Attachment_01_-_SABER_BASIC_SOW_7Mar2016_Rev1_ApprovedChanges.pdf

PDF 476 KB Posted

Attached to
SIMPLIFIED BASE ENGINEERING REQUIREMENT (SABER) Federal contract opportunity
Solicitation number
FA8201-16-R-0007
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Attachment 01 - SABER Basic SOW Rev 1

View the file

Other files for this federal contract opportunity

Other files attached to SIMPLIFIED BASE ENGINEERING REQUIREMENT (SABER), newest first.
File Type Posted
Questions_and_Responses_15_March_2016.pdf PDF
Questions_and_Responses_15_March_2016.pdf PDF
SABER_Seed_Project_SOW_7Mar2016_Rev1_TrackChanges.pdf PDF
SABER_Section_L_7March2016_Rev1_TrackChanges.pdf PDF
SABER_Section_M_7March2016_Rev1_TrackChanges.pdf PDF
SABER_BASIC_SOW_7Mar2016_Rev1_TrackChanges.pdf PDF
Attachment_15_-_Rate_Worksheet_Rev_1.xlsx XLSX spreadsheet
Attachment_13_-_SABER_Section_M_7March2016_Rev1_ApprovedChanges.pdf PDF
FA8201-16-R-0007-0002_pdf_FINAL.pdf PDF
Attachment_26_-_Bldg_2405_and_2408_Mastic_Asbestos_Containing_Material_Samples.pdf PDF
Attachment_12_-_SABER_Section_L_7March2016_Rev1_ApprovedChanges.pdf PDF
Attachment_17_-_SABER_Seed_Project_SOW_7Mar2016_Rev1_ApprovedChanges.pdf PDF
Question_and_Responses_7_March_2016.pdf PDF
Site_Visit_Attendee_List.pdf PDF
FA8201-16-R-0007-0001.pdf PDF
Responses_to_Questions_-_5Feb2016.pdf PDF
Attachment_13_-_SABER_Section_M_FINAL_3Feb2016.pdf PDF
Attachment_25_-_Seed_Project_Pictures_3Feb2016.pdf PDF
Attachment_04_-_Wage_Determination_UT100.pdf PDF
Attachment_05_-_Wage_Determination_UT102.pdf PDF
Attachment_17_-_SABER_Seed_Project_SOW_FINAL_28Dec2015.pdf PDF
Attachment_23_-_Site_Visit_Information.pdf PDF
Attachment_16_-_Bona_Fide_Office_Requirements.pdf PDF
Attachment_19_-_Bldg_950 _970 _980_Asbestos_Report.pdf PDF
Attachment_18_-_Seed_Project_Burglar_Bar_Drawing.pdf PDF
Attachment_15_-_Rate_Worksheet_FINAL.xlsx XLSX spreadsheet
Attachment_06_-_Wage_Determination_UT104.pdf PDF
Attachment_08_-_Wage_Determination_WY15.pdf PDF
Attachment_12_-_SABER_Section_L_FINAL_3Feb2016.pdf PDF
Attachment_10_-_Government_Furnished_Property_(Scheduled)-_SGFP_V5.pdf PDF
Attachment_03_-_APPENDIX_C_MASTER_ON_or_OFF_BASE_UPDATED_Dec_2014.pdf PDF
Attachment_01_-_SABER_BASIC_SOW_FINAL_28Dec2015.pdf PDF
Attachment_21_-_Bldg_950 _970 _980_LBP_Report.pdf PDF
FA8201-16-R-0007.pdf PDF
Attachment_14_-_Construction_cost_estimate_breakdown_FINAL.xls XLS spreadsheet
Attachment_24_-_Site_Visit_Attendees.xlsx XLSX spreadsheet
Attachment_02_-_BASE_FACILITY_DESIGN_STANDARD_-_3_SEP_15.pdf PDF
Attachment_07_-_Wage_Determination_UT110.pdf PDF
Attachment_09_-_Hill_AFB_Construction_and_Demolition_Waste_Diversion_Report.pdf PDF
Attachment_20_-_Bldg_2405 _2408_Asbestos_Report.pdf PDF
Attachment_22_-_Bldg_2405 _2408_LBP_Report.pdf PDF
ppi_tool.accdb —
Attachment_11_-_Government_Furnished_Property_(Requisitioned)_RGFP_V4.pdf PDF
DRAFT_-_SABER_BASIC_SOW_8_Dec_2015.pdf PDF
DRAFT_-_SABER_Seed_Project_SOW_8_Dec_2015.pdf PDF
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SABER Solicitation FA8201-16-R-0007

STATEMENT OF WORK (SOW)

FOR

SIMPLIFIED ACQUISITION BASE ENGINEERING REQUIREMENT

(SABER)

HILL AIR FORCE BASE, UTAH

28 December 2015

TABLE OF CONTENTS

Section 01 00 00 (General Requirements)………………………………………………..3 Section 01 00 04 (Specific Requirements)………………………………………….…...15 Section 01 04 00 (Unit Price Book and Software Requirements)……………………….19 Section 01 31 01 (Project Management)……………………………………………....…23 Section 01 33 00 (Submittal Procedures)………………………………………………..27 Section 01 35 00 (Special Provisions for Working on or near the Flight Line)…………37 Section 01 35 29 (Safety and Occupational Health Requirements)………….……….….39 Section 01 45 00.00 (Contractor’s Quality Control)…………………………………..…41 Section 01 55 04 (Security Requirements)…………………………………………… Section 01 57 20.04 (Overreaching Environmental Protection)…………………………51

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 DEFINITION OF INSTALLATION

1.1.1 Installation will be defined as the property and facilities located within the jurisdiction of Hill Air Force Base (AFB), Utah.

