This document contains a solicitation for the procurement of ALR-69A diplexers for the F-16 fleet. The United States Air Force seeks to award an indefinite-delivery/indefinite-quantity contract to provide low-cost and rapid delivery of the diplexers in order to meet program timelines for fielding the ALR-69A Digital Radar Warning Receiver system as a replacement for legacy systems. Interested offerors are required to submit proposals by November 13, 2020 responding to the requirements set forth in the solicitation and attachments, which include specifications for size, weight, and performance characteristics. The solicitation also provides responses to questions from potential offerors seeking clarification on technical requirements and processes for accessing classified specifications.

View the file

Other files

File Type Posted
FA823220R3006_______0006.pdf PDF
Attachment_1_Statement_of_Work_Diplexer_13AUG2021.pdf PDF
Attachment_3_DDForm254_15SEP20_.pdf PDF
Attachment_2_Exhibit_A_CDRLs_.pdf PDF
FA823220R3006_______0005.pdf PDF
Attachment_1_Statement_of_Work_Diplexer_22Feb21.pdf PDF
Attachment_5_Section_M_22Feb21.pdf PDF
Attachment_6_Total_Evaluatied_Price_Table_.xlsx XLSX spreadsheet
Attachment_4_Section_L_22Feb21.pdf PDF
Q and A 7DEC2020.xlsx XLSX spreadsheet
FA823220R3006_______0004.pdf PDF
FA823220R3006_______0003.pdf PDF
Attachment_1_Statement_of_Work_Diplexer_9NOV2020.pdf PDF
Attachment_4_Section_L_9NOV2020.pdf PDF
FA823220R3006 Q and A 17NOV2020.xlsx XLSX spreadsheet
Attachment_1_Statement_of_Work_Diplexer_28Sep2020.pdf PDF
FA823220R3006-0002.pdf PDF
Attachment_4_Section_L.pdf PDF
Attachment_5_Section_M.pdf PDF
FA823220R3006.pdf PDF
Attachment_3_DDForm254_15SEP20.pdf PDF
FA823220R3006 Q and A 17 Sep 2020.xlsx XLSX spreadsheet
FA823220R3006-0001.pdf PDF
Synopsis.pdf PDF
Attachment_3_DDForm254_Initial.pdf PDF
FA823220R3006.pdf PDF
FA823220R3006.pdf PDF
Attachment_6_Total_Evaluatied_Price_Table.xlsx XLSX spreadsheet
Attachment_4_Section_L_9Sep20.pdf PDF
Attachment_5_Section_M_9Sep20.pdf PDF
Attachment_1_SOW_ALR69A_Diplexer_2_Sep_2020.pdf PDF
Attachment_3_DDForm254_Initial.pdf PDF
Attachment_2_Exhibit_A_CDRLs.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

QuestionsResponse
In the original synopsis for the program it stated the following: “4.The Government will release Technical Data Package (TDP) IAW U.S. Requirements. The solicitation contains CLASSIFIED information that will need to be requested by potential offerors as soon as possible.

a. The requesting Contractor shall provide a CAGE code, and a DD Form 2345. The contractor will be verified and screened through the Industrial Security Facility Database (ISFD) and the Joint Certification Program (JCP) to verify the Contractor’s ability to handle SECRET information.

b. The Contractor shall provide a CLASSIFIED shipping address to the Contracting Officer and Contract Specialist listed below.

c. Once the SECRET portion of the TDP is shipped on a CD, the Contractor shall sign an AF Form 310 to acknowledge shipment. The Contractor shall destroy the CD and all copies after a response to this solicitation is given to the Government or immediately after a determination to not provide a response is made.”

