Amendment 0001.pdf
PDF 67 KB Posted
- Solicitation number
- FA8201-10-B-0006
About this file
Amendment 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Additional Q A for IWTP 8_29_2010.pdf | ||
| Pics.zip | ZIP file | |
| FA8201-10-B-0006 Amend. 0002.pdf | ||
| Question for IWTP 1.pdf | ||
| Attendance Record.pdf | ||
| 090929 IWTP Clarifier 100 Design Specs.pdf | ||
| Solicitation.pdf | ||
| WD Davis Building.pdf | ||
| 090929 IWTP Clarifier 100 Design Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F2D0AA0189A001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment is to attach the questions and answ ers from the site visit, post the site visit attendance record, and schedule a second site visit.
The Second Site visit w ill be held on Friday 20 August 2010 at 11:00AM MST at Building 1289NE. If you do not have base access please contact Brian Lark at 801775-3859 or send your request via email at brian.lark@hill.af.mil.
All other attachments, provisions, and clauses remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Aug-2010
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA8201-10-B-0006
X 9B. DATED (SEE ITEM 11)
27-Jul-2010
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Aug-2010
CODE
OO-ALC/PKOB
SRA BRIAN LARK 6038 ASPEN AVE B1289NE
HILL AFB UT 84056-5805
FA8201 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
FA8201-10-B-0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The Issued By organization has changed from
75 CONS/PKB
SRA BRIAN LARK 6038 ASPEN AVE B1289NE
HILL AFB UT 84056-5805
to
OO-ALC/PKOB
SRA BRIAN LARK 6038 ASPEN AVE B1289NE
HILL AFB UT 84056-5805
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been modified:
SPECIFICATIONS/DRAWINGS
PROJECT NO: KRSM 070112
IWTP Modernization
Industrial Waste Treatment Plant, Bldg 575, Hill AFB, Utah
LIST OF SPECIFICATIONS
SECTION DESCRIPTION # OF PAGES
DIVISION 01 GENERAL
01 11 00 Summary of Work 1
01 31 13 Project Coordination 15
01 33 00 Submittal Procedures 7
01 43 33 Manufacturers' Field Services 3
01 45 16.13 Contractor Quality Control 9
01 45 33 Special Inspection, Observation, and Testing 5
01 50 00 Temporary Facilities and Controls 3
01 61 00 Common Product Requirements 7
01 78 23 Operation and Maintenance Data 6
01 88 15 Seismic Anchorage and Bracing 5
01 91 14 Equipment Testing and Facility Startup 4
DIVISION 02 EXISTING CONDITIONS
02 41 00 Demolition 6
02 61 00 Removal and Disposal of Contaminated Soil 6
DIVISION 03 CONCRETE
03 01 32 Repair of Vertical and Overhead Concrete Surfaces 9
03 01 33 Repair of Horizontal Concrete Surfaces 6
03 10 00 Concrete Forming and Accessories 4
03 15 00 Concrete Joints and Accessories 6
03 21 00 Reinforcing Steel 4
03 24 00 Fibrous Reinforcing 3
03 30 00 Cast-in-Place Concrete 27
03 39 00 Concrete Curing 3
03 62 00 Nonshrink Grouting 6
03 64 23 Crack Repair Epoxy Injection Grouting 9
DIVISION 04 MASONRY (NOT USED)
DIVISION 05 METALS
05 50 00 Metal Fabrications 17
05 52 00 Metal Railings 9
05 53 00 Metal Gratings 5
DIVISION 06 WOOD, PLASTICS, AND COMPOSITES (NOT USED)
DIVISION 07 THERMAL AND MOISTURE PROTECTION
07 21 00 Thermal Insulation 3
DIVISION 08 OPENINGS (NOT USED)
DIVISION 09 FINISHES
09 97 13 Steel Tank and Clarifier Mechanism Coatings 15
DIVISIONS 10-25 (NOT USED)
DIVISION 26 ELECTRICAL
26 05 01 Electrical 32
DIVISIONS 27-30 (NOT USED)
DIVISION 31 EARTHWORK
31 23 13 Subgrade Preparation 3
31 23 16 Excavation 4
31 23 23 Fill and Backfill 10
DIVISION 32 EXTERIOR IMPROVEMENTS (NOT USED)
DIVISION 33 UTILITIES
33 16 13.13 Welded Steel Tank 13
33 47 13.04 Clarifier Foundation Liner 13
DIVISION 34-39 (NOT USED)
DIVISION 40 PROCESS INTEGRATION
40 05 15 Piping Support Systems 9
40 05 33 Pipe Heat Tracing 5
40 27 00 Process piping General 5
40 27 00.03 Carbon Steel Pipe and Fittings-General Service 2
40 27 00.11 Chlorinated Polyvinyl Chloride (CPVC) Pipe and Fittings 2
40 42 13 Process Piping insulation 5
DIVISIONS 41-43 (NOT USED)
DIVISION 44 POLLUTION CONTROL
44 42 24.05 Clarifier 16
DIVISIONS 45-49 (NOT USED)
SCHEDULE OF DRAWINGS
SEQ. SHEET NO. DESCRIPTION
1 G-01 TITLE SHEET, VICINITY MAPS, AND DRAWING INDEX
2 G-02 SYMBOLS, ABBREVIATIONS AND LEGENDS
3 G-03 PROCESS HYDRAULIC PROFILE
4 G-04 STRUCTURAL NOTES
5 G-05 STATEMENT OF SPECIAL INSPECTION -SHEET 1
6 G-06 STATEMENT OF SPECIAL INSPECTION -SHEET 2
7 G-07 STATEMENT OF SPECIAL INSPECTION -SHEET 3
8 C-01 OVERALL PROJECT SITE PLAN
9 C-02 PROCESS TREATMENT AREA -DEMOLITION PLAN
10 C-03 CLARIFIER FOUNDATION SECTION AND NOTES
11 C-04 CLARIFIER FOUNDATION SECTIONS
12 S-01 CLARIFIER -FOUNDATION PLAN
13 S-02 CLARIFIER -TOP PLAN
14 S-03 CLARIFIER -SECTION
15 S-04 CLARIFIER -DETAILS
16 SD-01 STANDARD DETAILS
17 SD-02 STANDARD DETAILS
18 SD -03 STANDARD DETAILS
19 M-01 CLARIFIER –PLAN
20 E-01 LEGEND AND ABBREVIATIONS
21 E-02 SINGLE LINE DIAGRAM -MCC.P3 (NEW)
22 E-03 SINGLE LINE DIAGRAM -MCC.P3 (NEW)
23 E-04 MCC.P3 ELEVATION AND SCHEDULE (EXISTING)
24 E-05 CLARIFIER SITE PLAN
25 E-06 CONTROL DIAGRAMS
26 E-07 SECTIONS AND DETAILS
Title Date # Of Pages
General Wage Decision, UT100037 07/16/2010 6
Site Visit Attendance Record 08/10/2010 1
Questions and Answers 08/18/2010 3
(End of Summary of Changes)
File details come from the government source that posted it. Updated .