1.2 PRECEDENCE

1.2.1 Individual installation specific requirements shall take precedence over the requirements in this section.

1.3 COMPETITIVE ACCEPTANCE

1.3.1 Competition will be limited to 8(a) firms located within Utah or 8(a) construction firms outside of Utah that have an approved bona fide office in Utah at the time of bid submittals, and the assigned NAICS code. All other 8(a) participants are deemed ineligible to submit offers.

1.4 PROJECT DESCRIPTION

1.4.1 The Contractor shall furnish all management, supervision, labor, materials, equipment and incidentals required for a broad range of maintenance, repair and minor construction work on various real property facilities at installations covered under this contract, including design and engineering services incidental to construction. The Contracting Officer (CO) will conduct negotiations with the Contractor and issue individual task orders for maintenance, repair and minor construction projects identified by the Base Civil Engineer (BCE), or their approved representative, as part of the Simplified Acquisition of Base Engineering Requirements (SABER) program. Individual task order projects will vary in size, typically ranging between $25,000 and $1,000,000, including but not limited to trades such as carpentry, plumbing, electrical, mechanical, painting, pipe fitting, sheet metal, welding, roofing, site work, site utilities, excavation, concrete, masonry, pavement repair, asbestos and lead paint removal, security hardware installation and demolition. However, individual task order projects may exceed $1,000,000 due to repairs, maintenance, and equipment to fulfill project requirements.

1.5 CONTRACT DOCUMENTS, REFERENCE STANDARDS, AND PUBLICATIONS

1.5.1 The following documents are a part of the solicitation and any resultant contract. The Contractor shall utilize the referenced documents in the accomplishment of tasks prescribed in task orders. The standards and publications listed in each section of the specifications, form part of these specifications to the extent referenced. The Contractor shall conform to the provisions of the most recent issue of the listed standard or publication.

1.5.1.1 SABER Specification

This SABER Specification is numbered and organized in accordance with (IAW) the Construction Specification Institute's (CSI) Master Format. All specifications are filed in Division 2 through 48 per CSI guidelines. The specifications are taken from the Unified Facilities Guide Specifications (UFGS). The UFGS website is http://www.wbdg.org/.

1.5.1.2 Standards

The SABER specification furnishes concise industrial and/or commercial standards for maintenance, repair and minor construction of government facilities.

1.5.1.3 Unit Price Book

The Unit Price Book (UPB) is described in Section 01 04 00.

1.5.1.4 Unified Facilities Criteria (UFC)

The UFC shall be used as the standard building code for all construction under this contract. The UFC website is http://www.wbdg.org/. Any and all changes to the UFC will immediately become requirements of this contract. The UFC references the International Building Code (IBC) 2015 as the basic requirement. The UFC modifies those basic requirements in UFC 01-200-01.

1.5.1.5 Installation Design Standards

Each installation’s facilities design guides and standards shall be adhered to on all construction projects. Any possible deviations from these standards shall be brought to the CO before implementation.

1.5.1.6 Bid, Performance, and Payment Bonds

Bid Bonds will be required IAW FAR 52.228-1 as specified at the Task Order level.

Performance and Payment Bonds will be required IAW FAR Clause 52.228-15 and due not later than 10 days after award notification. A minimum blanket bond capacity of $5 million for SABER Task Orders is required. Additional bonding will be required if active SABER projects exceed $5 million.

1.6 EXECUTION

1.6.1 Pre-Performance Construction Meeting

1.6.1.1 Before work begins on this contract, the CO will arrange for a meeting with the Contractor to discuss the contract in general, including administrative matters, project requirements, submittal procedures, approval and payment schedule, quality control expectations, request for proposal (RFP) and task order procedures, traffic control, construction access requirements, as-built criteria, performance requirements, security procedures, accident prevention, safety and fire prevention briefings.

1.6.2 Business Telephone

1.6.2.1 At the beginning of this contract, the Contractor shall provide the CO with Contractor personnel telephone number, e-mail, and website for regular working hours. The Contractor shall also provide after hours (emergency) telephone numbers for the Contract Manager (CM) at a minimum. The Contractor shall provide the CO with an updated phone list whenever changes in personnel or phone numbers occur. The Contractor is required to provide a means of mobile communications (i.e., cellular phone and/or pager) for the PM, for the life of the contract.

1.6.3 Work Hours

1.6.3.1 The Contractor shall complete the work of projects between the hours of 7:00 a.m. and 4:00 p.m. local time, excluding Saturdays, Sundays, and Federal Holidays unless otherwise specified in the Task Order SOW. Access to work sites may be restricted to these hours and days. The Contractor may not work during non-standard hours unless the request and justification is approved by the CO. The Contractor must submit a request and justification for working non-standard hours to the CO at least 5 working days prior to working non-standard hours. Work that requires inspection during accomplishment or that prevents inspection of other work after accomplishment must be coordinated with and approved in advance by the CO. Inclement weather, operational delays, and security related delays might affect the contractor’s work periods. The Contractor must make allowances for these events, as resulting lost time will not be reimbursable.

a. The Government recognizes the following legal holidays established by federal statute:

(1) New Year's Day, 1 January

(2) Martin Luther King Day, third Monday in January

(3) President’s Day, third Monday in February

(4) Memorial Day, last Monday in May

(5) Independence Day, 4 July

(6) Labor Day, first Monday in September

(7) Columbus Day, second Monday in October

(8) Veteran's Day, 11 November

(9) Thanksgiving Day, fourth Thursday in November

(10) Christmas Day, 25 December

b. Work Interruptions And Delays

(1) The Contractor may be required to temporarily stop work for operational requirements, special events, installation exercises, or while Distinguished Visitor (DV) familiarization visits/tours are conducted. Official late reporting and snow calls may affect the contractor’s work periods. The Contractor shall make allowances for these events and resulting lost time will not be reimbursable. Notification to the Contractor shall be provided by the CO.

