Asbestos_Abatement_Questions.docx
DOCX document 14 KB Posted
- Attached to
- Abatement Services Federal contract opportunity
- Solicitation number
- FA8201-14-R-0016
About this file
Answers to questions received
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA8201-15-R-0005-0003.pdf | ||
| FA8201-15-R-0005-0002.pdf | ||
| Supplemental_Schedule_B_Rev._3.xlsx | XLSX spreadsheet | |
| Line_Item_Descriptions_Rev1.pdf | ||
| Line_Item_Descriptions.pdf | ||
| Wage_Determination_UT104_Davis_County.pdf | ||
| Wage_Determination_UT107_Tooele_County.pdf | ||
| FA8201-15-R-0005.pdf | ||
| Asbestos_Abatement_Statement_of_Work_Final.pdf | ||
| Minimum_Order_Statement_of_Work.pdf | ||
| Revised_Supplemental_Schedule_B.xlsx | XLSX spreadsheet | |
| SSPP_DD_Form_1423_-_CDRL.pdf | ||
| Wage_Determination_UT102_Box_Elder_County.pdf | ||
| Past_Performance_Information_Sheet.pdf | ||
| QCIC_DD_Form_1423_-_CDRL.pdf | ||
| Minimum_Order_Letter_RFP.pdf | ||
| Wage_Determination_UT100_Summit_County.pdf | ||
| Wage_Determination_UT110_Weber_County.pdf | ||
| FA8201-15-R-0005-0001.pdf | ||
| Wage_Determination_WY15_Sublette_County _WY.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Asbestos Abatement Questions:
1. Will there a pre-determined number of offerors to be selected or will all who submit and meet the requirements be selected to offer services as described in the solicitation?
Page 72 of 75 Egvaluation Critieria for Award states the government intends to award two contracts
2. There are a couple projections of values of work to be performed; $5M-$10M and $3,500K-$10M. Does Hill AFB have a projected tasks scheduled or will this be on a as needed basis?
Tasks will be scheduled on an as needed basis. Value will range from minimum or $500.00 to maximum $2,000,000.00 for individual task orders. See page 5 of solicitation.
3. If there is a scheduled tasks to be performed can you elaborate on size and magnitude?
See answer above.
| 4. | In the solicitation it states payment and performance bonds of $1M each will be required after |
| award. Is the anticipated sizes of the tasks in value be in that range? I ask this due to the solicitation stating that multiple award contractors will have opportunity to be considered for each order in excess of $3,000.00 dollars and P&P bonds only required if in excess of $150K. |
The maximum amount on individual task orders will be $2M. Contractos will need bonding capability up to that maximum. The statement on page 1 is changed to reflect that number. P&P bonds will only be required on task orders in excess of $150K.
5. Can you confirm in the solicitation and offer page 3 of 75 the max net amount will be the grand total of the Abatement IDIQ Supplemental Schedule B?
Yes. The grand total of the Supplemental Schedule B will be the max amount on CLIN 0001. CLINs 0002, and 0003 are Not Seperately Priced (NSP) and should not have a dollar value.
6. Do we fill out BLOCK 17 and 18 on the CDRL’s referenced in CLINs 0002, and 0003?
QCIC DD Form 11423 and SSPP DD form 1423 (CDRL A001 and CDRL A002) are for submittals required after contract award. Blocks 17 and 18 should not be filled out.