This is a Total Evaluated Price (TEP) workbook template for a T-38C Avionics Sustainment and Support Program contract. The workbook contains pricing tables for a 10-year period spanning January 2026 through March 2036, with a 3-month transition period (January-March 2026) followed by ten 12-month Contractor Logistics Support (CLS) delivery orders.
The pricing structure includes 25 Contract Line Item Numbers (CLINs) covering program management, COMBS labor, FSR labor, overtime, material costs per flight hour, damaged parts, engineering services, software support, courseware support, modifications, special studies, block upgrades, travel, and other services. Notable elements include normalized flight hour costs (minimum 4,400 hours/month during base period, 3,800 hours/month during option period), notional amounts for overtime ($2,500/month with 3% annual escalation), and pre-set amounts for government damaged parts ($1M/year) and AFI 4700 RoadRunner support ($5,000/year). The template requires offerors to input labor rates and indirect costs to calculate fully-burdened labor rates for various engineering and technical positions.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Total Evaluated Price
| Pricing Table: CLS Delivery Orders | ||
| CLS Period of Performance - 1st CLS delivery order = 01 April 2026 - 31 March 2027. 2nd CLS delivery order = 01 April 2027 - 31 March 2028. ect…. | Transition 01 Jan 2026 - 31 Mar 2026 | 1st CLS DO |
01 April 2026 through 31 March 2027 2nd CLS DO 01 April 2027 through 31 March 2028 3rd CLS DO 01 April 2028 through 31 March 2029 4th CLS DO 01 April 2029 through 31 March 2030 5th CLS DO 01 April 2030 through 31 March 2031 6th CLS DO 01 April 2031 through 31 March 2032 7th CLS DO 01 April 2032 through 31 March 2033 8th CLS DO 01 April 2033 through 31 March 2034 9th CLS DO 01 April 2034 through 31 March 2035 10th CLS DO 01 April 2035 through 31 March 2036
| FILL IN YELLOW CELLS | Total Evaluated Price (TEP) | |||||||||||||||||||||||||
| Base Year | Year 2 | Year 3 | Year 4 | Year 5 | Year 6 | Year 7 | Year 8 | Year 9 | Year 10 | |||||||||||||||||
| CLIN | Description | Unit of Issue | BEQ | Type | Included in TEP | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Total |
| X001 | Program Management (Paragraph 3.4) | Months | 12 | FFP | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X002 | COMBS Labor (Paragraph 3.15) | Months | 12 | FFP | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X003 | FSR Labor Cost (Paragraph 3.14) | Months | 12 | FFP | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X004*** | COMBS & FSR Overtime (Paragraph 3.15.7 through 3.15.11) | Months | 12 | CR | X | NTE $2,500 per month for the Base Year with 3% escalation per FY | $ 343,916 | |||||||||||||||||||
| X005** | CLS, Material Cost Per Flight Hour (Paragraph 3.10.9, 3..11, and 3.16) | Flight Hours | 95,000 | FFP | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X006* | Government Damaged Parts (Paragraph 3.16) | Lot | 1 | CPFF | X | $1M per year*** | $ 10,000,000 | |||||||||||||||||||
| X007 | Engineering Services (Paragraph 5.1, 6.0, 7.2, and 7.3) | Months | 12 | FFP | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X008 | Software Applications Support (Section 4) | Months | 12 | FFP | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X009 | Courseware Support (Section 8) | Months | 12 | FFP | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X010**** | Out-of-Cycle Modifications (Paragraph 5.11.1 and Section 6) | Lot | 1 | FFP | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X011**** | Out-of-Cycle Modifications (Paragraph 5.11.1 and Section 6) | Lot | 1 | CPFF | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X012**** | Special Studies (Paragraph 3.12) | Lot | 1 | FFP | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X013**** | Block Upgrades (Paragraph 4.1.2, 7.1, and 7.4) | Lot | 1 | FFP | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X014*** | Travel (Paragraph 3.6) | Lot | 1 | CR | X | NTE $88,000 for the Base Year with 3% escalation per FY | $ 1,008,821 | |||||||||||||||||||
| X015*** | FSR Travel Support (Paragraph 3.14.1) | Months | 12 | CR | X | NTE $1,000 per month for the Base Year with 3% escalation per FY | $ 137,567 | |||||||||||||||||||