1.6.4 Safety Requirements

1.6.4.1 See Appendix C

1.6.5 Request For Proposal (RFP)

1.6.5.1 For each project, the Contractor will be furnished with one electronic copy of the Task Order SOW. The contractor may also be provided with one set of drawings and/or specifications, if available. The level of design provided to the Contractor shall be a written narrative describing the basic concept of the Task Order. The Contractor may reproduce any drawings and specifications at the contractor’s own expense if additional copies are needed. The Contractor shall check all drawings and specifications immediately upon receipt for discrepancies and notify the CO immediately of any and all discrepancies found in the form of a Request for Information (RFI). Enlarged plans and details shall govern where the same work is shown at smaller scales. The Contractor shall review any Government provided drawings and verify the information for accuracy prior t o proposing on Task Order and shall be responsible for any errors which might have been avoided thereby. All Government provided drawings are for reference only.

1.6.6 Site Visit

1.6.6.1 The Government and Contractor(s) will conduct a pre-proposal site visit for each task order. Discussions may include, but are not limited to: scope of work, method of construction, sequence of operations, progress schedule, means of access to project site, delivery and storage of materials and equipment, work restrictions, coordination requirements, project goals, liquidated damages and potential difficulties/problems.

The contractor shall submit Request for Information (RFI) questions within 7 days of initial site visit or as directed in the TO specific RFP.

1.6.7 On-Site Conditions

1.6.7.1 Drawings, if provided, showing the location of equipment, piping, ducts, and conduit are diagrammatic and may not show every detail required. In addition, site conditions will not always permit installation in the locations shown. Drawings showing equipment, piping, ducts, conduit, etc., to be removed, altered, or installed may require deviation from the configuration of the demolition or installation drawings due to existence of conflicting ducts, conduits, hangers, light fixtures, structural items, and temporary walls, etc. All such minor details of work which are not shown on the drawings, as well as such items not specifically mentioned in the specifications, but which are essential and necessary for the completion of the work, and to make all systems or equipment operational, shall be considered as incidental and shall be included as part of the work. When this situation occurs, the final placement of permanently installed items shall be subject to approval by the applicable CO. The Contractor shall be responsible for inspecting to his satisfaction, all areas and/or items of possible conflict. Failure to verify the dimensions and locations will be at the Contractor's risk and shall not relieve the Contractor from accomplishing the work required by the task order.

1.6.8 Project Proposal

1.6.8.1 Individual project proposals shall follow instructions in each Task Order RFP/IFB. The

Contractor shall submit the proposal within the time identified in the TO RFP, typically 14 calendar days from date of site visit. However, TO RFP response dates may vary depending upon the complexity of the project, urgency, and end of fiscal year requirements.

a. Cost Estimates

(1) All Task Orders shall be estimated, negotiated, and awarded based upon prices in the UPB (see Section 01 04 00). The cost estimate portion of the Contractors’ proposals shall be prepared and produced using the cost estimating software described in UPB and Software Requirements (Section 01 04 00, this specification). This applies to all work done on SABER Task Orders, even if work is done by a subcontractor.

b. Construction Schedule

(1) A construction schedule is required IAW FAR 36.515 for projects with a continuous performance period of 60 days or more. Additionally, the Contractor shall submit a construction schedule when required by the Task Order SOW. The construction schedule shall be on an AF Form 3064 and completed according to the instructions on the reverse side of the form. In addition to the construction schedule on the AF Form 3064, the TO SOW may require a project to have a critical path or milestone schedule. The Contractor shall provide weekly construction updates on each task order on an AF Form

3065.

c. Design Solution

(1) The contractor shall provide, as part of the proposal, a basic design solution showing a complete understanding of the requirement. When required, drawings included with the proposal must be thorough enough to allow the Government and Contractor to estimate prepriced and non-prepriced items. Design incidental to accomplishing the required tasks outlined in each task order will be required.

Typically, Contractor maximum design for SABER is up to 35%. If the design requires the services of a registered architect or engineer, it is generally outside the parameters of minimum design; however, in some situations specific building codes may require a licensed engineer or architect for certain elements of a project.

As an example, a licensed engineer may be required for certain components of a fire suppression system to be replaced or repaired and a fire suppression engineer may be required to sign off on changes to the system. The extent of these designs will depend upon the complexity of each task. Also, designs shall clearly illustrate compliance with local, state, and federal building construction codes. Contractors are not required to bid on projects that exceed 35% design. As required in the SOW or otherwise required, the Contractor shall include the following documentation in the task order proposal. This documentation includes but is not limited to:

(2) Design drawings showing basic layout and planning of work.

(3) Design Calculations

I. The contractor shall provide as part of the proposal design calculations to substantiate appropriate equipment or material selection/sizing, component assembly and proposed layout and sizing of utilities and structural elements. The contractor shall at a minimum supply the following calculation as required per Task Order:

i. Mechanical: HVAC load analysis and unit sizing, pipe sizing, and duct sizing.

ii. Electrical: Electrical system capacity, conductor, conduit, protective devices and other equipment sizing.

iii. Structural: Structural system and foundation sizing.

iv. Pavement/Site Work: Area run-off quantities, drainage capacities, and grading slopes.

v. Energy: Provide energy savings and Return on Investment (ROI).

(4) Certified Shop Drawings. Shop drawings shall show in detail the proposed fabrication and assembly of structural elements and/or the installation (i.e., form, fit and attachment details) of materials or equipment.

1.6.9 Working Drawings

1.6.9.1 The Contractor shall keep on the work site a copy of the Project drawings and specifications and shall at all times provide the Air Force Project manager access thereto in accordance with FAR 52.236-21. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of a difference between drawings and specifications, the specifications shall govern.

Contactor shall immediately check the furnished drawings and notify the Government of any discrepancies.

1.6.9.2 If the Contractor fails to maintain the record drawings as required herein, the CO will consider that satisfactory progress has not been achieved for the period in question. Final payment will be withheld until As-Built record drawings are submitted by the contractor and approved by the CO.

