Hill AFB Abatement IDIQ Questions and Answers.docx

DOCX document 13 KB Posted

Attached to
Asbestos Abatement, Hill AFB Utah
Solicitation number
FA8201-21-R-0004
Issued by

View the file

Other files

File Type Posted
(Revised) Hill AFB Abatement IDIQ Questions and Answers.docx DOCX document
Solicitation updated - FA820121R0004.pdf PDF
Past Performance Information.docx DOCX document
Solicitation - FA820121R0004.pdf PDF
03 - SOW APPENDIX C.pdf PDF
WD - Box Elder.pdf PDF
Supplemental Schedule B - Price List.xlsx XLSX spreadsheet
Section L.pdf PDF
IDIQ Abatement SOW-updated.pdf PDF
CDRL QCIC DD Form 1423.pdf PDF
WD - Tooele.pdf PDF
CDRL SSPP DD Form 1423.pdf PDF
Section M.pdf PDF
WD - Daggett Duchesne Rich Summit.pdf PDF
Seed TO - Solicitation Amendment - FA820121R00050001.pdf PDF
Seed TO Bldg100 Bay H SOW.pdf PDF
WD - Morgan Weber.pdf PDF
WD - Wyoming.pdf PDF
Seed TO - RFP Bldg 100 Bay H Rm 221.pdf PDF
WD - Davis.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hill AFB Abatement IDIQ Questions and Answers

1. Question: It says that proposals will be submitted electronically, but does not specify what type of electronically! Will the government accept thumb drives? This will be a large submittal. If government is requesting all data to be sent via; e-mail, what is the size limits that can be accepted if any?

Answer: Proposals should be saved to a CD and mailed to the contracting office. Thumb drives are not acceptable and the file will most likely be too big for an email. Therefore best method is to submit proposal on a CD.

Address to be sent to:
Attention: Kurt Webb and/or Trevor Myers
6038 Aspen Avenue
Hill AFB, Utah 84056

2. Question: Contract clauses Section- I (b) states in order to be considered for award, the offeror is required to implement NIST SP 800-171, the offeror shall have a current assessment (i.e.; not more than 3 yrs old unless a lesser time is specified in the solicitation) (see 252.204.7020) for each covered contractor information system that is relevant to the offer, contract, task order, or delivery order. Is this required for this type of contract?

Answer: Assessment is not required for this type of contract. Contractor does not need to have an assessment to be considered compliant to the proposal requirements.