This year with beta.SAM many chagnes have occurred regarding the process for release of Technical data. With the release of this solicitation, we requested access to all of the associated technical data wich was justified by our interest in submitting a proposal to this solicitation, coupled with our currently approved DD2345 (attached). Within a day we received “approval” to access the controlled information on beta.SAM which was Attachment 7. Attachment 7 was CUI but does not match the expectation created by the statement in the synopsis (above) regarding the release of classified Technical Data. Our question is whether there is actually classified technical data as described in the synopsis; and if so, do we need to resubmit our DD2345 directly to you for release of it or will you be confirming with JCP directly?There is a classified portion of the specification that will be provided upon request and verification. The Government will follow the process outlined in the Synopsis for the classified portion of the specification. The request through beta.SAM.gov is for the unclassified portion of the specification posted with the RFP (FA823220R3006). A separate, written request (via e-mail), for the classified portion of the specification is expected from each potential offeror. Emails should include a current DD2345 and Classified Shipping Address to receive the technical data.
Paragraph 4.1.1 of the SOW references a diagram in Appendix 1 of the RFP. We have not been able to locate that drawing. Could you please let us know which file contains the drawing, if there is a drawing?This SOW reference has been amended as a result of replacing OO-G719769, Rev C with OO-G719769, Diplexer attachment to the solicitation.
On a related topic, paragraph 3.2.2.1 of OO-G719769 Rev C indicates that the package size and mounting configuration is to be proposed by the vendor. Is this correct?Please use Solicitation attachment OO-G719769, Diplexer in place of OO-G719769, Rev C for proposal preparations. The updated OO-G719769 specifies in Figure 2 the Preliminary Outline Diagram of the Unit, as referenced in paragraph 3.2.2.1.
Paragraph 3.2.2.1 of OO-G719769 Rev C does not appear to define connector location. Are all connectors required to be on the same surface of the diplexer or is it allowable for one connector to be on the opposite surface from the other two connectors?See Figure 2 of the updated solicitation attachment OO-G719769, Diplexer for connector locations.
Paragraph 3.2.2.1 of OO-G719769 Rev C also indicates that preferred mounting is either mounting studs or through holes. Between these two options is there a preference?The preferred mounting method is to mount through studs, per OO-G719769, Diplexer Figure 2
Paragraph 3.2.2.2 of OO-G719769 Rev C indicates a maximum weight of 5.0 ounces, three TNC connectors alone weigh approximately 1.5 ounces therefore the weight may be a risk factor. Should the vendor propose an alternate weight?Per the updated solicitation attachment OO-G719769, Diplexer, weight of the unit shall not exceed 6.0 ounces.
Paragraph 4.6.6 of OO-G719769 Rev C indicates that the low temperature storage test should be performed at -54° C while paragraph 3.2.9.1 indicates that the diplexer shall survive a low storage temperature of -62° C, which is correct?Per the updated solicitation attachment OO-G719769, Diplexer, the low temperature storage test should be performed at -54° IAW paragraph 4.6.6. The non-operating temperature in paragraph 3.2.9.1 now states a temperature range of -62°C to +95°C
Paragraph 4.6.7 of OO-G719769 Rev C indicates that the low temperature operational test should be performed at -20° C while paragraph 3.2.9.2 indicates that the diplexer shall be fully spec compliant at a temperature of -54° C, which is correct?Per the updated solicitation attachment OO-G719769, Diplexer, the low temperature operational test should be performed at -20° IAW paragraph 4.6.7. The normal operating temperature in paragraph 3.2.9.2 now states a temperature range of -54°C to +71°C
Table II of OO-G719769 Rev C, we believe that note 4 applies to step 7 in this table, is this correct?Reference OO-G719769, Diplexer document for clarification.
This is not actually a question, we noticed that in paragraph 4.4.2 508 FSG/GFFBO is referenced as performing group B testing. Should this reference be to AFLCMC/WWMPA?Reference to a specific organization has been removed as a result of replacing OO-G719769, Rev C with OO-G719769, Diplexer. However, Group B testing shall be performed initially by the contractor up to the point of delivery. The Government will perform First Article testing on a simulated platform and provide first article approvals.
Are we correct to assume that the WBS can be included as an attachment to Volume II and outside the page count limit?The WBS can be included as an attachment to Volume II and will not be included in the page count limitations.
Which quantity are we to assume for the production quantity; 2,640 units or 937 aircraft x 4 units = 3,748 units?2,640 units; Reference to the approximately 937 aircraft has been removed from the SOW as a result of this solicitation amendment
Is the USAF able to provide a breakdown on the contractual ceiling amount?The government cannot share additional infomration regarding the contract ceiling.
Instructions for Cross Reference Matrix are included in instructions for Volume I but instruct us to include the Cross Reference Matrix in Technical Volume (II). Please confirm that the Cross Reference Matrix is to be included in the Technical Volume rather that the Executive Summary Volume.This was an oversight in location of the Cross Reference Matrix instructions within Section L. The Cross Reference Matrix note incldued with Table 3.1 indicating placement of the cross reference matrix in Volume II Technical is correct.
Can the Government clarify if the signed RFP is different from the signed copy of the Solicitation/Model Contract? If there is no difference, please clarify where the signed solicitation should be included: Volume I or Volume IV?There is no difference. Including the signed copy of the Solicitation and all applicable amendments shall be included in Volume IV - Contract Documentation.
[potential offeror] would like to request Appendix 1 so that we are able to review the diagram.This SOW reference has been amended as a result of replacing OO-G719769, Rev C with OO-G719769, Diplexer attachment to the solicitation.
We are requesting a clarification on the weight specification for the ALR-69A diplexer. There seems to be a discrepancy between what is stated in the SOW (Attachment_1_SOW_ALR69A_Diplexer_2_Sep_2020.pdf) and what is stated in the Specification (Attachment_7_SpecOO_G719769_Rev_C.pdf). Section 1.2.1 SOW: Size, Weight and Power (SWaP): Current diplexer size is approximately 4x4x1 inches, current diplexer weight is approximately 2 pounds. Full electrical performance shall be as specified in OO-G719769, Rev C, dated 21 Apr 2017. Section 3.2.2.2 Specification: WEIGHT. WEIGHT OF THE UNIT SHALL NOT EXCEED 5.0 OUNCES. Could you provide some clarification to address this discrepancy[?]
Please use Solicitation attachment OO-G719769, Diplexer in place of OO-G719769, Rev C for proposal preparations. The updated OO-G719769 provides clarity on the specifications the Diplexer is expected to meet.