1.6.10 Moving Furniture and Equipment

1.6.10.1 For each task order, the Government SABER Office and the Contractor shall coordinate with occupants of the proposed work area on responsibilities of moving furniture and equipment. If the Contractor moves the furniture, associated costs may be included in the proposal. The Government shall hold the Contractor responsible for any damages when the Contractor moves the furniture.

1.6.11 Delivery of Materials

1.6.11.1 Delivery of materials and equipment shall be made with a minimum of interference to government operations and personnel.

1.6.12 Division of Work

1.6.12.1 The work shall, so far as practicable, be done in definite sections or divisions and confined to limited areas that shall be completed before work in other sections or divisions will begin.

1.6.13 Clean Up

1.6.13.1 Hallways, exits and access routes must be kept free of debris and safe at all times. Prior to departure from the work area each day, the Contractor shall remove and properly dispose of all waste materials or rubbish generated by the project work in a contractor-supplied dumpster/trailer. The Contractor shall not use government dumpsters for construction debris/material. Daily cleanup of all job sites includes leaving the affected project area in a good state of order. Thorough daily cleanup may be required in certain high-visibility areas on a case-by-case basis as described in the statement of work (SOW) for specific Task Orders. Upon completion of the project, the Contractor shall conduct a thorough final cleaning.

1.6.14 Government-Furnished Equipment/Materials/Property

1.6.14.1 The Contractor with his own forces shall transport all government-furnished equipment (GFE) and/or government-furnished materials (GFM) and/or government-furnished property (GFP), if applicable, as described on the Task Order. The GFE/GFM/GFP shall be transported from the government’s storage area to the work site or as indicated on the Task Order. The Contractor shall follow the instructions of the CO regarding the disposition.

1.6.14.2 Government-furnished property will be determined at the Task Order level and the Government Furnished Property Forms attached to the Basic Contract will be completed IAW instructions at http://dodprocurementtoolbox.org/site/detail/id/26.

1.6.15 Equipment and Furniture on the Site

1.6.15.1 The Contractor shall cover equipment and furniture that is to remain in place within the contract operations area and protect it against damage or loss. Contractor shall store equipment and furniture that is removed in performance of work where directed, or reuse in work as required by the Task Order SOW, drawings, or specifications.

Equipment and furniture temporarily removed shall be protected, cleaned or replaced in equal or better than its original condition upon completion of the Task Order. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the Contractor.

1.6.16 Damage to Real Property

1.6.16.1 Any damage done by the Contractor to existing real property shall be repaired to prior conditions. Contractor shall patch and repair any holes or damage done to walls during the removal of any items or materials. Contractor shall match the existing conditions and meet the requirements of these specifications. The COR will determine if the repair work done is sufficient. All repair work will be at the Contractor’s expense.

1.6.17 Covered Chutes

1.6.17.1 All chutes used for refuse, and the like, shall be covered or of such design to fully confine the material to prevent the dissemination of dust.

1.6.18 Salvageable Items

1.6.18.1 All materials removed and not reused in the project as specified herein or as required by the project SOW, drawings, or specifications, remain the property of the Government. The CO will determine if these materials are salvageable or unsalvageable.

Salvageable materials shall be managed as directed by the CO with the concurrence of the Installation Environmental Office. See Environmental Protection Section 01 57

20.04 for further guidance.

1.6.19 Trash Removal

1.6.19.1 Unsalvageable materials, as determined by the CO, shall become the property of the Contractor and disposed of at the Contractor's expense. Materials to be removed shall be removed without damage to adjacent areas. All damage resulting from the removal activity shall be repaired by the Contractor at no cost to the Government. Repair shall be made with materials of like nature, type and construction as those which were damaged or as those which exist adjacent to the areas to be repaired. See Environmental Protection Section 01 57 20.04 for further guidance.

1.6.20 Monthly Reporting

1.6.20.1 The Contractor must submit reports monthly showing the tons of material disposed of at a landfill and the tons of material diverted from a landfill. See Environmental Protection Section 01 57 20.04, paragraph 1.5.2 for further guidance.

1.6.21 Permits

1.6.21.1 The Contractor is responsible for listing any and all necessary permits on each project submittal register that are required. The Contractor shall plan for and obtain any and all permits and provide two copies to the CO. See Environmental Protection Section 01 57

20.04 for further guidance. All environmental permits must be coordinated and approved through the Installation Environmental Office.

1.6.22 Pre-Final and Final Inspections

1.6.22.1 The contractor shall hold Pre-Final and Final inspections for each TO. The inspections will be conducted by the customer, SABER PM, CO and SABER contractor and subcontractors.

1.6.22.2 The contractor shall notify the SABER PM and CO a minimum of seven (7) days prior to Period of Performance completion date to conduct a pre-final inspection of the project and develop a punch list. The contractor shall have seven (7) days to complete all punch list items and any other items that are part of the project.

1.6.22.3 The contractor shall have all punch list items, any other items that are part of the project and final cleaning of the project area complete at time of final inspection. The contractor shall provide all requested/required drawings, manuals and/or any other requested literature at time of final inspection, Beneficial Occupancy or final invoice will not be accepted until all parts of the project are completed to the satisfaction of the CO, SABER PM and customer.

1.7 PRODUCTS AND SUBMITTALS

1.7.1 Standard Products

1.7.1.1 Materials and equipment shall be standard products of a manufacturer regularly engaged in the manufacturing of such products, which are of a similar material, design and workmanship. All products shall be new unless otherwise directed in the TO SOW.

See Environmental Protection for affirmative procurement requirements.

1.7.2 Contract Submittal Requirements

1.7.2.1 In addition to submittals required in each task order, these specifications require various contract submittals. The Contractor shall provide these submittals IAW the instructions found in these specifications and on the Submittal Register.

