15340 - 238 Mezzanine and Modular Office SOW - Updated.pdf

PDF 139 KB Posted

Attached to
15340 - Mezzanine & Modular Office
Solicitation number
FA8227-26-A-1002
Issued by

About this file

This is a Statement of Work (SOW) for the design and construction of a 1,200 square foot (30' x 40') enclosed mezzanine in Building 238, South Center, located at Hill Air Force Base.

The contractor shall provide all labor, materials, and equipment to design and construct the mezzanine structure with integrated stairs, walls, ceiling, and interior finishes. The mezzanine will contain an office, break room, and multi-purpose area (computer lab and meeting space). The structural design must prioritize a maximum of nine support columns bolted to existing concrete with no new footings preferred; if infeasible or cost-prohibitive, the contractor must propose reasonable alternatives or dual-option proposals. The structure must maintain a minimum clear height of 11 feet below the mezzanine on the ground floor to accommodate repair work and tool storage. All steel components shall be painted light grey with industrial-grade primer and paint. Interior finishes include carpet tiles for the main office area and luxury vinyl plank (LVP) with rubber wall base in the break room. The contractor shall provide flooring options for customer selection.

The scope includes installation of electrical systems with three dedicated circuits for refrigerators and four for microwaves in the break room, data runs to designated computer locations, and LED lighting with dimmer switches throughout both levels with specified lumen counts. The contractor shall stub out plumbing supply and drain lines and rough-in plumbing for a double sink basin, with final connections performed by the customer. Fire alarm and suppression systems must be integrated per code requirements. All work must comply with Unified Facility Criteria (UFC), Hill Air Force Base Facility Design Standards, and all applicable local and national building, electrical, plumbing, mechanical, and fire safety codes. The contractor may use a caged staging area for material storage during construction.

View the file

Other files

File Type Posted
15340 - Additional Contractor Questions n Answers.docx DOCX document
15340 - Contractor Questions n Answers.pdf PDF
15340 - Updated Drawings.jpeg JPEG file
IMG_0608.jpg JPG image
IMG_0607 2.jpg JPG image
IMG_0606.jpg JPG image
15340 - 238 Mezzanine Modular Office Combo.pdf PDF
15340 - 238 Mezzanine and Modular Office SOW.pdf PDF
15340 - 238 Mezzanine and Modular Office SOW.docx DOCX document
15340 - 238 Mezzanine Modular Office Combo.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work: Mezzanine Construction

Project Design and Construction of a 1200 sq. ft.

Mezzanine in Building 238, South Center

1.0 Project Overview & Summary

This Statement of Work outlines the requirements for the design and construction of a new 1200 square foot (30’ x 40’) enclosed mezzanine to be located in the South Center section of Building 238.

The scope of this project includes the construction of a new mezzanine and stairs with a fully enclosed space featuring an office, a break room, and a multi-purpose area designated for use as both a computer lab and a general meeting space.

The project encompasses all associated structural, electrical/lighting, data, and fire alarm/suppression systems. Careful consideration must be given to the placement of support columns to maximize usable workspace and allow for general repair work and tool box storage on the ground floor. All work must adhere to applicable life safety and building codes.

2.0 Scope of Work

The contractor shall provide all labor, materials, and equipment necessary to perform the following:

• Design: Provide a complete design package for the new mezzanine, adhering to all specified codes and standards. The design should prioritize a maximum of nine (9) support columns and avoid new footings where possible. If this approach is not feasible or is cost-prohibitive, a reasonable alternative or a dual-option proposal is required.

• Construction: Fabricate and erect the new mezzanine steel structure and decking and stairs.

• Enclosure: Frame and finish all walls and the ceiling for the upper level.

• Interior Finishes: Install flooring, cabinetry, and other specified finishes.

• Utilities: Install all required systems, electrical, data, and lighting for both the upper mezzanine level and the area below. Coordinate with the customer for plumbing hookups (accomplished by customer).

• Safety Systems: Integrate fire alarm and suppression systems as required by code.

• Contractor will be able to use caged area to stage materials where the mezzanine is needing to be built.

3.0 Technical Specifications

Category Requirement Details

Structure Dimensions & Location

30’ x 40’ mezzanine located in the south-center portion of Building 238.

Support Columns

Design for a maximum of nine (9) columns, bolted to the existing concrete slab. No new footings are preferred.

Clear Height (Below)

A minimum of 11'0" clear height from the ground floor to the underside of the mezzanine.

Load Bearing The structure and stairs must be rated for its intended office/assembly occupancy and meet all applicable facility codes.

Paint All steel components are to be painted light grey using a durable, industrial-grade primer and paint.

Interior Finishes

Flooring Main Area/Office: Carpet tiles. Break Room: LVP (Luxury Vinyl Plank) wood planks and rubber wall base in all areas. (Contractor to provide options for customer selection.)

Electrical & Data

Data Install data runs to all designated computer locations within the multi-purpose area and office.

Break Room Circuits

Provide three (3) dedicated circuits/receptacles for refrigerators. Provide four (4) dedicated circuits for microwaves with receptacles at appropriate counter height.

Plumbing Scope & Coordination

The contractor shall stub out plumbing supply and drain lines. The final installation and connection will be performed by the customer.

The design must ensure customer can meet all plumbing codes.

Break Room Fixtures

Rough in plumbing for double sink basin.

Lighting

Type & Standards

All lighting shall be LED with Dimmer switches and meet applicable standards for brightness. The proposal must include designed Lumen counts for each area.

Locations Install lighting fixtures on the enclosed upper level and on the underside of the mezzanine to illuminate the ground-level workshop area.

4.0 Codes and Standards Compliance

All design and construction work must conform to the latest editions of the following:

• Unified Facility Criteria (UFC)

• Hill Air Force Base Facility Design Standards

• All applicable local and national building, electrical, plumbing, mechanical, and fire safety codes.

Statement of Work: Mezzanine Construction
Project Design and Construction of a 1200 sq. ft. Mezzanine in Building 238, South Center
1.0 Project Overview & Summary
2.0 Scope of Work
3.0 Technical Specifications

File details come from the government source that posted it. Updated .