Question & Answers: C-17 PCTS 10 May 12 #1-3

1. What is the proposed budget or estimated target price for this? Request for Proposal

(RFP) means the vendor shall propose per the solication requirement; to include a cost.

2. Was there a RFI, source source, or industry day previously posted or held? Yes there was a sources sought notice posted to FBO for Request of Information (RFI) from 12 Jan 12-

14 Feb 12. Reference solicitation for the only site visit/industry day that will be and has been scheduled.

3. Who built the test system for the original C-17 APU? The original C-17 stand was built by Triumph.