Q A_5_PAD.docx

DOCX document 17 KB Posted

Attached to
Aircraft Components and Accessories
Solicitation number
FA8505-13-R-31129
Issued by

View the file

Other files

File Type Posted
FA850513R31129______0002.pdf PDF
Q A_6_PAD.docx DOCX document
Passive_Attack_Display_(PAD)_X201122867_Rev-11_Jun_13.pdf PDF
FA850513R31129______0001_11_Jun_13.pdf PDF
Q A_4_PAD.docx DOCX document
Q A_3_PAD.docx DOCX document
Attach_5_97X0011.pdf PDF
Attach_3_Boeing_G667-E.pdf PDF
Attach_1_MDC_A4246_Rev_C_-_F15_Dynamic_Load_Requirements.pdf PDF
Attach_4_Boeing_STL_00A0060.pdf PDF
Q A_2.docx DOCX document
Attach_2_Boeing_H417-D.pdf PDF
PAD_Q A__1_23_May_13.docx DOCX document
PADSOW7May13.docx DOCX document
PADPkg.pdf PDF
PADSPECX201122867.docx DOCX document
CDRLSPAD.pdf PDF
FA850513R31129.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA8505-13-R-31129

Q&A #5: 5 Jun 13

Questions:

1. Will the government provide early funding for the long-lead material required to meet the short production lead time of 60 days after completion of Flight and environmental testing?

2. Page 20 of the solicitation states that "electronic commerce method to receive proposals, modifications, revisions is permitted and preferred." Page 38, Section A references physical delivery requirements for the proposal. Please clarify the method of delivery required for the proposal, either physical or electronic copies.

Answers:

1. Although the Production CLINs will be funded up front, awardee will not be able to incur expenses or invoice prior to Pre-Production units approval.

2. Electronic responses are preferred but hard copies are acceptable.