3-01650 - REV Phasing Plan.doc

DOC document 39 KB Posted

Attached to
RECOVERY - UHHZ020212 - Repair/Replace Usts, Exch Service Sta, B/922
Solicitation number
FA8501-08-R-0050
Issued by

About this file

Specification to Solicitation FA8501-08-R-0050 Repair/Replace Storage Tanks, Bldg 922.

View the file

Other files

File Type Posted
1- 16 April 2009 Revision —
2- 01300 - Submittals & Certificate of ComplianceREV.doc DOC document
EE112OQ0REV .pdf PDF
d- Bid Schedule —
FA8501-08-R-0050.doc DOC document
ME104OQ0 REVISED.pdf PDF
CE102OQ0 REV.pdf PDF
ME105OQ0 PHASING REV.pdf PDF
GE101OQ0REV.pdf PDF
EE110OQ0REV .pdf PDF
01005 - Statement of Work REV.doc DOC document
5- 15050-REV.doc DOC document
e - 16 Apr 09 contractor cost blank.xls XLS spreadsheet
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01650 – PHASING UHHZ 020212

Revised Section

PART 1 - GENERAL

1.01

GENERAL:

A.

Major Phases: The work shall be divided into major phases as shown below.

PART 2 - PRODUCTS -- OMITTED.

PART 3 - EXECUTION

3.01 MAJOR PHASE 1: Provide labor, material, equipment, and coordination required by Construction Documents to provide THREE NEW UG TANKS, ALL ASSOCIATED ACCESSORIES, ELECTRICAL, AND PIPING AS REQUIRED, work inside B/922, leak detection system, etc. The gas service station shall be fully operational during this phase.

A.

Start: Work for phase 1 will begin after submittals are approved.

3.02 MAJOR PHASE 2: Provide labor, material, equipment, and coordination required by Construction Documents to provide UG piping to all Dispensers.

Connect NEW Veeder Root electronic monitoring system to all new tanks, other devices, etc. Connect all new piping to all the dispensers. Recalibrate and certify all dispensers which shall be performed by a dispenser manufacturer’s or state’s certified technician. This change shall be accomplished in 15 days. . Contractor shall provide walkway access for the store which will be open to the customers. All dispensers shall be fully shut down during this phase.

3.03 MAJOR PHASE 3: Provide labor, material, equipment, and coordination required by Construction Documents to remove all existing UG tanks, piping, etc. Repair landscaping, concrete, asphalt, curbing, etc. as required. Remove contaminated soil as required. Contractor shall provide access for the fuel tank truck to fill the new tanks,. Dispensers D1, D2, and D3 will be shut down for the demolition work. All dispensers D4 thru D9 shall be fully functional.

3.06 RESPONSIBILITIES:

A Provide Walkways for Government personnel to access areas which remain occupied, such as bridges or roped-off corridors.

B.

Protect from dust, paint, debris, and damage all items in place or stored in the work

C.

Provide Daily Cleanup of work area when adjacent area is occupied by government personnel and as directed.

D. Extra Work Required by Phasing: Perform associated incidental work necessary for proper function of installed equipment and material. (For example, if Phase 1 requires installation and acceptance of a temporary submersible pump and the power wiring is in Phase 3, provide the power wiring needed for Phase 1).

E. Contractor shall provide fence or other as needed fence around the phased work area as approved by the COR to isolate the construction area from other areas which are occupied by the Government personnel.

F. . Deleted G. Contractor shall not start work on major phase 3 until the new fueling system (major phase 2 work) is complete and fully operational.

H. The gas service station shall be operational at all time during the entire project construction work except it will be only partial shut down in phase 3 and full shut down in phase 2.

I. Contractor shall not work on phase 3 until new Veeder Root monitoring system inside B/922 is connected, fully functional and the new fueling system including all tanks and dispensers are recalibrated, certified, completed and fully operational to the satisfactory of the COR..

J. Contractor shall provide a proposed detailed construction phasing plan for review and approval. Contractor shall provide additional piping, valves, etc. as required to maintain the gas service station in operational at all times as specified except the shut down times as indicated in item H. above.

K. Contractor shall submit a detailed work plan to meet mission or occupancy needs which shall include all phases for review and approval. This plan shall coincide with project schedule to include dates and sequence of work.

3.08 SCHEDULE: Below is tentative schedule for work for base bid and options 1 thru 3. The number as shown below is the number of calendar days. Contractor shall incorporate schedule into his progress chart. Times for each phase should not vary more than 20% from times (calendar days) indicated below:

ITEM TOTAL

ITEM

TIME CMLTVE

NTP

Mobilization, Submittals etc.

106 106

PHASE I

PHASE II

PHASE III

Base bid and Option 3

Contract close out documents (base bid and option 3)

40 281 Option 1

Option 2

*** END OF SECTION ***