1.7.3 Submittal Requirements

1.7.3.1 See Section 01 33 00 Submittal Procedures.

1.8 CONCURRENT CONSTRUCTION

1.8.1 Construction work closely related to and/or located at the site of the work under this contract, including other military projects and normal maintenance and repair work may occur. The Government reserves the right to engage in and to perform work, with its own forces or other contractor forces, of the same type as the successful Offeror without breaching or violating this contract.

1.9 UTILITY SERVICES

1.9.1 Availability of Utility Services

1.9.1.1 All reasonably required amounts of water and electricity, where available, will be made available to the Contractor by the Government from existing system outlets and supplies. The quality, quantity and consistency of the utilities supplied are not guaranteed. Some task orders may not allow the use of government utilities. The Contractor shall, at his own expense, make all temporary connections and install distribution lines. All temporary lines shall be installed and maintained by the Contractor in a safe and workmanlike manner subject to approval by the CO and shall be removed by the Contractor in like manner prior to final acceptance of the construction. Reasonable quantities of electricity and water used to make final tests of completely installed systems will be furnished by the Government as determined by the CO prior to execution.

1.9.2 Fire Hydrant Connections

1.9.2.1 Only compatible adapters shall be utilized for hydrant connections. All connections to fire hydrants shall be provided with a backflow preventer. A hydrant wrench of the correct size shall be used to control the flow. Temporary connections to fire hydrants shall be disconnected at the end of each working day. Any use of fire hydrants shall be coordinated with and approved by the Hill AFB Fire Department & American Water prior to work. Notification by the Contractor to the CO, Hill AFB Fire Department, and American Water shall be made at least ten (10) workdays prior to any connection.

1.9.3 Conservation of Utilities

1.9.3.1 Energy Management Control Systems (EMCS)

a. The contractor shall follow all requirements outlined in the most recent version Hill AFB Facility Design Standard.

b. The Contractor shall be responsible for operating under conditions that preclude the waste of utilities and shall comply with energy conservation directives for each installation.

c. Supplemental lighting shall be used only in areas where and when work is actually being performed. When work areas are vacated, lighting shall be turned off.

d. Mechanical equipment for heating, ventilation, and air conditioning systems shall be adjusted by authorized craftsman only.

e. Water faucets or valves shall be turned off after the required usage has been accomplished.

1.10 UTILITY OUTAGES

1.10.1 The Contractor shall request and coordinate, any utility outage necessitated by the project work at least thirty (30) working days prior to the proposed outage unless otherwise approved in writing by the CO. The Contractor shall not operate any valve, circuit breaker, or other utility shut-off device unless approved by the CO. The Contractor shall verify that there are no conflicts with the scheduled outage immediately before shutting off the utility. The Contractor will be responsible to implement lockout/tag out procedures, as needed.

1.10.2 Requests – AF Form 103, Base Civil Engineer Work Clearance Request

The contractor shall obtain and process an AF Form 103, Base Civil Engineer Work Clearance Request, from the SABER PM for all utility outages needed during the performance of a TO. Contractor shall provide an approved and signed copy to the SABER PM a minimum of seven (7) days prior to the scheduled outage date. The contractor shall reference the specific Task Order; stipulate the specific utility system and/or circuits to be affected; the location of the work; the time, date and duration of the requested outage for each system and describe the contingency plans for restoring the utility to service.

1.10.3 Restrictions

Outages shall be kept to a minimum both in number and in duration. When multiple outages are required, as many outages as can be accurately scheduled shall be submitted as a group. No outage shall exceed eight (8) hours unless approved in writing by the Project Manager prior to outage execution.

1.11 PARKING

1.11.1 Parking of contractor vehicles shall be restricted to the project parking lot at the location designated by the CO. Under no circumstance shall the Contractor park vehicles and or equipment, even temporarily, on the grass unless approved in advance by the CO. The company name shall be prominently displayed on all construction vehicles and equipment parked in the designated spaces. Parking shall not violate fire or safety regulations.

1.12 TRAFFIC CONTROL

1.12.1 The Contractor shall comply with the recommendations contained in Part 6 of the US Department of Transportation, Federal Highway Administration Manual on Uniform Traffic Control Devices to ensure proper warnings to motorists and adequate traffic control. Traffic control signage should be installed IAW Utah Department of Transportation M&S Standards. All signs, warning lights, barricades, and other traffic control devices shall be provided by the Contractor. The Contractor shall maintain the normal traffic egress to and from the installation during construction at all times. If traffic flow on any roadway is to be modified for any reason, the Contractor must notify the Project Manager and coordinate a road closure by submitting a traffic coordination plan for approval to the PM twenty one (21) working days prior to commencing with construction activities. The schedule and phasing of roadway lane closure will be discussed in a pre-construction meeting.

1.13 SANITARY PROVISIONS

1.13.1 Use of government facilities may not be allowed. The Contractor shall utilize only those restrooms designated for their use, provided such usage does not conflict with usage by installation personnel and that such usage does not result in unsanitary conditions or damage to the restroom. If government restrooms are authorized as part of a task order, the Contractor will be required to maintain standard cleanliness in restrooms. Should usage by the Contractor result in unsatisfactory conditions, the CO may restrict or prohibit further usage by the Contractor. In no instance shall paint or other construction materials be disposed of in the rest room nor shall fixtures be utilized for cleaning tools or construction equipment.

1.13.2 Temporary Sanitary Provisions

The Government, at its discretion, may direct the Contractor to provide temporary toilets for the contractor’s use. When the Contractor provides their own temporary toilets, they shall ensure that they satisfy state and local health requirements for the use of construction personnel. Location, type, proposed maintenance, etc., shall be approved by the CO prior to placing toilets. Temporary toilets shall be promptly removed at the completion of construction. All costs incurred in connection with the temporary toilets shall be borne by the Contractor.

