MACC IV - Q and A Matrix Responses - 18 Dec 2020.xlsx
XLSX spreadsheet 80 KB Posted
- Attached to
- Hill AFB Multiple Award Construction Contract (MACC IV) Federal contract opportunity
- Solicitation number
- FA820121R0001
About this file
This document is a request for proposal for the Hill Air Force Base Multiple Award Construction Contract IV. The purpose is to establish an indefinite-delivery, indefinite-quantity design-build contract covering general construction managed by the 75th Civil Engineering Group at Hill Air Force Base and Utah Air National Guard Base. Task orders will define specific project requirements at these locations as well as remote sites. Proposals are due by January 7, 2021. Accompanying attachments provide the solicitation and bidder's library. Questions are due by December 11, 2020, with government responses by December 18, 2020. The contract specialists and contracting officer point of contacts are identified.
View the file
Other files for this federal contract opportunity
Show all 50
Hill AFB Multiple Award Construction Contract (MACC IV) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Basic SOW
| MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC IV) FA8201-21-R-0001 - 18 Dec 2020 | |||||
| Question # | Reference | Discussion | Question/Comment | Government Response | |
| 1 | 1.5.1.2. | PM Responsibilities | This paragraph does not indicate if the PM is required to be on site. Can this function be completed with off site resources? | This function can be completed with off site resources; however they must be able to get to a project location quickly. The Basic SOW has been updated to state, "The PM shall be located in the local area and be available to be on site with an hour." | |
| 2 | 1.5.1.4 | 1.5.1.4 CQC System Manager – must have experience similar to this contract, CQM for contractors course graduate, full time person on-site, but doesn’t say that Superintendent can wear both hats? | The CQC System Manager and the Superintendent must be separate individuals unless stated otherwise in a task order SOW. | ||
| 3 | 3.1 | Construction Quality Control Plan – Is designated “Lead CQC System Manager” noted in this section the same person as is noted in section 1.5.1.4? Is it possible for Superintendent to also fill this role on TO’s, or is it required to be a separate individual? | The CQC System Manager and the Superintendent must be separate individuals unless stated otherwise in a task order SOW. | ||
| 4 | 3.4.1.1 | Applicability of VPP (Voluntary Protection Program) – contractors and subs have to familiarize | |||
| themselves with OSHA VPP? | Compliance with VPP is required for work completed on an AF installation; therefore, any subcontractors that the prime contractors intend to have work on Hill AFB must be familiar with VPP in order to follow it properly. | ||||
| 5 | 3.5 | Green Procurement – Follow Base Facility Design Standard (BFDS) and Whole Building Design Guide (WBDG) with FAR 11.201(a) exceptions. What does this entail? Similar to LEED requirements? | There are elements of sustainable design that are similar; however, for a more thorough understanding of Green Procurement the Government will included a reference to UFC 1-200-02 in the Basic MACC IV SOW Para 3.5.1. (Revised document will be posted at a later date) | ||
| 6 | Appendices | Appendices noted at the end of this document are not included with attachments on Beta.SAM. Will these documents be provided prior to proposal due date for MACC IV? | This is identified in the Description of the solicitation posting on beta.SAM.gov. Please refer to the posting and thoroughly read the description in order to know how to request the Bidder's Library which contains attachments 06-33. | ||
| 7 | Basic SOW Paragraph 1.5.1.4 states that CQC System Manager and any additional CQC System Managers must be a graduate engineer, architect, or a graduate of construction management with 5 years of experience….or a technician with 10 years of experience. It also stipulates that this person must be on-site at all times and have no other duties. The Solicitation stipulates a task-order minimum of $2,500 and a maximum of $20,000,000. | ||||
| This is a wide range of potential task orders with a wide variety of potential administrative and staffing requirements. Is it the government’s intent that the contractor provide a separate CQC System Manager (with no other duties) for every individual task order within this range regardless of the size, price, and period of performance? Or can this staffing requirement be stipulated on a task-order basis? | Yes, it is the Government's intent to have separate CQC System Managers for all Task Orders within the range of possible projects. |
The Basic SOW already states, "The CQC System Manager is assigned no other duties, except when the Task Order SOW specifically states it is allowed." Therefore, if the size of the project allows for the CQC System Manager to be able to take on other duties, the task order SOW will identify that.
