SOW for Sample Task First Configuration.pdf
PDF 150 KB Posted
- Solicitation number
- FA823212R3007
About this file
Sample Task First Configuration
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA823212R3007 Amend A003.pdf | ||
| FA823212R3007 Amend A002.pdf | ||
| K20 vendor list.pdf | ||
| FA823212R3007 Amend A001.pdf | ||
| K10 vendor list.pdf | ||
| FA823212R3007 Amend 1.pdf | ||
| BRACKET IDIQ SOW Appendix C.pdf | ||
| DD1423 CDRLs A001-A004.pdf | ||
| FA823212R3007.pdf | ||
| Brackets IDIQ SOW Appendix A.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 of 3 5/3/2012
ATTACHMENT 2
SAMPLE TASK
STATEMENT OF WORK (SOW)
Helmet Mounted Integrated Targeting (HMIT)
METAL BRACKET/PLATES/ASSEMBLIES IDIQ
MARCH 29, 2012
2 of 3 5/3/2012
INTRODUCTION
1.1 Purpose
1.1.1 The purpose of this task order is to provide the U.S. Air Force metal brackets, plates and assemblies, per the attached drawing package for the F-16 fleet to include all Block aircraft.
1.2 Scope
1.2.1 This SOW addresses the requirement for the Contractor to supply 140 Bracket kits.
1.2.2 The Contractor shall build and deliver required kits to the specifications and standards called out in attached drawings 16K0330, 16Z5525 and 16Z5524.
CONTRACTOR TASKING / REQUIREMENTS
1.3 Contractor Specific Requirements
1.3.1 The Contractor shall build and deliver, assembles -5 and -23 as called out in drawing 16K0330, assembles -1,-3,-5 and -801 as called out in drawing 16Z5525, and assemble -1 as called out in drawing 16Z5524. All assembles shall be built to the qualities specified in subject drawings and placed in a kit.
1.3.2 The contractor shall build all required parts to the specifications provided in the attached drawing package.
1.4 Quality Assurance
1.4.1 The Contractor shall comply with SAE AS9100 and AS9102 and as a minimum, shall include inspection, validation, evaluation, corrective action and procedures necessary to effect quality of all products provided under this contract.
1.4.2 The Contractor shall allow inspection by the Government and shall be applicable to all subcontractors and members of the contractor's team, as appropriate.
1.4.3 Quality Assurance will demonstrate that the government’s designs are adhered to and that material used conforms to the approved designs/drawings provided by the government. (CDRL
A001)
1.5 Delivery Requirements
1.5.1 The Contractor shall deliver the number of kits specified in the following schedule.
1.5.2 A Status Report will be provided documenting the effort towards achieving the Delivery Order
(D.O.) objectives. (CDRL A002)
1.6 First Article
1.6.1 The Contractor shall provide a first article to the government for testing and inspection. The
Contractor shall not produce production articles until after Government approval of the first article. The Government will have 5 days after receipt of the first article to inform the
Contractor of acceptance of rejection. After acceptance of the first article, the article shall
12-
Oct
12-
Nov
12-
Dec
13-
Jan
13-
Feb
13-
Mar
13-
Apr
13-
May
13-
Jun
13-
Jul
13-
Aug 13- Sep
14 12 13 9 8 12 12 12 12 12 12 12
3 of 3 5/3/2012 become a production article and be counted as one of the deliverable items for the first month’s delivery.
1.6.2 In the event of rejection of the first article, the Contractor will be notified in writing by the
Government of the specific reasons why the part was rejected. Unless otherwise specified the
Contractor shall have 5 workdays to correct the rejected part and resubmit to the Government for re-inspection.
1.7 Packaging
1.7.1 All parts shall be wrapped separately so that paint/epoxy is protected. Parts will be shipped in a
“kit”. Kits for the HMIT project consist of 1 each of the following brackets: 16K0330-5, 16K0330-23, 16Z5524-1, 16Z5525-1, 16Z5525-3, 16Z5525-5, and 16Z5525-801.