1.14 TOBACCO

1.14.1 The Contractor shall limit smoking and use of tobacco to authorized areas only.

Tobacco use shall be IAW applicable installation and DOD policy.

1.15 SUBCONTRACTOR UTILIZATION PLAN

1.15.1 Contractor shall ensure adequate subcontractor pools exist to promote competition, to provide best value to the Government, and to meet performance and schedule requirements. Contractor shall provide a Subcontractor Utilization Plan that demonstrates management of subcontractors, establishment and utilization of subcontractor pools, ability to obtain additional subcontractor resources to meet performance and schedule requirements. This plan will assist the Government in determining if prime contractors have adequate subcontractor resources and ability to obtain additional subcontractor resources to meet performance and schedule requirements. The Subcontractor Utilization Plan will be submitted and reviewed annually at the beginning of each ordering period; updates may be requested at any time during contract period of performance.

1.16 CONTRACT ADMINISTRATION

1.16.1 Contracting Officer (CO): Government official authorized to enter into, make changes to, or terminate contracts on behalf of the United States (US) Government. COs are responsible for ensuring performance of all necessary requirements of the contract, to ensure compliance with the terms of the contract, and safeguard the interests of the US Government in its contractual relationships.

1.16.2 Contracting Officer Representative (COR): An individual designated and authorized in writing by the contracting officer to perform specific technical or administrative functions. The COR will assist in the technical monitoring and administration of the contract.

1.16.3 A Quality Assurance Surveillance Plan (QASP) will be incorporated at the Basic

Contract level.

1.17 ACRONYMS:

AF Air Force

AFI Air Force Instruction

BFDS Base Facility Design Standard

CO Contracting Officer

CM Contract Manager

COR Contracting Officers’ Representative

DOD Department of Defense

QCO Quality Control Officer

SOW Statement of Work

TO Task Order

GFE Government Furnished Equipment

GFM Government Furnished Materials

GFP Government Furnished Property

ROI Return on Investment

HVAC Heating, Ventilation and Air Conditioning

UPB Unit Price Book

IBC International Building Code

UFC Unified Facilities Criteria

BCE Base Civil Engineer

SABER Simplified Acquisition of Base Engineering Requirements

CSI Construction Specifications Index

UFGS Unified Facilities Guide Specifications

DV Distinguished Visitor

NFPA National Fire Protection Agency

RFP Request for Proposal

CE Civil Engineer

O&P Overhead & Profit

DOD Department of Defense

AFB Air Force Base

CCI City Cost Index

NPI Non Pre-Priced Item

PM Program Manager or Project Manager

EPA Environmental Protection Agency

OSHA Occupational Safety and Health Administration

SSHO Site Safety and Health Officer

QC Quality Control

CAD Computer Aided Design

IAW In Accordance With

MSDS Material Safety Data Sheet

RMECEF Recovered Materials Estimate and Certification

CPG Comprehensive Procurement Guide

QASP Quality Assurance Surveillance Plan

PART 2 PRODUCTS – Not Used PART 3 EXECUTIONS – Not Used

END OF SECTION 01 00 00

SECTION 01 00 04

SPECIFIC REQUIREMENTS (HILL AIR FORCE BASE)

1.1 LOCATION

1.1.1 This section contains requirements applicable to Hill AFB, Utah.

1.2 WORK CLEARANCE REQUEST – AF Form 103

1.2.1 In all cases, the Contractor shall have contingency plans for continuing work during utility outages caused by the Contractor or outside forces. The plan must also include procedures for promptly repairing utility breaks/interruptions made or caused by the Contractor.

1.2.2 Contractor shall be responsible for completion of 75 CEG/CEOER Form 12 (Dig Permit) contacting all appropriate utility owners to coordinate work, identify, locate, and mark all utility lines in the vicinity of the project work site (commercial and military utility lines). Contractor is responsible to maintain all utility location markings once identified and marked by utility owner. The Contractor will be required to mark the limits of site work/excavation to indicate location, direction, length, and depth of site work/excavation in order to facilitate the utility owner’s field marking of existing utilities. Signed original permit shall be on job site during excavation.

1.2.3 The Contractor shall provide, as attachment to the 75 CEG/CEOER Form 12, drawings showing exact location and description of the work to be accomplished. Should any of the coordination points indicate additional utility lines or structures to those already shown on the drawings, by sketch on the Contractor’s drawing or by field location marking, the Contractor shall be responsible for the protection of each of the indicated items. It is the responsibility of the Contractor to verify the exact location of all indicated utility lines and structures, and for the protection of the same, in the project work area. Should damage occur to any utility line or structure, the Contractor shall be responsible for the prompt repair of the damage to return the item to its original working condition.

1.3 ELECTRICAL SERVICE AND COMMUNICATIONS FACILITIES

1.3.1 The Contractor will not disturb electrical and/or communications facilities and wiring.

Where such facilities require removal for accomplishment of the project work, the Contractor shall notify the Contracting Officer (CO) in writing at least ten (10) calendar days in advance of the requirement, for the accomplishment of such removal work by the Government. The Contractor shall allow the utility owner enough time to remove the systems required. If damaged by Contractor’s construction activities, the Contractor shall restore service within 24 hours with no cost to the government.

1.4 CONDITIONS OF WORK:

1.4.1 Disruptions

1.4.1.1 The Contractor shall perform his work in a manner which will minimize disruptions to normal Hill AFB operations.

1.4.1.2 Area of Work:

1.4.1.3 The Contractor will be allowed a reasonable working area.

1.4.1.4 Regulations and Policies

1.4.1.5 The Contractor shall comply with all applicable Hill, AFB policies and regulations pertaining to safety, health, security, traffic control, fire prevention, and environmental protection.