Section L
| MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC IV) FA8201-21-R-0001 - 18 Dec 2020 | |||||
| Question # | Reference | Discussion | Question/Comment | Government Response | |
| 1 | Section L 3.3.3 c | Past Performance | Are the three projects required per Section L 3.3.3 (c) to be the same projects as submitted per 4.3 of Past Performance or are they to be different projects for a total of six? | If they are applicable for both Vol II - Technical and Vol III - Past Performance, then an Offeror may submit the same project(s) to meet both requirements. They are not required to be completely different projects for each technical requirement, and the past performance requirements. | |
| 2 | 3.3 and 3.3.4.5 | Drawing requirements. | Section 3.3 lists the drawing sheets we are to submit. In contract section 3.3.4.5 lists several more drawing sheets and requirements. Which section are we to adhear to? | Section 3.3 provides no instructions and only lists the Technical Subfactors and their elements, while section 3.3.4.5, which is an element of Subfactor 4, provides instructions and details the architectural requirements for the Offeror's to submit. Therefore, adhere to the actual Subfactors (3.3.1, 3.3.2, 3.3.3, and 3.3.4) and their elements (all the sub-paragraphs of 3.3.1, 3.3.2, 3.3.3, and 3.3.4). | |
| 3 | 3.3 and 3.3.4.9 | Drawing requirements. | Section 3.3 lists the drawing sheets we are to submit. In contract section 3.3.4.9 lists several more drawing sheets and requirements. Which section are we to adhear to? This is a large building, all the requirements in this section will not fit on one sheet. | Section 3.3 provides no instructions and only lists the Technical Subfactors and their elements, while section 3.3.4.9, which is an element of Subfactor 4, provides instructions and details the electrical requirements for the Offeror's to submit. Therefore, adhere to the actual Subfactors (3.3.1, 3.3.2, 3.3.3, and 3.3.4) and their elements (all the sub-paragraphs of 3.3.1, 3.3.2, 3.3.3, and 3.3.4). The Government hasn't restricted the submission to only one sheet. The Offeror is able to turn in more than one sheet. | |
| 4 | 3.3.4.7 and 3.3.4.7.1 | Drawing requirements. | Is this section looking for a concrete mix design or a footing foundation plan? What type of details are you specifically looking to see? Is the concrete door product data to be on the drawing or someplace else? | A concrete mix design is only needed for the concrete door per the Sample Project SOW Section 2.8.1.4. A footing foundation plan will be required per the Sample Project SOW Section 2.8.1.4. The concrete door product data or design should be included in the drawings. Product data for alternate door can be included in the technical proposal and/or in the drawing set. | |
| 5 | 3.3 and 3.3.4.8 | Drawing requirements. | Section 3.3 lists the drawing sheets we are to submit. In contract section 3.3.4.8 lists several more drawing sheets and requirements. Which section are we to adhear to? | Section 3.3 provides no instructions and only lists the Technical Subfactors and their elements, while section 3.3.4.8, which is an element of Subfactor 4, provides instructions and details the concept mechanical drawing requirements for the Offeror's to submit. Therefore, adhere to the actual Subfactors (3.3.1, 3.3.2, 3.3.3, and 3.3.4) and their elements (all the sub-paragraphs of 3.3.1, 3.3.2, 3.3.3, and 3.3.4). | |
| 6 | 3.3 and 3.3.4.8 | Drawing requirements. | Section 3.3 lists the drawing sheets we are to submit. In contract section 3.3.4.9 lists several more drawing sheets and requirements. Which section are we to adhear to? | See response to Question 3 above. | |
| 7 | 3.3.4.5 | Drawing requirements. | This is the only section that mentions "concept drawings" 15% level. Are all 8 sample project drawing sheets to be developed to the 15% level? Other sections in the SOW descrime much more detail be shown than a 15% would have. Clarify what is to be shown on the 8 drawing sheets | The information needed for drawings that are required for proposal submission for the MACC IV Basic IDIQ award are detailed in Sections L&M. The information required for each drawing is at a15% level; however, there are specified calculations that are also required. | |
| 8 | Section L- 3.3.3 Subfactor 3: Contractor Requirements | Subsection b instructs the offeror to submit 3 design-build example projects that meet the required location and dollar value criteria. | |||
| Subsection c instructs the offeror to submit 3 design-build example projects demonstrating experience working with all the listed disciplines. | It is unclear whether the projects in subsection b are the same as the projects in subsection c. If they are the same, the offeror would submit a total of 3 projects. If they are different, the offeror would submit a total of 6 projects. Please clarify the total amount of projects the offeror is to submit under this section. | See response to question 1 above. | |||
| 9 | Section L- 3.3.2 Subfactor 2: A-E Qualifications | Subsections a, c, and d all require the submission of project examples, but a required format is not listed. | |||
| Subfactor 3: Contractor Requirements requires use of Appendix C to format project examples listed under that section. | Please clarify how the project examples are to be formatted under this section. | Section L, Appendix C will be updated to provide more detail on what Offerors need to submit for example projects. (Revised document will be posted at a later date) | |||
| 10 | Section L- 4.0 Factor 3: Past Performance | This factor requires submission of relevant past performance evaluations for the offeror and joint venture members, but no contracts are requested for the A-E firm. | Please clarify whether or not past performance evaluations are required for the A-E firm. | Past Performance is required for the A-E partner and Section L 4.1 and Section M 5.0 will be updated to reflect this change. (Revised documents will be posted at a later date) | |
| 11 | Attachment 2 |
Section L, 3.3.2 Subfactor 2: A-E Qualifications: b)
| pg 14 of 30 | A-E Qualifications shall be submitted on Standard Form (SF) 330, Section L Appendix D, for each discipline: Architectural, Civil, Structural, Electrical, Mechanical, and Fire Protection Engineering. A minimum of 15 years of experience as a licensed Professional is required for each Engineer of Record for each discipline, with the exception of the Fire Protection Engineer which must have a minimum of 5 years of experience. In addition, the example project, including calculations, must be signed and stamped by a licensed Professional Electrical Engineer. | Should SF330 Part IIs be include in Subfactor 2 for the A-E Design Firm and potential design subcontractors? | Yes. | ||
| 12 | Section L 3.3.2 a) | 3.3.2 says "Past project examples shall be formatted IAW Section L, Appendix C". a) says "the example project, including calculations, must be signed and stamped by a licensed Professional Electrical Engineer." | Please define whether only that information listed in Appendix C: Example Project Template is to be provided or if "calculations" are to also be provided. Please define what if any documantation submitted within this subfactor is to be "signed and stamped by a licensed Professional Electrical Engineer". | Section L, Appendix C will be updated to provide more detail on what Offerors need to submit for example projects. Calculations may be included as an attachment to support the example project's reason for meeting the specific requirement. In addition Section L 3.3.2.a. will be updated to specify what the offeror needs to submit in order to show the calculations are certified. (Revised documents will be posted at a later date) | |
| 13 | Section L 3.3.2 and Appendix C | 3.3.2 says "Past project examples shall be formatted IAW Section L, Appendix C" Apendix C, 1. says "If the contract was not direct with the end user, then the example project experience is not considered to be Prime Contractor Experience" | Must A/E Qualification be performed undar a contract "direct with the end user" or may they be performed under a sub contract to a Prime Contractor such as in a design build delivery method projectt? | For the A-E firms, they can be either direct contracts with the end user or as a subcontractor on a design-build contract. Section L, Appendix C will be updated to provide more detail on what shall be submitted for example projects. (Revised documents will be posted at a later date) | |
| 14 | Section L 3.3.2 b) | 3.3.2 b) says "Qualifications shall be submitted on Standard Form (SF) 330" It also says "the example project, including calculations, must be signed and stamped by a licensed Professional Electrical Engineer" similar to 3.3.2 a). | Please confirm that all of Subfactor 2 including including example projects described 3.3.2 in sub-paragraphs a), c) and d) are to be submitted on Standard Form (SF) 330. | No, all example projects in Subfactors 2 and 3 are to be submitted IAW Section L, Appendix C and not submitted on the SF330. | |
| 15 | Section L 3.3.2 d) | 3.3.2 d) says "examples of three (3) past projects". 3.3.2 sub-paragraphs a) and c) describe example projects with specific atributes. | Please confirm whether the example projects described in sub- paragraphs a) and c) are in addition to those of d) (5 total example project are to be submitted) or if the specific attributes required in a) and c) must be demonstrated within the projects submitted under d) (3 total example projects are to be submimtted). | Each subfactor element must be met. It is up to the Offeror to determine how they will do this. If the Offeror has an example project that can satisfy more than one example project requirement, they may submit that one project to satisfy those example project requirements as long as they identify in their proposal how the project meets the different requirements. Therefore, the number of projects submitted will be up to the Offeror. | |
| 16 | Section L 3.3.2 d) and Section M 4.2 d) | 3.3.2 d) and 4.2 d)say "similar in scope with regards to complexity, cost, and size of the Sample Project.". | This statement is arbitrary. Please provide specific metrics for past projects that define similarity "with regards to complexity, cost, and size". | The Sample Project SOW provides enough information for offerors to determine scope and complexity, and the cost information is available from the magnitude of the project provided in the TEP matrix and by the Offeror's proposal. This is sufficient information for Offeror's to determine what past performance projects they should submit. | |
| 17 | 1.3 Table 1 - Volume II Page Counts | Subfactor 1 - 30 page limit | Sub Factor 1 of Volume II has a page limit of 30 pages. This subfactor requires submission of an overall safety plan and QC Plan. Please exclude page limits for this section to allow for submission of thorough Safety/QC Plans. | The Government has changed the page limit for Subfactor 1 to 50 pages. | |
| 18 | Subfactor 2 - AE Qualifications SF330; paragraph b. | Paragraph b requires submission of AE Firms SF330 for following disciplines: Architectural, civil, structural, electrical, mechanical, and fire protection engineering. | AE Teaming Agreement from MACC SOW Paragraph 1.5.1.5 also requires a Geotechnical Engineer and LEED AP or Green Building Initiative Accredited Professional. Do we need to submit SF330 for the Geotechnical Engineer and LEED AP in addition to disciplines listed in this section? | No, the Government has determined that a Green Building Initiative AP is not necessary and the requirement will be removed from the Basic MACC IV SOW para 1.5.1.5. The Government has determined that evaluating the LEED AP and the Geotechnical Engineer is not necessary to determine acceptability for IDIQ award; however, it is a requirement of the SOW and all the awardees will be required to adhere to SOW requirements. |
(Revised document will be available at a later date)
| 19 | Subfactor 2 - AE Qualifications Past Projects; paragraph a, c, and d | Past Projects | Paragraphs a, c, and d all required past projects to be submitted. Paragraph a requires a past project showing short circuit analysis, arc flash, voltage drop, etc.; paragraph c requires past project for LEED AP; and d requires 3 projects similar in size, scope, complexity, and cost. Do we need to submit 3 or 5 past projects for the AE firm? | See response to Question 15 above. |
| 20 | Section 5.1.3 | Section I - Contract Clauses | Are there any submission requirements for this section? | Yes, Offerors must fill-in each of the clauses that require Offeror's to fill-in and submit that with the Volume IV. |
| 21 | 5.1.4 | Section J - List of Documents, Exhibits, and Other Attachments | Are there any submission requirements for this section? Attachment 4 - TEP is to be submitted in Volume I. | Section J does not require Offeror's to submit anything; rather, it provides the attachments they will need in order to successfully submit their proposal. |
| 22 | Please specify what information should be provided under Volume I, Factor 1, Section 3 – General. | It is up to the Offeror to decide what information to provide within the General section. | ||
| 23 | Volume III, Factor 3: Past Performance asks offerors to provide information on a maximum of three “contracts.” Please clarify what is meant by the term “contract” – does it refer to an IDIQ-type contract, or an individual project/task order? | Contract refers to any contracted project that is similar in scope and complexity to the technical requirements and is active or completed within the past five (5) years from the issuance date of this solicitation. | ||
| 24 | Volume III, Factor 3: Past Performance states that offerors should provide three contracts for the Offeror “and three (3) contracts, if available, for any joint venture members.” Does this mean that, if we are a joint venture, we should provide three contracts for the joint venture, as well as up to three contracts per joint venture member? In that case, we would have up to nine contracts – three for the joint venture itself, and three for each member company. | Offerors shall provide three (3) contracts for their company, three (3) for their joint venture partner, and three (3) for their A-E partner for a total of nine (0) contracts. | ||
| 25 | Can the government provide the sign-in sheet from the site visit? | Yes, it has been posted. | ||
| 26 | Will the sample project be awarded? | See response to Question 6 in Draft Solicitation Tab. | ||
| 27 | Subfactor 4 Volume 2. | Confusion about number of pages allowed | 2. The subfactor 4 of volume 2 says the APP has no max page limit. However, Subfactor 1 for Safety and CQC plans per the chart are limited to 30 pages total. This seems reverse. i.e. the master corporate Safety and QC are limited to 30 pages, however; the sample project CQC and Safety plans are unlimited. Please clarify. | See response to Question 17 above. The Sample Project Safety/Accident prevention plan will remain unlimited as the Government wants to see more specific details at the project level; therefore the Sample Project Safety/Accident Plan page limit is unlimited. |
| 28 | Section L; 3.3.2 Subfactor 2: A-E Qualifications; a) & b) |
Section M; 4.2 Subfactor 2: A-E Qualifications; a) Section L
a) One (1) example of the A-E firm’s past project containing short circuit analysis and coordination, arc flash, and voltage drop calculations. The example project shall be similar in scope in regards to complexity, cost, and size of the Sample Project (Subfactor 4). In addition, the example project, including calculations, must be signed and stamped by a licensed Professional Electrical Engineer. Example project shall be less than seven (7) years old from the issue date of the RFP.
b) A-E Qualifications shall be submitted on Standard Form (SF) 330, Section L Appendix D, for each discipline: Architectural, Civil, Structural, Electrical, Mechanical, and Fire Protection Engineering. A minimum of 15 years of experience as a licensed Professional is required for each Engineer of Record for each discipline, with the exception of the Fire Protection Engineer which must have a minimum of 5 years of experience. In addition, the example project, including calculations, must be signed and stamped by a licensed Professional Electrical Engineer.
Section M
a) The Offeror’s proposal for this subfactor element is technically acceptable when the Offeror provides one (1) example of the A-E firm’s past project which must include a short circuit, coordination, arc flash, and voltage drop calculations. Additionally, the example project must be similar in scope in regards to complexity, cost, and size of the Sample Project (Subfactor 4). The example project shall be less than seven (7) years old from the issue date of the RFP. The example project, including calculations, must be signed and stamped by a licensed Professional Electrical Engineer. The statement “the example project, including calculations, must be signed and stamped by a licensed Professional Electrical Engineer” is mentioned several times in Sections L and M for Subfactor 2. However, as written the statement could be viewed as simply a criterion that the example project must meet or a request to included signed calculations with the example project.
Is the Government is expecting offerors to provide evidence that this requirement was met and, if so, what type of evidence does the Government want to see included with the SF330? Section L 3.3.2.a and Section M 4.2.a. will be revised to clarify what is needed for stamped and signed requirements. Section L 3.3.2.b. that was referenced is an old copy and the portion mentioned no longer exists.
(Revised documents will be posted at a later date)
| 29 | Section L | 3.3.1.1 Safety Plan - Offeror shall submit an initial Contract Occupational Safety and Health Plan that meets the requirements outline in MACC IV Basic SOW, Section Appendix C. This section allows 30 Pages for both Safety and QC Plans. Appendix C provides direction on what is to be included in the safety plan and includes bulleted items as well as an extensive list of detail items. It also states "The contractor shall ensure that each element identified below is adequately addressed in detail in the safety and health plan: " | Are we to inlcude detailed information for all of the additional list? If so, this will not fit in the 30 page limitation along with the QC Plan. Can these Items be eliminated from the requirement? | See response to Question 27 above. |
| 30 | Section L | Under Volume 2 – Section 6: Subfactor 2, paragraph 3.3.2.a - A-E Project Example, it states “…In addition, the example project, including calculations, must be signed and stamped by a licensed Professional Electrical Engineer…” These signed calculations are more than 20 pages long. | Due to the 75-page limit for subfactor 2, will the government please EXCLUDE the calculations from the page limits for Subfactor 2? OR will the government please remove the requirement to provide calculations in response to 3.3.2.a. | See response to Question 12 above. |
| 31 | Section L | Paragraph 1.3.6, Cross Referencing states that each volume shall be written on a stand-alone basis; however, the instructions for Volume IV, Section J - List of Documents, Exhibits and Other Attachments, require us to cross reference the TEP, which is provided in Volume I. | Please confirm that it is acceptable to make reference to the TEP in Volume IV, even though it is required to be provided in Volume I, Factor 1: Cost/Price | Yes, Offerors can reference in Volume IV to the TEP that will be submitted in Volume I. |
| 32 | Section L | 6.1.1 requires us to submit any exceptions to the solicitation requirements, if any. Is it acceptable to provide any exceptions at the end of Volume IV: Contract Documentation? | Yes, it is acceptable to include the exceptions formatted IAW Section L, Table 2, at the end of Volume IV. | |
| 33 | Given the fact that we have not been able to download and save the PPI Tool required for Volume III, Factor 3, would the government allow submission of Volume III on the proposal due date rather than requesting submission 10 calendar days prior to the proposal due date? | Volume III is only requested to be submitted ten (10) days prior to the proposal due date; however, it is not required to be submitted at that time. It is acceptable to submit Volume III by the proposal due date if desired. | ||
| 34 | 1.1 | Volume III, Past Performance is due 10 days prior to the rest of the Proposal volumes. Will any feedback be available within that 10 day period? Ie: past performance does not meet requirements, some offerors are eliminated before proposal date? | No, a thorough review of proposals must be completed in order to determine who will be included and excluded form the competitive range. No clarifications, communications, or discussions will be achieved before the proposal due date. | |
| 35 | 2.6 | Cost Accounting Standards – small businesses don’t have to follow CAS. Does that also apply to JV’s? | Yes. | |
| 36 | 3.3.3 | Past performance question about 3 examples – can non-DB past projects be used? Or lack of DB experience on military or aviation projects problematic? | Any past projects that are similar in scope and complexity to the Sample Project or the projects that are required for examples in the technical Subfactors may be submitted for evaluation. | |
| 37 | 4.1 | Past Performance, General – This paragraph says 5 years, but other locations in this document say 7 years. Which is correct? | For Past Performance (Vol III) the Government has deemed contracts that are active or completed within the last five (5) will be sufficient to evaluate an Offeror's past performance. For Technical (Vol II) the Government has deemed contracts completed or at the Beneficial Occupancy Date within the last seven (7) years to be sufficient to evaluate an offerors technical capabilities. | |
| 38 | Section L / 3.3.3 | “Contractor Requirements” (b) Identifies the offerors D-B past performance requirements. Considering that three D-B project examples are required to be contractually completed with one (1) valued over $5m and two (2) valued at least $2m, this may be allot to require of a small business. | (1) Can the past performance of potential subcontractors / team members be utilized to demonstrate relevant experience? | The Government is looking for past performance from the Prime, Joint Venture Members and the A-E partner team. The Government is not looking for subcontractor past performance because the subcontractor's used can change from project to project. |
| 39 | The past performance requires that the example projects must be “contractually complete” as per the date of the RFP issuance date. Would the government consider changing this requirement to the example project being “substantial complete” versus “contractually complete”? | Past Performance in Section L 4.1. allows for "as active or completed efforts performed within the past five (5) years." The Example Projects required for the Technical Subfactors did require contractually complete contracts; however, the Government has decided to included projects that are not contractually complete but have received Beneficial Occupancy. Section L, Appendix C will be updated to provide more detail on what Offerors need to submit for example projects. |
(Revised documents will be provided at a later date)
| 40 | Section L/4.1 | 4.1 General states that the Past Performance evaluation, recency is defined as active or completed efforts performed within the past five (5) years from the issuance date of this solicitation. This requirement defines the PP evaluation example project(s) limited to past 5 years and defined active or completed efforts relevant. | Please clarify the past performance contradictions between Section L 3.3.3 and 4.1? | See response to question 37 above. |
| 41 | Attachment 05 - pg. 22 |
Attachment 02 - pg. 7
6.2.4.2 Paper Copies: The contractor shall submit six (6) copies of proposal. The proposal shall include accompanying folded half (½) size drawings (11” x 17”) in one spiral bound volume. Drawing sheets shall be correct order of reference withing the respective sections.
Volume II - Technical - Total Page Limits: 260 - Number of Paper Copies: 5 - Number of Electronic Copies: 2 Are we to provide 5 or 6 paper copies? The Sample Project SOW para 6.2.4.2 and Section L, Table 1 will be updated to state "three (3)" copies rather than five (5) or six (6).
(Revised documents will be provided at a later date)
| 42 | Due to the extreme increase in Covid-19 cases and mutiple prime employees have been unable to work, can the proposal due date be extended? | See response to question 16 in the Section L tab of the MACC IV Q and A Matrix Responses - 11 Dec 2020 - FINAL. | |||
| 43 | 3.3.2 Subfactor 2: A-E Qualifications | Section b requires submission of A-E qualifications of SF330. The SF330 is a 14 page document with many different sections requiring information other than architect/engineer personnel qualifications. For example, relevant project information is required on the SF330, but relevant projects are already being submitted for the A-E firm as part of the proposal. | Please confirm only section E, Key Personnel of the SF330 is to be filled out for each architect/engineer and submitted for this proposal. | All parts of the SF330 are to be filled out, except Section F as indicated in Section L 3.3.2.b. | |
| 44 | Proposal Submittal | Would the Government please consider accepting the proposal electronically. Because of the COVID virus, we have been informed that the usual carriers cannot guarantee delivery of packages on time. This makes the completion of the proposal difficult, given that trades contractors will deliver their pricing close to the delivery time. Thank you for your consideration. | Section L 1.1, 1.3.1, and Table 1 will be updated to reflect that electronic copies must be sent via DoD Safe safe.apps.mil, and that paper copies must be received by the Contracting Officer no later than five (5) business days after the proposal due date. | ||
| 45 | Section L Paragraph 3.3.1 Technical Subfactor 1 | Section L Paragraph 3.3.1 Technical Subfactor 1 – Section L stipulates a 30 page limit for the entirety of Technical Subfactor 1 to include both the Safety Plan and the CQC Plan. | |||
| The applicable specifications identify several sample documents that should be included as part of these plans. It will be very difficult to squeeze these two plans into 30 pages total with all of the applicable appendices. Can we include sample templates as a separate appendix outside of the stipulated page limit, or is there some way to increase said page limit on Subfactor 1? Suggest increasing this page count to at least 50. | See response to Question 17 above. | ||||
| 46 | Attachment 02-Sec L, 1.3 Volume Org- 1.3.1 Table 1 | Increasing the Number of Copies allowed for Subfactor 2 | Would the government consider increasing the number of allowed pages from 75 to 100 for 3.3.2 Subfactor 2: Architect-Engineer (A-E) Qualifications? | Yes, the Government will update Section L Table 1 to reflect 100 pages for Subfactor 2 instead of 75. | |
| 47 | Attachment 02-Sec L, 1.3 Volume Org- 1.3.1 Table 1 | Excluding the SF 330 form from the 75 page limit for subfactor 2 | Would the government consider not including the A-E Qualifications Standard Form (SF) 330, Section L Appendix D, for each discipline in its 75 page limit for subfactor 2 ? | See response to Question 46 above. The Government has determined that the additional allowance for pages is sufficient. | |
| 48 | Attachment 02-Sec L, 3.3.2 Sub 2-A-E Qualifications paragraph c | LEED Past Projects | The government is asking for a past project certified silver or greater. Is this project to involve LEED certification? | The Sample Project requirements in Technical Subfactor 4 do not require LEED certification. | |
| 49 | Attachment 02-Sec L, 3.3.3 Sub 3-Contractor Req paragraph b&c | Past Projects | Can the 3 requested projects in paragraph ( b ) showing Design Build experience be combined with the 3 requested projects in paragraph ( c ) showing experience in the stated disciplines? | If the offeror has an example project that can satisfy more than one example project requirement, they may submit that one project to meet more than one example project requirement as long as they identify in their proposal how the project meets the different example project requirements. | |
| 50 | Attachment 02-Sec L, 3.3.3 Sub 3-Contractor Req paragraph b&c | Past Projects | Can the 3 requested projects in paragraph ( b ) showing Design Build experience be same projects as the 3 requested projects in paragraph ( c ) showing experience in the stated disciplines? | See response to question 15 above. | |
| 51 | Attachment 02-Sec L, Appendix A - Printing Reports and Submitting PPI Tool | PPT Tool | Please confirm that we are to include hard copies from the PPT database in our Past Performance Volume III. | Section L, Table 1 will be revised to remove the requirement for a hard copy submission of the Offeror's Volume III - Past Performance. | |
| 52 | Section 3.3.1.2 Construction Quality Control Plan states to provide a QC Plan in accordance with the Basic SOW and UFGS 01 45 00. The UFGS calls for information regarding definable features of work as well as specific testing including name spec and frequesncy | Is this QC plan to be specific to the seed project or to the overall MACC? If it is the overall MACC How should we include specific testing and Features of Work?. | The CQC Plan required in 3.3.1.2 is for the overall MACC IV, and the CQC Plan required in 3.3.4.2 is required for the Sample Project. |
For the overall MACC IV CQC Plan Features of Work and specific testing are not required, but will need to be identified in each task order.
For the Sample Project CQC Plan Features of Work and specific testing should be included for the Sample Project, B2113.
| 53 | Attach 1 - 1.5.1.5 | ||||
| pg 7 of 17 | Geotechnical Engineering is discussed in the Basic SOW (1.5.1.5) but it is not mentioned in Section L, Vol. 2, Factor 2, Subfactor 2 and 3. | Is Geotechnical Engineering a required discipline? | Yes, it is a required discipline for the task order projects; however, the Government has not deemed it necessary to evaluate for award. | ||
| 54 | The wage determinations included in the solicitation package appear to be outdated. Please provide the latest wage determinations. | Updated Wage Determinations will be posted soon. |
Section M
| MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC IV) FA8201-21-R-0001 - 18 Dec 2020 | ||||
| Question # | Reference | Discussion | Question/Comment | Government Response |
1 Section M; 4.2 Subfactor 2: A-E Qualifications; a) Please see question under Section L Tab. See responses to Section L questions in the Section L tab.
TEP
| MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC IV) FA8201-21-R-0001 - 18 Dec 2020 | ||||
| Question # | Reference | Discussion | Question/Comment | Government Response |
| 1 | Attachment 04 TEP Matrix | The government will apply a Notational number of hours multiplied by the rates provided by the contractor for the 4 project management positions noted as part of the evaluation of offers.. | Should the contractor include their own project management costs for these managers in their general conditions within the sample task order or will the government compensate them according to the Notational Amount matrix? Or is this matrix strictly for evaluation purposes and not contractural? | The TEP is for evaluation purposes; however, IAW Section L 2.2 the fully burdened labor rates will be contractually binding for the IDIQ. |
| 2 | Sample Project Division Detail | Sample Project Division Detail - Divisions 35, 41, 44 | Please clarify what specs/scope of work is included in Divisions 35, 41, and 44. | The specs/scope of work for all Divisions are available in the Sample Project SOW. It is up to the Offeror to determine how to break out the proposal into the different Divisions. |
| 3 | Pricing form | Formulas don't work | Having worked with your pricing form before I wish to note you have removed the formulas from some of the columns. Therefor the sub and self perform items to not add. All numbers must be hard entered in final form direct. Please correct the Xcell pricing form. | The reason there are no formulas in the Base Totals are because the Government does not know the Division Breakout of all the offerors. For example, some offerors could propose the concrete task will be completed by the prime and another offeror might have the concrete task completed by the subcontractor. If that is the offeror’s question, I believe it is stated in the notes that the blue cells are required to be completed by the offeror and the sum of the Base Totals needs to equal the Division Breakout. |
Sample Task Order SOW
| MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC IV) FA8201-21-R-0001 - 18 Dec 2020 | ||||
| Question # | Reference | Discussion | Question/Comment | Government Response |
| 1 | Can photos of the exisiting electrical equipment be provided? Photos of the existing disconnects, panels, etc. will assist in the required design. | The Government intends to provide photos of existing panels and disconnects as a new attachment. |
(This new attachment will be provided at a later date.
| 2 | In Regards to the Control Center Stations. Will these be government furnished? If not Can specific information for the required equipment be provided. | Yes Government will provide system furniture for control stations. | |||
| 3 | 2.1.4 | This section instructs the contractor to demolish the restrooms and associated components | Please clarify in which Bays restrooms are to be demolished. | See response to question 187 below. | |
| 4 | 2.5.3.2.1 & 2.6.3.3.1 | These sections state Bays 2, 4, 5, 6, and 7 require compliance with DoD Explosive Safety requirements and reference an Appendix outlining these requirements. | Please provide the appendix with DoD Explosive Safety standards to be followed in Bays 2, 4, 5, 6, and 7. | Bays 2 and 4 are the only bays with explosive standards. Bays 3,5,6. are within the explosive footprint | |
| 5 | 2.7.3.2 | This section requires installation of new secondary service conductors from the utility transformer. | |||
| At the site visit held on 12/3/2020, it was noted the existing conductor insulation is cracked, and the conductors appear to be damaged. | Please confirm the existing conductors cannot be reused, and that new conductors must be installed. | New secondary conductors shall be provided to replace the existing. | |||
| 6 | 2.2.16. & |
2.2.17.3 &
| 2.2.18.3 | These sections require the contractor to provide office trailer units with HVAC hookups for the temporary housing of records during construction. | Please clarify the size and quantity of trailer units to be provided. | For bidding purposes provide (4) 60' x 24' modular office trailer units with standard 8' ceiling height and approx. 1340SF. For each trailer unit provide the following: 1. Provide ADA stair and ramp system. 2. Provide 7' high and 15" deep double backed shelves with engineered seismic rated bracing. 3. Provide ADA spacing for shelf system throughout. 4. Provide additional illumination in order to provide sufficient lighting between stacks. 5. Ensure trailer is structurally capable of supporting a load of 120 lbs/SF. | ||
| 7 | 5.3 | Site Visit - Contractor shall perform a site visit with the AE Design Team to review existing conditions in order to obtain the information required to complete the bid. | Will another site visit be permitted in order to review the existing site conditions with the AE team? | Another visit will not be permitted due to time constraints. | |
| 8 | 5.3 | Site Visit - Contractor shall perform a site visit with the AE Design Team to review existing conditions in order to obtain the information required to complete the bid. | Will AE team be able to perform laser scanning during site visit to get accurate dimensions. | Laser measuring was allowed during the site visit. | |
| 9 | 1.1 | Sample Project | Is the sample project going to be awarded? If not now, is the intent to award at a later date? | See response to Question 6 in the Draft Solicitation tab. | |
| 10 | 1.3 | Project Management | What is management requirements for this sample project? PM, Super, QC, Safety? Onsite or offsite? | Refer to MACC IV Basic SOW and B2113 Sample Project SOW for this information. | |
| 11 | 1.4.1 | Coordination with other HAFB Entities | What is the process for gaining access to the secured area? Will an escort be needed? | The Contractor Awardee of the Sample Project will be provided with the necessary information to acquire access to the secured area. | |
| 12 | Site Visit | Photos | No photos were allowed at the site visit of the project due to the secured location/facility. Will construction photos be allowed to be taken during the course of construction? | After award of the Sample Project photos may be permitted as coordinated with the User. Limited photos may be taken but not by the contractor. | |
| 13 | Layout | Laydown yard | Will laydown yard be available during construction? | Yes. This will be coordinated with the User when the Sample Project is awarded. | |
| 14 | Layout | Haul Route | What is the haul route for deliveries/debris removal? Is there a place on base where materials/dirt may be dumped? | All material must be removed from the Base and properly disposed of. | |
| 15 | Layout | Site Fencing | Does project need construction fencing around site? | No. | |
| 16 | Layout | Site Utilities | Will hydrants be able to be used during construction? Are there any special requirements for use (backflow preventer, etc.)? | Yes, but the Contractor will need to coordinate this with the COR and/or the CE utility shops. | |
| 17 | 1.4.1 | Coordination with other HAFB Entities | Will facility be occupied during construction? | Yes, but very limited. | |
| 18 | 2.1 | Demo | Will any items be salvaged by the base? Will salvaged items be picked up by the base or will contractor need to deliver to location? | The Government will remove saved items. | |
| 19 | 2.1.4 | Restrooms | Please provide photos and more details on existing restrooms, partition walls, etc. (layout, height, location, etc.) | See response to question 187 below. | |
| 20 | 2.1.5 | Demolition of existing X-Ray Equipment | Are there any special safety/training certifications or requirements for demolishing/handling the x-ray equipment? | There are no special certifications. Contractor should have suitable sub-contractor involved. | |
| 21 | 2.1.5 | Demolition of existing X-Ray Equipment | Are there any transportation/traffic/driver requirements for removing and transporting the X-ray equipment? | The X-Ray equipment will not be removed but modified and upgraded. This will be clarified in the Sample Project SOW. |
(Revised document will be posted at a later date)
| 22 | 2.2.1 | Exterior - Seismic Standards - Section 2.2.1 states that "The Contractor shall ensure the existing structure is up to current seismic standards following 2018 international Existing Building code (EIBC). | Will project need to be brought up to current seismic standards? | Seismic upgrades to the building will not be required. The only work needed is listed in the SOW. |
| 23 | 2.2.2 | General - Existing Furniture/Equipment | Please confirm all existing furniture/equipment will be moved/relocated by end user. | All furniture/equipment the Government wants will be removed and stored by Government. |
| 24 | 2.2.4.7 | Surveillance System High Resolution | Contractor to install a 6-point camera system with high resolution. Please give specs on high resolution as there are varying levels of high resolution and costs associated with this. | High Resolution 5MP 2592X1944 |
| 25 | 2.2.5.4 | Control Center Station | Please provide specs on new control center video screens; ICT x-ray equipment computer; and observation instruments. | Must support 5MP2592X1944 in a 32" Video monitor screen |
| 26 | 2.2.7 | Bay 5 Unoccupied Munition Storage | Bay 5 currently houses the fire riser on the west end of the building. Is this fire riser to remain? | The fire suppression for the facility is to be brought up to code including the riser. Contractor's Fire Protection Engineer must be the one to evaluate these requirements and whether or not the current riser must be demolished or repaired to meet them. If the existing riser will not be utilized it must be demolished back to the main water line. |
| 27 | 2.2.15 | Bay 13 Unoccupied Storage Bay | Bay 13 currently has ACT. Is this to remain or be demoed? Is new ACT required in this space? | The Government is assuming the question meant to refer to VCT rather than ACT. |
Yes, it has to be demoed.
No, a new VCT is not required.
| 28 | 2.3 | Site Work | Is there any additional site work for this project aside from Sections 2.3.1, 2.3.2, and 2.3.3? For example, any repairs to sidewalk, remaining asphalt outside of areas listed, etc.? | There is no additional site work anticipated for this project. |
| 29 | 2.4.1 | IDS/Secure Room | Is Bay 16 the only bay to receive IDS and be classified as an Secure Room? Or is this applicable to entire facility? | Yes, Bay 16 is the only bay to receive IDS and classified as a Secure Room. |
| 30 | 2.4.1 | Secure Room | Is wire mesh required over windows in this room to meet Open Storage (Secure Room) standards? | Please refer to DoD Manual 5200.01, Volume 3, Appendix to Enclosure 3, as stated in paragraph 2.4.1. |
| 31 | 2.5.7.2 | Fire Alarm Conduit | Can fire alarm wire be free aired above ACT or does all fire alarm wiring need to be in conduit? Does conduit need to be red? | All fire alarm wiring shall be run in conduit with approved makings for fire alarm use. |
| 32 | The General scope 1.4.2. Asbestos and Lead Removal States. Refer to the asbestos and lead based paint report. Provide proposal by an approved asbestos and lead-based paint abatement contractor to address the mediation and removal of hazardous materials Identified in the report. I just want to clarify that the abatement contractor is to use the provided survey for bidding purposes? | Yes, rely on the reports provided for bidding purposes. | ||
| 33 | Section 2.6.4.4 Mentions 4 existing steam vaults to be demolished and removed. These vaults are not mentioned on the asbestos survey report. Can the Government verify if there is asbestos thermal system insulation on the steam lines inside the vaults? | Yes, the Government can confirm there is asbestos. |
Please note an update will be made to the Sample Project SOW Section 2.6.4.4 which will require only two (2) of the steam vaults to be demolished.
| 34 | Attachment 21 of the RFP is indicating much more structural work and blast protection. Please confirm the work we need to figure is only the work listed in the SOW. | See response to Question 22 above. | ||
| 35 | Please provide a map for the site utilities (gas, sewer, water…). | A site map with all known utilities has been posted. | ||
| 36 | The sample project SOW states the contractor shall ensure the existing structure is up to current seismic standards following the 2018 International Existing Building Code (IEBC). Is it the government’s intention to do a seismic upgrade to the building? | See response to Question 22 above. | ||
| 37 | 2.2.1: The contractor shall ensure the existing structure is up to current seismic standards following 2018 International Existing Building Code (IEBC). | Is the SOW requiring full seismic investigation? Is it the government’s intention to do a seismic upgrade to the building? | See response to Question 22 above. | |
| 38 | 2.2.5.3: The contractor shall design two restrooms that comply with ADA to replace existing restrooms…. (15 users require only one restroom). | Code will require two restrooms. Please confirm that two restrooms are required. | See response to question 187 below. | |
| 39 | 2.2.5.3: The contractor shall design two restrooms that comply with ADA to replace existing restrooms…. (15 users require only one restroom). | Restroom currently has urinal in addition to toilet. Is the expectation that a urinal will be required in new restrooms as well? | See response to question 187 below. | |
| 40 | 2.2.5.3: The contractor shall design two restrooms that comply with ADA to replace existing restrooms…. (15 users require only one restroom). | Restrooms may require additional space to accommodate ADA clearances. Is it acceptable to shift wall toward control room to allow for this? | Yes. | |
| 41 | 2.4: Bay 16 is indicated to be for open storage of classified information. This will require upgraded wall construction at infilled clerestory. Please confirm. | Please refer to DoD Manual 5200.01, Volume 3, Appendix to Enclosure 3, as stated in paragraph 2.4.1. | ||
| 42 | The SOW requires 95% efficient forced air gas heat with DX cooling. This limits equipment selection to high efficiency gas fired furnaces as the only available option. Is that the intent of the project? | Yes. | ||
| 43 | The SOW identifies bays 2,3, & 4 as a zone and bays 5-16 as a zone. Will it be acceptable break those zones into smaller zones to accommodate equipment maximum capacities and to match similar occupancy and use requirements? | Yes. The zones identified in the SOW are the minimum number of zones. Additional zone may be added. | ||
| 44 | Data on the fire sprinkler hydraulic design placard suggests that the fire sprinkler system requires 38 psi with 1603 gpm flowing. A recent fire hydrant flow test at the adjacent building suggests that the water pressure available at 1603 gpm will be 33 psi. Since the require pressure is likely to exceed the available pressure, a fire pump will be required to boost water pressures. Is it acceptable to create a 14' wide by 12' deep room on the west side of Bay 5 to house the required fire pump? | The Offeror's Fire Protection Engineer must be consulted when making any comparisons between the requirements of the existing system and the new system. For example, hydraulic calculations may show that pressure requirements could be lower if larger pipe sizes are used. If a pump ends up being required the Government will evaluate the new pump requirements at that time. The size and requirements of the pump room must comply with all codes including but not limited to temperature, ventilation, panel access, and maintenance or replacement of the pump. | ||
| 45 | Fire sprinklers may be omitted from below exterior canopies/overhangs of non-combustible construction except where combustible materials are stored (NFPA 13 8.15.7.5). Please confirm that combustible materials are not stored below exterior canopies on east and west sides of the building. | Combustible materials are not stored below exterior canopies. | ||
| 46 | Attachment 05 Sample Project SOW 2.2.4.5 | Mechanical Requirements | Temperature for Bay 2 is defined. Are there humidity requirements? | There are no humidity requirements because film in not stored in that area. |