| X016**** | Over & Above (Paragraph 3.13) | Lot | 1 | FFP | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X017**** | Over & Above (Paragraph 3.13) | Lot | 1 | CPFF | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X018 | Permanent Change of Base Location (Paragraph 13.3) | Lot | 1 | CR | This CLIN shall not be proposed as part of the Offeror's basic contract proposal. This CLIN shall only be proposed upon receipt of a defined requirement and Contracting Officers request. | |||||||||||||||||||||
| X019**** | DMSMS Proposal and Solution (Paragraph 5.10) | Lot | 1 | CPFF | X | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||||
| X020 | Transition Phase-In(Paragraph 9.1) | Lot | 1 | FFP | X | $ - 0 | ||||||||||||||||||||
| X021 | Transition Phase-Out (Paragraph 9.2, 9.3, 9.4) | Lot | 1 | FFP | X | $ - 0 | ||||||||||||||||||||
| X022 | Life-Time/Last-Time Buy Requirements (Paragraph 5.10.7) | Each | 1 | CPFF | This CLIN shall not be proposed as part of the Offeror's basic contract proposal. | |||||||||||||||||||||
| X023 | Data | Lot | 1 | NSP | Not Seperately Priced | |||||||||||||||||||||
| X024*** | AFI 4700 RoadRunner Support (Paragraph 3.17) | Lot | 1 | CPFF | X | $5,000 per year | $ 50,000 | |||||||||||||||||||
| X025 | Transition Phase-In Incentive Fee (Paragraph 9.1.12) | Lot | 1 | FFP | IAW CLS PWS Paragraph 9.1.12 | |||||||||||||||||||||
| Total Evaluated Price | $ 11,540,304 | |||||||||||||||||||||||||
| * | Complete as per Section L 4.6.3 with a normalized amount plus offeror proposed fixed fee. | |||||||||||||||||||||||||
| ** | A minimum cost per flight hours will be reimbursed at a floor of 4400 hours per month during the 5-year base and 3800 hours per month during the 5-year option | |||||||||||||||||||||||||
| *** | This is a notional amount for planning purposes | |||||||||||||||||||||||||
| **** | Government notional hours applied to proposed rates for TEP. For evaluation purposes only. |
Labor Rate Matrix
| Labor Rate Worksheet | |||||||||||||||||||||||||||||||||||||||||||||||||
| Notes and Instructions: | 1 | This worksheet will be auto-populated based on inputs to the following worksheets: (1) Direct Labor Rates (2) Indirect Rates | |||||||||||||||||||||||||||||||||||||||||||||||
| 2 | Do not rename worksheet tabs. It is only necessary to populate the cells. | ||||||||||||||||||||||||||||||||||||||||||||||||
| 3 | The Offeror may alter the calculation of the fully burdened direct labor rate if it is not in accordance with the Offeror's disclosed accounting practices. If so, the Offeror must provide the rationale in the cost/price volume. | ||||||||||||||||||||||||||||||||||||||||||||||||
| 4 | One composite not-to-exceed (NTE) rate per labor category per year will apply to all members of the offeror's team (including the prime offeror, inter-divisions, and all tiers of subcontractors). No additional labor rate categories will be added during contract performance except at the Government's sole discretion. | ||||||||||||||||||||||||||||||||||||||||||||||||
| 5 | The profit/fee rate applied to each labor category rate will be determined by the pricing arrangement (FFP, CPFF). All profit/fee rates shall be the same within each pricing arrangement for all labor rates for all years. | ||||||||||||||||||||||||||||||||||||||||||||||||
| 6 | Profit/Fixed fee should not not being claimed on FCCOM (if used). | ||||||||||||||||||||||||||||||||||||||||||||||||
| 7 | For CPFF contract actions, the fixed fee dollar amount for each labor category shall be contractually binding. | ||||||||||||||||||||||||||||||||||||||||||||||||
| 8 | This table shall be used as a NTE for labor for all future contract actions and modifications (CLINs X010, X011, X012, X013, X016, X017, X019). Any deviations or modifications to this table will solely be at the Government's discretion. | ||||||||||||||||||||||||||||||||||||||||||||||||
| 9 | Ensure that the basis of each element, and supporting rationale, are included in the cost/price volume in accordance with Section L | ||||||||||||||||||||||||||||||||||||||||||||||||
| 10 | Existing CBA rates shall be used as outlined in Section L. | ||||||||||||||||||||||||||||||||||||||||||||||||
| 11 | As outlined in Section M, the Government will apply notional hours to the Offeror's proposed labor rates as part of the Total Evaluated Price (TEP). These notional hours are for evaluation purposes and will not be contractually binding. These notional hours will not be disclosed to offerors. | ||||||||||||||||||||||||||||||||||||||||||||||||
| FIXED FEE RATE: | 0.00% | PROFIT RATE: | 0.00% | ||||||||||||||||||||||||||||||||||||||||||||||
| Base Year | Year 2 | ||||||||||||||||||||||||||||||||||||||||||||||||
| Base Year | Notional Hours (CPFF) | Notional Hours (FFP) | Notional Hours | ||||||||||||||||||||||||||||||||||||||||||||||
| Fringe Benefits | Overhead | G&A | Total | COM | Fixed Fee | Profit | CLIN X011 | CLIN X017 | CLIN X019 | CLIN X010 | CLIN X012 | CLIN X013 | CLIN X016 | Fringe Benefits | Overhead | G&A | Total | COM | Fixed Fee | Profit | CLIN X011 | ||||||||||||||||||||||||||||
| Labor Category | Direct Labor | % | T | % | T | % | T | Total | % | T | Cost + COM | % | T | CPFF Rate | % | T | FFP Rate | Hours | Total | Hours | Total | Hours | Total | Hours | Total | Hours | Total | Hours | Total | Hours | Total | Direct Labor | % | T | % | T | % | T | Total | % | T | Cost + COM | % | T | CPFF Rate | % | T | FFP Rate | Hours |
| Single Manager | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Program Support Manager | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Chief Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Program Manager | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Senior Manager | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Project Technical Manager | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Principle Scientist | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Senior Scientist | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Scientist | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Junior Scientist | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Principle Systems Engineer/Assistant Project Technical Manager | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Senior Systems Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Systems Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Junior Systems Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Principle Aerospace/Mechanical Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Senior Aerospace/Mechanical Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Aerospace/Mechanical Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Junior Aerospace/Mechanical Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Principle Electronic/Electrical Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Senior Electronic/Electrical Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Electronic/Electrical Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Junior Electronic/Electrical Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Principle Chemical/Material Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Senior Chemical/Material Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Chemical/Material Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Junior Chemical/Material Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Principle Software Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Senior Software Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Software Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Junior Software Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Principle Systems Analyst | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Senior Systems Analyst | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Systems Analyst | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Junior Systems Analyst | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Senior Quality Assurance/Configuration Management Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Quality Assurance/Configuration Management Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Quality Assurance/Configuration Management Analyst | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Principle Industrial Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Senior Industrial Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Industrial Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Junior Industrial Engineer | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Principle Logistician | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Senior Logistician | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Logistician | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Junior Logistician | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Principle Mathematician | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | ||||||||
| Senior Mathematician | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 | 0.00% | $ - 0 | $ - 0 |