1.5 ROUTE

1.5.1 Only route(s) designated by the COR for each Task Order shall be utilized by the Contractor for access to the work site. The use of an existing elevator shall be arranged prior to use through the COR and subject to his controls. Such use will be of an intermittent and temporary nature. The Contractor shall provide and maintain suitable and adequate protective covering for the elevator machinery, the hatchway entrance, and the interior of elevator during any period of temporary usage. In no case shall the load exceed the rated capacity of the elevator.

1.6 UTILITY OUTAGES

1.6.1 In addition to the requirements set forth in section 01 00 00, paragraph 1.10, Utility Outages, unless a documented Government delay occurs, the Contractor shall be responsible for meeting outage time requirements.

1.7 FILL MATERIALS

1.7.1 All fill materials, including rock, gravel, broken concrete or asphalt, etc. shall be disposed of at an approved base landfill. No fill material from any project under this contract shall leave the base, unless under specific direction of the CO.

1.7.2 Additional fill material shall be imported and delivered to the site from off base as a necessary part of project. Material composition shall be subject to the requirements of UFGS Section 31 23 00. Additional fill may be available from the Hill, AFB landfill.

If use is not specified in Government SOW, Contractor shall request use through a project specific RFI.

1.8 CONTRACTOR VEHICLES

1.8.1 The company name shall be prominently displayed on all Contractor vehicles/equipment operated on Hill AFB. The contractor may obtain temporary vehicle entry passes needed to transport materials and equipment at Building 1964, (Truck Gate). The Contractor shall be equipped to present proof of insurance, driver’s license, vehicle registration, and other documentation as needed to obtain vehicle pass.

Entry to the restricted area of Hill AFB will require a vehicle pass and additional clearances (i.e. for personnel) as described in UFGS Section 01 55 04, Security Requirements for Hill, AFB.

1.9 TASK ORDER (TO) PROCEDURES:

1.9.1 Task Order (TO) Request for Proposal (RFP): TO RFP will be issued to each of the contractors by the CO when the project is identified. The TO RFP may not have traditional plans and specifications but will include a TO SOW. The TO SOW will include a list of work elements and/or sketches that define the project and state the Government requirements. All attachments to the TO RFP, if applicable, will be considered to be a part of the project scope of work. A pre-proposal site visit will be held by the Government and the contractors as requested in the TO RFP, to discuss all conditions and details of the work. Contractor clarification/questions shall be submitted in writing IAW TO proposal instructions. On average, Period of Performance of TOs is 60 days or less.

1.9.2 Submission of TO RFP: The contractors shall be requested to submit the TO proposal to the issuing office within the period stated in the TO RFP which may consist of:

a. Technical Proposal. Concept sketches or drawings for proposed methods, performance schedule of design and construction, proposed technical approach/solution, list of required work elements, management approach, key personnel and/or subcontractors, catalogs, and/or other material submittals.

b. Price Proposal. The price proposal for the design and construction cost.

c. Past Performance. Recent and relevant performance information may be required. Definitions of "recent" and “relevant” will be specified in the TO RFP for each project.

The TO proposals shall be prepared at no cost to the Government, and are not reimbursable by the Government.

1.9.3 TO Evaluation Criteria: Individual TOs will be competed equally among all awardees after award of the seed project IAW FAR 16.505(b), Fair Opportunity. Task orders will be firm fixed price and will clearly define the specific work required. SABER Task Orders awards will be made on a best value basis determined by Lowest Price Technically Acceptable (LPTA), Tradeoff, or Low Price. Specific instructions to Offerors and evaluation criteria for individual TOs will be specified in the Task Order RFP. The Task Order source selection method will be selected at the discretion of the Government in consideration of the project scope, complexity, magnitude, and urgency.

1.9.4 Competition: All SABER contractors will be solicited for each project. SABER contractors are encouraged to participate in all site visits and shall submit proposals for all funded TOs. Failure to participate responsibly in site visits and proposal submissions may be reflected in Contractor Performance Assessment Reporting System (CPARS) ratings. Contractors may request a proposal submittal exemption in writing to the CO within 5 calendar days of issuance of TO RFP with rationale for not participating. However, when the TO RFP contains FAR Clause 52.232-18, Availability of Funds, submission of proposals for those projects is at the sole discretion of the respective contractors and their declination to participate in any or all such solicitations will not be negatively reflected.

1.9.5 Unless the CO applies the exceptions per Federal Acquisition Regulation

(FAR)16.505(b)(2), each TO will be awarded, as a result of competition to the contractor who offers the best value to the Government considering the criteria specified in the TO.

1.9.6 Performance Evaluations: At the conclusion of each TO or other times as determined appropriate by the CO or Government Project Manager, the contractor’s performance evaluation will be made through the CPARS. The evaluation will take into account all aspects of the contractor’s performance. The contractor will be provided an opportunity to review and comment to the government evaluation result through the CPARS. Past performance may be used during TO evaluations, which may have an impact on the award of the TO.

PART 3 EXECUTION – Not Used

END OF SECTION 01 00 04

SECTION 01 04 00

UNIT PRICE BOOK AND SOFTWARE REQUIREMENTS

1.1 COST ESTIMATING SOFTWARE REQUIREMENTS

1.1.1 The Contractor shall purchase, maintain, and use the latest version of e4Clicks Basic or Premier Project Estimator (or Government-approved equivalent) for their own use.

The Contractor shall use e4Clicks software, or Government-approved equivalent, to estimate and submit all of their estimates, both electronically and on paper. The Contractor is responsible for deciding which software version to purchase and the number of copies of the software required to support their contract requirements. The Contractor shall have the most current version of the software and databases at all times and throughout the period of performance of the contract. The Contractor may also submit all of their estimates, both electronically and on paper, using the Construction Cost Estimate Breakdown worksheet, located in AFFARS 5336.9001.

