | DOCX document | |
| Drawing Addendum 2_Cable Tray Routing.pdf | ||
| FFP Addendum 1.docx | DOCX document | |
| Specs Addendum 1_Section 01 33 00.pdf | ||
| Specs Addendum 1_Section 01 01 50.pdf | ||
| Project Drawings.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
12 August 2010
RFI#1
Reconfigure Visualization Lab – Project 090036 Question: Per Drawing page I001 there are four types of flooring required on this project. The Project documents do not clarify, but from previous experience at least two of the flooring types are typically provided integrally to the computer access floor units. Are we to assume that the static dissipative tile (SDT) and floor carpet (FC) are stand alone, and the floor resilient (FR) and floor laminate (FL) are to be integral to the computer access flooring? Please advise.
Response: All four (4) types of flooring required for this project shall be integral to the computer access flooring.
-88 ABW/CEPMW Design Manager