AIR_SPEC_FD2020-20-50151_REVISED_02.pdf

PDF 407 KB Posted

Attached to
CHARGE ASSEMBLY Federal contract opportunity
Solicitation number
FA8213-20-R-3016
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

This document outlines the requirements for a federal contract to procure charge assemblies. The contractor shall provide 5 charge assemblies under line item 0001AB for delivery within 120 calendar days of award, and an additional 200 charge assemblies under each of line item 0001AD and 0001AE for delivery within 12 months of approval of first article testing. First article test plans and reports are required under line items 0001AA and 0001AC. The contractor must meet all applicable safety and testing requirements for ammunition and explosives. The Department of the Air Force Materiel Command Lifecycle Management Center at Hill Air Force Base is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to CHARGE ASSEMBLY, newest first.
File Type Posted
FA821320R3016-0002.pdf PDF
FA821320R3016-0001.pdf PDF
SPI.pdf PDF
Item_Description_009313590ES.pdf PDF
Engineering_Data_List.pdf PDF
Packaging_Statement_of_Work.pdf PDF
CADPAD_Item_Marking_Instruction.pdf PDF
Rework_and_Repair_of_Nonconforming_Material.pdf PDF
CDRLS_PR.pdf PDF
QALI_CLEA_FD2020-20-50151.pdf PDF
ADC_SOW_Jan2018Final.pdf PDF
GFPFA821320R3016_1.pdf PDF
First_Article_CDRLs_FD2020-20-50151.pdf PDF
REPSHIP.pdf PDF
JFQR_ShapeChargeAssembly_009313590ES.pdf PDF
FA821320R3016.RTF RTF text file
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AIRMUNITION SPECIFICATION

FD2020-20-50151

NSN: 1336-00-931-3590ES

1. The contractor shall provide an advanced Report of Shipment (REPSHIP) to the consignee no later than 24 hours prior to the shipment arrival, and for ammunition shipments no later than two hours after shipment departure. A (REPSHIP) shall include all the following data in accordance with Attached REPSHIP.

2. Department of Defense Identification Code (DODIC): KY69

3. Government Furnished Material:

Stock Number: 1420-01-480-1667 Part Number: 91-00001 Noun: Seething Material Quantity: 6600 FT

4. Contractor shall provide a Government Furnished Material (GFM) consumption report as described in CDRL (DI-MGMT-80438B) – this applies to new production. GFM shall be identified by NSN, lot number, and serial number where possible. Reporting to commence upon receipt of GFM and then every _30_ (reporting frequency). Item Manager Email Address:

nikole.reeder@us.af.mil

5. Ammunition Data Cards (ADC) shall be filled out; input in accordance with Attachment 2, Statement of Work – Ammunition Data Cards; and state quantity/serial number of lot acceptance test units in the remarks block. One hard copy of the ADC shall accompany shipments to each shipping location. CDRL (DI-MISC-80043B)

6. Items shall be marked in accordance with CAD/PAD Item Marking Instruction Version 1.5, 01MAY2019, reference attachment.

7. Shelf Life Code marking NOT required per MIL-STD-129.

8. Hazard Classification Information:

9. Hazard Class/Division: 1.2

10. Storage Compatibility Group: D

11. DOT Marking/Proper Shipping Name: EX2008110058

12. DOT Class/Hazard Class: 1.2D

13. DOT Label/Shipping Label: Explosive 1.2D

14. UN Serial No.: UN0102

15. UN Proper Shipping Name/UN No: Cord, Detonating

16. Net Explosive Weight per item (NEW): 0.003000

17. NEW Unit of Measurement: lbs.

NEW for all packaging/shipping documents shall reflect the NEW identified above per JHCS or IHC. . If NEW is altered to adjust item performance and is greater than the weight listed, an ECP shall be submitted to the government prior to manufacturing or at least 60 days prior to shipping and shall include the SDS (formerly MSDS) and applicable supporting documentation.

18. All Engineering Change Proposals (ECPs), Notice of Revisions (NORs), and Request For

Variances (RFVs formerly RFD/RFWs) affecting the approved product baseline configuration, acceptance test procedures, or manufacturing process of any item(s) on this contract shall be in accordance with EIA-649-B. Major ECPs with NORs and Critical/Major RFVs shall be submitted to the responsible Government Engineering Authority for review/disposition by CCB.