1.1.2 The estimating and project management software package shall support all of the City Cost Indexes provided by RSMeans annually and quarterly in addition to supporting Division Level Material/Installation, Division Level Weighted Average, Weighted Average Material/Installation and Weighted Average Totaling for Bare Cost pricing and Overhead and Profit (O&P) unit pricing. The software shall be able to export to Microsoft Excel™ and Adobe PDF™ file types as well as create electronic Air Force Forms 3064 (Progress Schedule), 3065 (Contract Progress Report) 66 (Schedule of Submittals), 3000 (Material Submittals), 3052 (Construction Cost Estimate), etc. and Department of Defense (DoD) Form 1354 Real Property documents.

1.1.3 Information on this software and pricing may be obtained by emailing sales@4-clicks.com advising it is for use on the Hill AFB Simplified Acquisition of Base Engineering Requirements (SABER) follow-on contract. Government Service Administration (GSA) pricing may be available with written consent from the Contracting Officer.

1.2 DEFINITIONS

1.2.1 Unit Price Book (UPB): The list and price information for all pre-priced items covered in this contract. The UPB shall include the base cost pricing from the RSMeans Facilities Cost Data Guide, RSMeans Assemblies, and the RSMeans Master Composite Cost Data Guides – consisting of Building Construction, Electrical, Mechanical, Plumbing, Green Book, Interior, Site Work & Landscape, Concrete & Masonry and Heavy Construction Cost Data. The UPB shall also include RSMeans trades line items, average line items, and Government Furnished Materials line items.

1.2.2 Line item: An item or system denoted in the UPB by a unique line item number.

1.2.3 Bare costs: The cost of a line item without any multiplier.

1.2.4 Multipliers: All factors added to the bare cost pricing of the UPB. This includes the City Cost Index (CCI).

1.2.5 Prepriced line item: A line item from the UPB with approved changes.

1.2.6 Non-prepriced line item (NPI): A line item that is not a prepriced line item.

1.2.7 Conventional line item: A line item listed directly from an RSMeans Cost Data

Guide(s).

1.2.8 RSMeans trades line item: These are the bare cost hourly rates found in the back of the annually published RSMeans hardcopy books.

1.2.9 Average line item: An item that is created by using a minimum and maximum line item.

If an average line item can be found in the UPB, that line item will be used. If there is no line item for an average, but there is a line item for minimum and maximum and the average line item is applicable the contractor will locate the two line items, the minimum and the maximum in the UPB. Then, the Contractor will create an alternate prepriced line item using the average total cost of the two line items. This will be used as a means to create an average line item when none exists. This line item will be prepriced. If the minimum and maximum line item cannot be found in the UPB, the average line item will be an NPI.

1.2.10 Government-Furnished Materials (GFM): On occasion, the government may choose to supply the Contractor with materials to accomplish project requirements. If this occurs, the line item prices for labor and equipment only will be used. They are considered as prepriced. The Contractor will not adjust the labor and equipment pricing. The materials are to be maintained by the Contractor, and excess materials are to be returned to the government.

1.2.11 All prices in the UPB are for completed and in-place construction unless explicitly described otherwise. Incidental fasteners such as, nails, screws, bolts, weldments, connectors, and adhesives are included in the bare material cost. Unless specifically omitted in the UPB line item description, testing, adjusting, balancing, and start-up of installed equipment is included in the unit price line number cost found in the UPB.

Line items are for end finishes. For example, the line item price for concrete broom finish includes all finishes necessary to result in the broom finish.

1.2.12 The UPB prices certain line items with a “Minimum labor/equipment charge.” This minimum charge is often the price a tradesman would charge to make a special visit to perform that work. If the contractor is already on-site and the minimum is met, then this item shall not be used as an adjustment to the Unit Price line items.

1.2.13 Line items for mobilization and demobilization are for one or the other unless noted otherwise. Normally, a piece of equipment will need to be mobilized and demobilized.

Therefore, the line item would normally be included twice per piece of equipment used.

Small equipment placed in rear of truck or towed by a pickup truck is limited to those items included in the RSMeans crews.

1.3 PRICE DETERMINATION

1.3.1 City Cost Index (CCI): The CCI will be applied with totaling components after the bare cost of the line items have been totaled.

1.3.1.1 The CCI for task orders at Hill AFB will use the current CCI for the city nearest to where the project will be performed (generally Ogden, UT).

1.3.1.2 Conventional line items will use the most current published Weighted Average Total

CCI.

1.3.1.3 The RSMeans trades, selective demolition, removal and replacement, average, and GFM lines items will be summated and multiplied by the most current published Weighted Average Total CCI.

1.3.1.4 Prepriced Line Items: Bare cost line items from the Unit Price Book (UPB) will be summated with the CCI applied as described above. This is the prepriced line item total.

1.3.1.5 Non-Prepriced Line Items: The non-prepriced line items shall be summated. This is the non-prepriced line item total. This includes all Professional Labor Categories (as required) for each Task Order with unburdened labor rates and hours.

1.3.1.6 Profit and Overhead: Task Order profit and overhead rates shall be broken out as a separate line item(s) on each project price proposal.

1.3.1.7 Final Project Price: The summation of the prepriced, non-prepriced, and profit/overhead line item totals, shall result in the final project price.

1.4 COST ESTIMATE ORGANIZATION

1.4.1 Cost estimates will be developed using the Facilities Guide for all repair work and Master Composite Guide for all new construction work.

1.4.2 Cost Estimates will be comprised of three sections: 1) Division Summary, 2) Totaling Components and C) Line Item Estimate.

a. Section 1, Division Summary: This section shall include the RSMeans prepriced divisions, Trades, Assemblies and Alternates (both prepriced and non-prepriced).

These items shall make up the Bare Total. No markups shall be applied at this level.

b. Section 2, Totaling Components: This section includes totaling components setup for all applicable markups. (CCI’s shall be applied as described above.)

c. Section 3, Line Item Estimate: This section shall include all of the estimate line items.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .