Sample_Sustainment_Scenario_Task.docx

DOCX document 28 KB Posted

Attached to
Modification of Equipment Federal contract opportunity
Solicitation number
FA8214-14-R-0005
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Attachment 23 - Sample Sustainment Scenario

View the file

Other files for this federal contract opportunity

Other files attached to Modification of Equipment, newest first.
File Type Posted
ATTACHMENT_1_Ground_PWS_10Feb14.docx DOCX document
GSSC_Questions_and_Answers_Combined_4.xlsx XLSX spreadsheet
ATTACHMENT_12_Labor_Category_Description_UPDATE_5Feb14.docx DOCX document
ATTACHMENT_18_Ground_GFP_UPDATE_3Feb2014.xlsx XLSX spreadsheet
ATTACHMENT_14_Mapping_Worksheet_UPDATE_5Feb14.xlsx XLSX spreadsheet
ATTACHMENT10SoftwareGRID.docx DOCX document
ATTACHMENT2BasicGRID.docx DOCX document
ATTACHMENT11CrossReferenceMatrixUPDATE.xlsx XLSX spreadsheet
ATTACHMENT13PricingMatrix.xlsx XLSX spreadsheet
ATTACHMENT20SectionLUPDATE.docx DOCX document
ATTACHMENT3CDRLInstructionsandCDRLsUPDATE22Jan14.pdf PDF
ATTACHMENT6SELMGMLECSOOUPDATE14Jan14.docx DOCX document
ATTACHMENT21SectionLAttachments.pdf PDF
ATTACHMENT7SELMGMLECGRID.docx DOCX document
ATTACHMENT15GSSCLaborRateMatrixUPDATE.xlsx XLSX spreadsheet
ATTACHMENT16BreakoutofLabCosts.xlsx XLSX spreadsheet
FA821414R0005_______0003.pdf PDF
ATTACHMENT22SectionMUPDATE.docx DOCX document
GSSC_Questions_and_Answers_Combined_3.xlsx XLSX spreadsheet
Data_Rights_H-Clause_Comments.doc DOC document
GSSC_Questions_and_Answers_Combined_2.xlsx XLSX spreadsheet
ppi_tool.accdb —
ATTACHMENT_19_Award_Fee_Plan_UPDATE_15Jan14.pdf PDF
ATTACHMENT_22_Section_M_UPDATE_9Jan14.docx DOCX document
ATTACHMENT_18_Ground_GFP_UPDATE_15JAN14.xlsx XLSX spreadsheet
Classified_Bidders_List.docx DOCX document
ATTACHMENT_3_CDRL_Instructions_and_CDRLs-UPDATE_16JAN14.pdf PDF
GSSC_Questions_ _Answers_Combined.xlsx XLSX spreadsheet
FA821414R0005_______0001.pdf PDF
ATTACHMENT_4_QASP.docx DOCX document
ATTACHMENT_21_Section_L_Attachments.pdf PDF
ATTACHMENT_20_Section_L.docx DOCX document
ATTACHMENT_9_Software_SOO.docx DOCX document
ATTACHMENT_8_Awardable_TASK_2_RFP.docx DOCX document
ATTACHMENT_18_Ground_GFP.xlsx XLSX spreadsheet
ATTACHMENT_17_DD254.pdf PDF
ATTACHMENT_22_Section_M.docx DOCX document
ATTACHMENT_19_Award_Fee_Plan.pdf PDF
ATTACHMENT_13_Pricing_Matrix.xlsx XLSX spreadsheet
ATTACHMENT_5_Awardable_Task_1_RFP.docx DOCX document
ATTACHMENT_3_CDRL_Instructions_and_CDRLs.pdf PDF
ATTACHMENT_15_GSSC_Labor_Rate_Matri.xlsx XLSX spreadsheet
ATTACHMENT_22_Section_M.docx DOCX document
ATTACHMENT_6_SELM-GMLEC_SOO.docx DOCX document
ATTACHMENT_2_Basic_GRID.docx DOCX document
ATTACHMENT_12_Labor_Category_Description.docx DOCX document
ATTACHMENT_14_Mapping_Worksheet.xlsx XLSX spreadsheet
ATTACHMENT_10_Software_GRID.docx DOCX document
ATTACHMENT_7_SELM_GMLEC_GRID.docx DOCX document
ATTACHMENT_11_Cross_Reference_Matrix.xlsx XLSX spreadsheet
Show all 50

Modification of Equipment has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TASK

IAW Section L para 4.2.3.1.7 The Offeror shall describe their processes, analysis, and rationale that determine their selected corrective action for the sample sustainment scenario. The Offeror shall describe in their solution all actions needed to resolve the situation and what actions they will take that support the Government. The solution shall define the issue, incorporate all appropriate technical documentation and provide full implementation details. The Offeror’s solution shall be complete and take into account the necessary actions to maintain/sustain the weapon system throughout its lifecycle. From the list of documents in the Bidder’s Library, the Offeror shall document in table format all technical documentation that will be affected with incorporation of the proposed solution.

SAMPLE SUSTAINMENT SCENARIO

NOTES

· All information required to answer this sample sustainment scenario is contained within the scenario or in the GSSC Bidder’s Library. The Government will not provide additional information to offeror including requests for information relating to this sample sustainment scenario.

· All assumptions should be clearly stated to ensure the Government team can evaluate the quality, thoroughness, and timeliness of the offeror’s solution and how well it synthesizes the solution activities required to successfully resolve and implement the sample scenario.

· All indications not specifically provided should be considered as achieved, having correct / acceptable indications.

· All supply information provided in this scenario is not necessarily an accurate representation of current status, but should be assumed to be accurate for purposes of answering this sample sustainment scenario.

· T.O. 21M-LGM30F-1-7 is an incorrect reference in T.O. 21M-LGM30G-1-17. An AFTO-22 has been submitted to correct the reference to T.O. 21M-LGM30F-1-24.

While conducting SELM test at Wing 3, Launch Facility Delta 05; the following indications were observed within 5 minutes of completing steps of the T.O. 21M-LGM30G-1-17.

Para: 10.3.6 Execute Launch Command (ELC).

IAW 10.3.6.b. Test ALCC initiated Execute launch command; by sending ELC per T.O. 21M-LGM30F-1-7. Set transmitter to test frequency. Set COMMANDS selector switch to ELC. Set ADDRESS WING and SQUAD switches to test address.

Test LCC reported receiving the following indications for Delta 05:

(11/0011:59) LIP on LAUNCH and ALERT boxes of FLIGHT STATUS display for Delta 05 (12/0000:43) LFNG in ALERT box of FLIGHT STATUS display for Delta 05

LF Status Display Wing 3, Launch Facility Delta 05:

12/0000:45 SECURITY nIZ
12/0000:45 MOSR n21, n48, n60
12/0000:45 GMR n18, n19, n24
12/0004:01 MS LFNI

On-site team initiated Para 11.2.2 and reported the following to TSM:

1. During para 11.2.4 SELM Quick Look Inspection - G&C umbilical was expected to have been released but is reported to still be connected to the missile.

TSM directed the on-site team to initiate para 11.2.7 and report findings before proceeding.

1. On site team reports SCS is in Safe position (no noted anomalies) and now installed SCS safing pin.

Test LCC is requested to initiate a GMI for Delta 05 and report status.

1. Test LCC reports LF Status Display indication; 12/0015:11 LFDN.

TSM directs on-site team to complete and report finding of para 11.2.5 before proceeding.

1. Team reports: 11.2.5 Inspect LF Ordnance.
Step “a” results / observation; G&C umbilical was expected to have been released but is reported to still be connected to the missile.
Step “b” results / observation; the safety control switch shows S; safed by team IAW with TSM direction.
Step “c” results / observation; the missile suspension system ordnance was not expected to be exercised and all lateral restraints are (not actuated) upright in normal operational configuration.

TSM directs on-site team to initiate para 11.2.6 and report findings before proceeding.

1. Team reports the following
a. Record indication observed for following items on coupler set, control-guidance: Item / Indication
On coupler drawer:
28V POWER ON (lamp) / on
G&C POWER ON (lamp) / off
SCS TEST (lamp) / off
b. Record and verify the condition observed for following circuit breakers on power supply group:Circuit Breaker / Condition
POWER SUPPLY A1 & A4 / closed
400HZ POWER MONITOR / closed
PROGRAMMER GROUP (AC POWER) / closed
PROGRAMMER GROUP DC / closed
G&C ELECTRONICS / closed
G&C COOLER / closed
c. Record and verify the condition observed for the following circuit breakers on the distribution box: Circuit Breaker / Condition
NCU ENABLE / closed
G&C COOLER / closed
VRSA POWER / closed

TSM directs on-site team to initiate para 11.2.4 and report findings before proceeding.

1. Team reports the following IAW para 11.2.4.a. G&C umbilical was expected to have been released but is reported to still be connected to the missile.

2. On-site team is directed to complete step 11.2.4.b and report all SCM TCD summary printout, TCD data printout, TCD detail status printouts: On-site team then reports the following indications:

(1) TCD Summary Printout
TCD GO
IGN=00000
RTR=00000
RLS=00000
CLD=19334
LID=00000
ORD=16608
BT3=00000
BT1=00000
MSS=
315 00:11:11.011
TCDSTART
LID=SIM
BT3=SIM
MSS=SIM
UMB=ACT

SYSTEM=A/CDB

YEAR=2011
SITE=740,D, 05
315 11:11:11.011
TCD SUMMARY
(2) TCD data printout.
(a) TCD START
(b) NCU ON
(c) NCU OFF
(3) TCD detail status printout.
(a) UMB
(b) TCD NO GO.
(c) TCD NO GO reports with the following numbers: 036, 050, 051, 052
(d) SSMU WRITE
(e) CHECKSUM=XX

TSM request Test LCC to initiate Ground Maintenance Interrogation.

1. Test LCC reports LF Status Display
12/0025:00 MS LFDN

The TSM and ICBM SD System Engineering Level Evaluation & Correction Team (SELECT) engineering make the following observations from TCD Summary, Data, and Detail Status printouts

•SCS and CSD(G) armed appropriately
•Flight Control and NCU Power On signal appeared to be on less than 5 seconds.
•Msl failed to achieve NCO stage 1 spin –up and TCD was terminated by DCU operations.

Based on scenario reported indications the TSM and ICBM SD SELECT directed the removal and replacement IAW applicable technical orders of the following listed Line Repairable Unit(s) (LRU).

1. Message Processor, C−9211A/GSW−13, P/N 25−74469−41

2. Coupler, Guidance And Control P/N 55100−107−501

3. Control−Monitor, C−9212A/GSW−13 (A6), or C−10153A/GSW−13 (A6)

4. Cable Assembly, Power, Electrical, HRK−959/E24A (W929)

5. Cable Assembly, Power, Electrical, HRK−960/E24A (W930)

6. Cable Assembly, Power, Electrical HRK−961/E24A (W931)

7. Cable Assembly, Power, Electrical, Branched, HRK−954/E24A (W941)

8. Switch Assembly, Launch Enable (S2), P/N 25−74568−1

9. Switch Assembly (S1) (81205 SPEC 10−21328−1), P/N KR76916

10. Relay Panel Assembly, Nozzle Control Unit (A1)

11. Panel Assembly, Load And Relay (A3)

These 11 LRUs were removed and replaced successfully. The site returned to operational status.

RESPONSE 1- From the above list, clarify most likely – to – least probable LRU(s) that caused sample sustainment scenario fault(s), and provide processes, analysis, and rationale for that determination IAW Section L para 4.2.3.1.7.

The repairable Relay Panel Assembly, Nozzle Control Unit (LRU unit) entered the Depot repair shop and AFSC reports the following LRU sub-components are not available from supply. Over the past year, this LRU has failed on 4 occasions leading to removal and replacement of the following items.

1. Relay Assembly, P/N MS25024−2 Asset declared obsolete by DoD supply; active vendors are not clear (without modification) to provide as originally configured by the manufacturer, design control activity, or supplier.

2. Panel Assembly, Fuse, P/N FRB80 Asset declared obsolete by DoD supply; no active vendor identified

3. Capacitor, P/N 43F4110MA4 Asset declared obsolete by DoD supply; active vendor is clear (without modification) to provide as originally configured by the manufacturer, design control activity, or supplier.

The repairable Panel Assembly, Load And Relay (LRU unit) entered the Depot repair shop and AFSC reports the following LRU sub-components are not available from supply. Over the past year, this LRU has failed on 3 occasions leading to removal and replacement of the following items.

1. A3K1, Relay Assembly, P/N MS24143D1 Asset declared obsolete by DoD supply; active vendor is clear (without modification) to provide as originally configured by the manufacturer, design control activity, or supplier.

2. A3A1, Resistor Board, part of P/N 25-74313 Asset declared obsolete by DoD supply; active vendors are not clear (without modification) to provide as originally configured by the manufacturer, design control activity, or supplier.

3. A3A1CR4, Part of P/N 25-74315-3 Asset declared obsolete by DoD supply; no active vendor identified

The repairable Control−Monitor, P/N 25-74470-( ), C−9212A/GSW−13 (LRU unit) entered the Depot repair shop and AFSC reports the following LRU sub-components are not available from supply. Over the past quarter, this LRU has failed on 15 occasions leading to removal and replacement of the following items.

1. Circuit Card Assembly, P/N 25−74330−5 Asset declared obsolete by DoD supply; no active vendor identified

2. Circuit Card Assembly, P/N 25−74334−5 Asset declared obsolete by DoD supply; active vendor is clear (without modification) to provide as originally configured by the manufacturer, design control activity, or supplier.

3. Circuit Card Assembly, P/N 25−74322−6 Asset declared obsolete by DoD supply; active vendors are not clear (without modification) to provide as originally configured by the manufacturer, design control activity, or supplier.

RESPONSE 2-From the above list please provide assessment of LRU sub-component(s) most likely associated (if any) with Wing 3 Launch Facility D05 SELM anomaly scenario, and provide IAW Section L para 4.2.3.1.7 all necessary actions related to this (these) component(s) to maintain/sustain the weapon system throughout its lifecycle.