Minor/Administrative ECPs with NORs and Minor RFVs shall be processed by the:

COGNIZANT GOVERNMENT ENGINEER / ACO/CONTRACOTR

ECPs -- CDRL (DI-SESS-80639D) NORs – CDRL (DI-SESS-80642D) RFVs – CDRL (DI-SESS-80640D)

Distribution Statement: _B_, Reason: _ADMIN AND OPERATIONAL USE ONLY_(ref. DoD 5230.24)

19. The contractor shall provide the Lot Acceptance Test Plan (LATP/ATP) for this item(s) in accordance with the contractual data requirements. No changes to previously approved government Acceptance Test Plans shall be made without prior government approval. The Lot Acceptance Test Plan provided must be approved by HAFB engineering at least 90 days prior to commencement of Lot Acceptance Testing allowing for 30 days approval time after submission.

CDRL (DI-QCIC-80553A)

20. Lot Acceptance Test Requirements are: IAW LATEST GOV. APPROVED ATP

21. The contractor shall furnish a Lot Acceptance Test/Inspection Report in the following system(s): WAWF

CDRL: (DI-NDTI-80809B)

22. LOT ACCEPTANCE TEST: In the event of an end item failure, the contractor shall notify the

PCO/ACO and Air Force Engineering Organization within 1 business day.

Air Force Engineering Organization: AFLCMC/EBHJ Organization E-mail: avery.johnson.3@us.af.mil

23. In the event of test failure(s), a Failure Analysis and Corrective Action Report with proposed corrective actions/recommendations is required. CDRL: (DI-SESS-80255A)

24. The age of the energetic materials and components (i.e. ALL explosives, propellants, pyrotechnics, cartridges, and/or initiators) used in the manufacture of these items or sub-components shall not exceed 24_ months based on the original manufacturing date. All energetic materials and components must be traceable to the original DoD qualified manufacturer and compliant with the ITAR part 120 and 121 (http://www.pmddtc.state.gov/regulations_laws/itar.html).

25. This item is designated as a Critical Safety Item (CSI). Documentation for critical characteristics may be found in the contract, TDP, assembly/inspection procedures or QALI.

MRB approval authority shall be retained by government engineer. Other characteristics requiring inspection or special oversight from DCMA: SEE ATTACHED QALI

26. Approval from government engineer is required prior to rework and repair of nonconforming material (see Attachment 5, Clause ES7034)

27. Item unique identification (IUID) marking is required. If required, marking shall be in accordance with MIL-STD-130 and DoD 5000-64.

28. The contractor shall host a post award meeting at the contractor’s facility no later than ____days after contract award and provide minutes of the meeting. CDRL (DI-ADMN-81505) PM email jerry.newland.2@us.af.mil

29. Contractor shall plan and provide a Conference Agenda for all Program Reviews

(PRs)/Technical Reviews (TRs) at their facilities and/or subcontractors facilities.

CDRL (DI-ADMN-81249A) PM Email: jerry.newland.2@us.af.mil

30. Contractor shall prepare and deliver conference minutes for all PRs and TRs.

CDRL (DI-ADMN-81505) PM Email: jerry.newland.2@us.af.mil

31. Contractor shall prepare and submit monthly progress reports documenting program status of milestones, schedule, cost objectives, and technical performance requirements. CDRL (DI- MGMT-80227) PM email: jerry.newland.2@us.af.mil

32. First Article Test/Inspection Report IAW AFMC form 260 CDRL (DI-NDTI-80603A) FAT-Government Test/Inspection, Non-explosive items only) or FAT-Contractor Test)

33. First Article Test Plan and Procedures CDRL (DI-NDTI-81307A)

34. Contracts involving ammunition and explosives (AE) will contain:

- DFARS Title 48 Part 252.223-7002, Safety Precautions for Ammunition and Explosives

- DFARS Title 48 Part 252.223-7003, Change in Place of Performance - Ammunition and Explosives Additionally, if the scope of work includes air shipment of explosives, the safety specification should require contractor compliance with:

- AFMAN 24-204(I), Preparing Hazardous Materials for Military Air Shipments

File details come from the government source that posted it. Updated .