This document is a set of construction drawings for an HVAC system replacement project at Tinker Air Force Base, Oklahoma, specifically for Building 285. The project number is WWYK210116 with a concept issue date of 29 May 2025, and it received an amendment revision on 01-AUG-2025.

The drawings include six sheets detailing demolition and renovation plans across multiple disciplines: General Notes & Vicinity Map (G-101), Architectural Demolition/Renovation Plan (A-101), Mechanical HVAC Demolition Plan (MD-101), Power-Lighting Demolition Plan (ED-101), Power-Lighting Renovation Plan (E-101), and Fire Protection Demolition & Renovation Plan (F-101). Key architectural work includes demolishing the entire acoustical tile ceiling system and providing new 2' x 2' Armstrong Dune acoustical tile with white grid, along with repairing any damaged wall planes to match existing finishes. The mechanical scope involves demolishing and replacing the existing packaged HVAC unit and its controls while retaining other components in the west addition; demolishing all HVAC equipment in the original building footprint (air handler, condenser, variable air boxes, ductwork, controls, thermostats, and associated devices); and designing a new HVAC system per Statement of Work requirements. The boiler remains if load analysis confirms sufficient capacity. Electrical work includes disconnecting existing power connections for HVAC units, removing light fixtures and associated components back to the nearest junction box, upgrading Panel "A" from 150A to 200A capacity, and installing new lighting layout with LED fixtures. Fire protection work involves protecting the existing fire sprinkler system, demolishing the conventional fire alarm system, and designing a new addressable combination fire alarm and mass notification system compliant with UFC standards. The contractor is responsible for field verification of existing conditions, coordination with other trades, site protection, damage repair, and commissioning of new equipment by an independent contractor.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVIEWED BY:

REVIEWED BY:

USING AGENCY:

ASBESTOS EVALUATION:

SAFETY:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

INDUSTRIAL HYGIENE:

DATE:

PROJECT DRAWING INDEX SIGNATURES

CORROSION ENGINEER: (CECE)

CE OPERATIONS: (CECO)

COMMUNICATIONS: (COMM)

CHIEF ENGINEER DIR: (CECE)

CHIEF DESIGN BRANCH: (CECE)

DESIGN MANAGER: (CECE)

ZONE MANAGER:

CONSTRUCTION MANAGEMENT: (CECE)

ENVIRONMENTAL:

BASE CIVIL ENGINEER: (CE)

FIRE DEPARTMENT: (CEFT)

GENERAL1. BRAND NAMES: REFERENCE TO SPECIFIC BRAND NAMES

OR COMPANIES IS FOR THE PURPOSE OF ESTABLISHING

MINIMUM QUALITY STANDARDS, IDENTIFICATION AND

GUIDANCE AND IS NOT INTENDED TO LIMIT SELECTION OF

OTHER MANUFACTURERS THAT ARE EQUAL OR EXCEED

THE SPECIFIED ITEMS IN TERMS OF PHYSICAL

PROPERTIES, INCLUDING, COLOR RANGE, FINISH,

DURABILITY, APPEARANCE, PERFORMANCE

CHARACTERISTICS, AND OTHER FACTORS. OTHER

PRODUCTS, MATERIALS, COLORS AND SYSTEMS, MAY BE

SUBMITTED FOR EVALUATION AND

APPROVAL/DISAPPROVAL BY THE CONTRACTING OFFICER.

2. THIS SET OF CONSTRUCTION DOCUMENTS SHALL BE

CONSIDERED AS A WHOLE IN THAT THE GENERAL

CONTRACTOR AND ALL THE SUB-CONTRACTORS ARE

RESPONSIBLE FOR THE INFORMATION PRESENTED ON ALL

SHEETS ON THE SET OF DRAWINGS AND ALL SECTIONS OF

THE SPECIFICATIONS.

3. THE CONTRACTOR IS RESPONSIBLE FOR ERECTING ALL

CONSTRUCTION FENCING AND BARRICADES AS REQUIRED

TO PROTECT CONSTRUCTION MATERIAL AND TO PREVENT

ANY UNAUTHORIZED PERSONNEL FROM ENTERING THE

CONSTRUCTION SITE.

4. ANY DAMAGE TO THE EXISTING GROUNDS OR FACILITIES

CAUSED BY CONSTRUCTION TRAFFIC OR ANY

CONSTRUCTION OPERATION SHALL BE REPAIRED OR

REPLACED BY THE CONTRACTOR TO MATCH OR EXCEED

EXISTING CONDITIONS AT NO ADDITIONAL COST TO THE

GOVERNMENT.

5. ALL WORK NOTED & LOCATED IN THESE DOCS SHALL BE

UNDERSTOOD BY THE CONTRACTOR TO REQUIRE ALL NEW

LABOR & MATERIALS UNLESS SPECIFICALLY NOTED TO BE

"EXISTING" OR "BY OTHERS".

WWYK210116

REPLACE HVAC SYSTEM,

B285

KEY PLAN:

GENERAL NOTES:

DISCIPLINE

PROJECT

LOCATION

1 G-101 GENERAL NOTES & VICINITY MAP

SHT.SEQ. SHEET TITLE

OF

TI

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

KL

AH

O M

A

PR

O

JE

C

T

IN

FO

R

M

AT

IO

N

D

ES

IG

N

F

IL

E

LO

C

AT

IO

N

R

EV

IS

IO

N S

M

AR

K

D

ES

IG

N

G R

O U

P:

D R

AW

N

B Y:

C H

EC

KE

D B

Y:

D

ES

IG

N

ED

B

Y:

D

AT

E D

ES

C

R

IP

TI

O

N

1 2 3 4 5

E

D

C

B

A

M

AN

AG

EM

EN

T

IN

FO

R M

AT

IO

N

1 2 3 4 5

E

D

C

B

A

IS

SU

E D

AT

E:

SHEET

SHEET NUMBER

SH

EE

T

TI

TL

E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

MD-101 MECHANICAL HVAC DEMOLITION PLAN

ED-101 POWER - LIGHTING DEMOLITION PLAN

E-101 POWER - LIGHTING RENOVATION PLAN

CONCEPT

W W

YK

R

EP

LA

CE

H

VA

C

SY

ST

EM

B2

M

AY

TE

PA

-S R

M

G-101

F

BA

KE

R

L

SE

LH

O

R

ST

En gr

\D es ig n\ s\

\2

6\

0_ Su pp or t\0 _3

_D ra w in gs \M od el

GE

NE

RA

L N

OT

ES

AN

D

VI

CI

NI

TY

M

AP

1 6

A-101 ARCHITECTURAL DEMOLITION / RENOVATION PLAN

F-101 FIRE PROTECTION - DEMOLITION AND RENOVATION PLAN

-A

UG

-2

AM

EN

DM

EN

T

RE

VI

SI

ON

S

PROJECT

LOCATION

TINKER AFB, OK

VICINITY MAP

BASE

OPERATIONS

B240

GOTT

GATE

TINKER GATE

PASS & ID B6611

HRUSKOCY

GATE

EAKER GATE

FIRE DEPARTMENT

B117

VANCE

GATE

LIBERATOR GATE

HOPE

GATE

LEGEND

CONTRACTOR

HAUL ROUTE

LANCER

GATE

TRUCK GATE

PIAZZA GATE

BASE CIVIL

ENGINEER

B400

(FUTURE

HAUL ROUTE)

(F

UT

UR

E

HA

UL

R

OU

TE

FUTURE

TRUCK GATE

FUTURE

HAUL ROUTE

TINKER AFB, OK

VICINITY MAP

BASE

OPERATIONS

B240

CONTRACTING

B3

GOTT

GATE

TINKER GATE

PASS & ID B6611

HRUSKOCY

GATE

EAKER GATE

FIRE DEPARTMENT

B117

VANCE

GATE

LIBERATOR GATE

HOPE

GATE

LEGEND

CONTRACTOR

HAUL ROUTE

LANCER

GATE

TRUCK GATE

PIAZZA GATE

BASE CIVIL

ENGINEER

B400

(FUTURE

HAUL ROUTE)

(F

UT

UR

E

HA

UL

R

OU

TE

FUTURE

TRUCK GATE

FUTURE

HAUL ROUTE 9001

R U

N W

AY

8/

RUNWAY 13/31

TA

XI

W

AY

G

TAXIW

AY H

TAXIWAY B

TAXIWAY C

TAXIWAY M

TA

XI

W

AY

K

TAXIWAY E

TAXIWAY A

TA

XIW

AY E

E

TAXIWAY F

TAXIWAY D

TAXIWAY E

TAXIWAY J

TA

XI

W

AY

G

TAXIWAY A

TAXIW

AY H

TAXIWAY C

TAXIWAY D

TAXIWAY EE

TAXIWAY F

Elm C reek

Crutcho Creek

Kuhlman Creek

Soldier Creek

Kuhlman Creek

Elm C reek

East Crutcho Creek

Elm Creek

El m

C re ek

Elm Creek

Elm C reek

Elm CreekElm C reek

Ku hlm an C re ek

Ea st

C ru tc ho

C re ek

Elm C ree k

West Crutcho Creek

W es t C ru tc ho

C re ek

Elm Creek

Soldier Creek

Elm C reek

Soldier CreekSoldier Creek

Ea st

C ru tc ho

C re ek

Elm Creek

Ea st

C ru tc ho

C re ek

East C rutcho C reek

Soldier Creek

So ld ie r C re ek

East C rutch o Creek

Soldier C reek

Soldier C reek

So ld ie r C re ek

East Crutcho Creek

416506

21222121

59475946

11401128

62540

61089

838837

62509

62528

62523

62501X

43774

62512

62516

62525

3592135916

99999

62543

32101

71086

53902

50414

55300

56601

930G

948-E

911-E

948-W

61019

911-W

33001

35913

62501

65672

930S

45134

43609

42116

62517

62515

62526

62527

62503

62513

61289

62542

62501OK

11289

62501

15930

15908

15904

15904

15908

15908

15904

15904

15908

62502

41046

62501

62514

62501

61018

71089

45134

96022

43120

41157

44045

45815

40592

43610

62522

41163

15930

15930

11824

Arnold St.

Ea st

D r.

SE 74th St

SE 59th St.

Ai r D ep ot

Patrol Rd.

St af f D r.

Reserve Rd.

5th Ave

"A " A ve

M un iti on s R d.

W ar eh ou se R d.

"B " A ve

7th St.

"H " A ve

M cN ar ne y Av e.

Mitchell Ave

Al er t R d.

Co ok

A ve

W es t D r.

"E "A ve

Extender Dr.

Sentry Rd.

34th St.

Twining Dr.

5th Ave.

Jo ne s

Globemaster Dr.

To w er R d.

Vanaman Rd.

In du st ria l B lv d.

So ut h St

1st St.

Do ol itt le

A ve

Pi cn ic R d.

Ja m es D r.

W ol fe D r.

Ai r D ep ot

Ai r D ep ot

"D " A ve

Perimeter Rd.

Rapcon Rd.

Reserve Rd

"L " A ve

Mercury Rd.

1st St.

Br ow n Dr

Po nd

R d.

O ld

A ir

De po t

Airey Dr.

Bradley Dr.

Entrance Road "C"

Entrance Road "A"

"C " A ve

"C " A ve

Vandenberg Dr.

Hi llt op R d.

Do rm ito ry

R d.

Dormitory Rd.

"M " A ve

Chennault Dr.

M itc he ll A ve

Spaatz Dr.

Co m m od ity D r.

Doolittle Ave

W hi te D r.

3rd Ave.

"D " D riv e

Ba ll

Pa rk

R d.

Joint STARS Dr.

Ai r D ep ot

B lv d

Turbine Dr. Turbine Dr.

Central Plant Dr.

6th St.6th St.

Falco n Dr.

Blackb ird

Dr.

W ey la nd

L oo p

Pegasus Dr.

Thunderbolt D r.

Munitions Rd. Ext.

Codding Rd.

Starlifter Dr.

Chidlaw Ct.

Co rs ai r D r.

Ra pt or Ct

N ig ht H aw k

Ct

Ph an to m

D r.

Fr an kl in

Po w er ho us e

Dr

Sk ym as te r D r.

Spaatz Ct.

La w re nc e

M un de ll

Nabors Dr.

In tr ud er

D r.

M cN ic kl e

M ill er D r.

Ta il

Fe at he r D r.

Holden Dr.

Ai re y C ir.

Smith Ct.

Ra ve n Ct

Air Dep ot Ai r D ep ot

Vanaman Rd.

1st St.

1st St.

TAXIWAY F

Ra w li ng s A ve

Mitc he ll A ve

Mercury Rd.

Ra ily ar d

Rd

He rc ul es

R d.

"F " A ve

Pr op ul sio n Dr

Stratofortress Dr.

96021

Arnold St.

OF

TI

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

KL

AH

O M

A

PR

O

JE

C

T

IN

FO

R

M

AT

IO

N

D

ES

IG

N

F

IL

E

LO

C

AT

IO

N

R

EV

IS

IO

N S

M

AR

K

D

ES

IG

N

G R

O U

P:

D R

AW

N

B Y:

C H

EC

KE

D B

Y:

D

ES

IG

N

ED

B

Y:

D

AT

E D

ES

C

R

IP

TI

O

N

1 2 3 4 5

E

D

C

B

A

M

AN

AG

EM

EN

T

IN

FO

R M

AT

IO

N

1 2 3 4 5

E

D

C

B

A

IS

SU

E D

AT

E:

SHEET

SHEET NUMBER

SH

EE

T

TI

TL

E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

CONCEPT

W W

YK

R

EP

LA

CE

H

VA

C

SY

ST

EM

B2

M

AY

TE

PA

-S R

M

M N

O

EL

A-101

K

FR

EE

M

AN

L

SE

LH

O

R

ST

En gr

\D es ig n\ s\

\2

6\

0_ Su pp or t\0 _3

_D ra w in gs \M od el

AR

CH

IT

EC

TU

RA

L

DE

MO

LIT

IO

N

RE

NO

VA

TI

ON

PL

AN

2 6

GENERAL NOTES

KEYED NOTES

DEMOLISH THE ENTIRE ACOUSTICAL TILE CEILING SYSTEM INCLUDING GRID.

PROVIDE AND INSTALL NEW 2' X 2' ACOUSTICAL TILE CEILING AND GRID.

TYPE ARMSTRONG DUNE WITH WHITE GRID.

ANY PAINTED WALL PLANES THAT ARE DAMAGED SHALL BE REPAIRED TO

MATCH THE EXISTING WALL FINISH AND THE FULL WALL PLANE SHALL BE

PAINTED TO MATCH EXISTING.

A-101

ARCHITECTURAL DEMOLITION / RENOVATION PLAN

SCALE: 1/8" = 1'-0"

1. THE DRAWING WAS PREPARED FROM EXISTING DRAWINGS AND LIMITED ACCESS

FOR FIELD OBSERVATIONS. CONTRACTOR SHALL FIELD VERIFY EXISTING

CONDITIONS FOR ACCURACY.

1WORK AREA

LEGEND:

= NOT IN CONTRACT (NIC)

-A

UG

-2

AM

EN

DM

EN

T

RE

VI

SI

ON

S

NIC

MECH

BOILER

MECH

BREAK ROOM

JANITOR

MENS

ROOM

WOMENS

ROOM

VESTIBULE

CO

RR

ID

OR

VESTIBULE

120CORRIDOR

OPEN

OFFICE

OPEN

OFFICE

TOILET

COMM/ELEC

CLOSET

C.O.'S

OFFICE

ASS'T &

RECP

OPEN

OFFICE

OFFICE

OFFICE

CONFERENCE

ROOM

CHIEF'S

OFFICE

OFFICE

A/V CLOSET

OFFICE

1 BUILDING 285 - FIRST FLOOR PLAN

"MDP"

PAVILION

MECH

BOILER

MECH

BREAK ROOM

JANITOR

MENS

ROOM

WOMENS

ROOM

VESTIBULE

CO

RR

ID

OR

VESTIBULE

120CORRIDOR

A

A

K-1728CHESAPEAKEC_LAVATORYVITREOUS CHINA K-4330KINGSTONC_TOILETSVITREOUS CHINA

"A"-2 "A"

AC-1

OPEN

OFFICE

OPEN

OFFICE

TOILET

COMM/ELEC

CLOSET

C.O.'S

OFFICE

ASS'T &

RECP

OPEN

OFFICE

OFFICE

OFFICE

CONFERENCE

ROOM

CHIEF'S

OFFICE

OFFICE

A/V CLOSET

OFFICE

FC-2

AutoCAD SHX Text S

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

KL

AH

O M

A

PR

O

JE

C

T

IN

FO

R

M

AT

IO

N

D

ES

IG

N

F

IL

E

LO

C

AT

IO

N

R

EV

IS

IO

N S

M

AR

K

D

ES

IG

N

G R

O U

P:

D R

AW

N

B Y:

C H

EC

KE

D B

Y:

D

ES

IG

N

ED

B

Y:

D

AT

E D

ES

C

R

IP

TI

O

N

1 2 3 4 5

E

D

C

B

A

M

AN

AG

EM

EN

T

IN

FO

R M

AT

IO

N

1 2 3 4 5

E

D

C

B

A

IS

SU

E D

AT

E:

SHEET

SHEET NUMBER

SH

EE

T

TI

TL

E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

CONCEPT

W W

YK

R

EP

LA

CE

H

VA

C

SY

ST

EM

B2

M

AY

TE

PA

-S R

M

A

AR

M

ST

R O

N G

MD-101

K

FR

EE

M

AN

L

SE

LH

O

R

ST

En gr

\D es ig n\ s\

\2

6\

0_ Su pp or t\0 _3

_D ra w in gs \M od el

ME

CH

AN

IC

AL

H

VA

C

DE

MO

LIT

IO

N

PL

AN

3 6

GENERAL NOTES

KEY NOTES

DEMOLISH AND REPLACE THE EXISTING PACKAGED UNIT AND ITS

ASSOCIATED CONTROLS.

ALL OTHER COMPONENTS OF THE EXISTING HVAC SYSTEM IN THE WEST

ADDITION OF THE BUILDING ARE TO REMAIN.

DEMOLISH ALL HVAC EQUIPMENT IN THE ORIGINAL BUILDING FOOTPRINT,

INCLUDING BUT NOT LIMITED TO THE AIR HANDLER, CONDENSER, VARIABLE

AIR BOXES, CONTROLS, THERMOSTAT, DUCTWORK, HOT WATER REHEAT

PIPING, EXHAUST FANS, AND THE SUPPLY / RETURN AIR DEVICES. DESIGN

AND INSTALL A NEW HVAC SYSTEM IN ACCORDANCE WITH THE STATEMENT

OF WORK.

EXISTING BOILER TO REMAIN PROVIDED LOAD ANALYSIS SHOWS SUFFICIENT

CAPACITY.

DEMOLISH THE EXISTING MECHANICAL ROOM LOUVERS, DAMPERS, AND UNIT

HEATER. DESIGN AND INSTALL REPLACEMENTS TO PROVIDE MECHANICAL

ROOM VENTILATION AND FREEZE PROTECTION.

MD-101

MECHANICAL HVAC DEMOLITION PLAN

SCALE: 1/8" = 1'-0"

1. THIS DRAWING WAS PREPARED FROM THE EXISTING AS-BUILT DRAWINGS FOR

PROJECT WWYK070335. CONTRACTOR SHALL FIELD VERIFY EXISTING CONDITIONS

FOR ACCURACY.

2. IF CONTAMINANTS SUCH AS CHEMICAL VAPORS OR WELDING FUMES, ETC. ARE

GENERATED DURING CONSTRUCTION, THE CONTRACTOR SHALL USE CONTROLS

TO PREVENT IMPACT TO BUILDING OCCUPANTS.

3. INSTALL A WATER TREATMENT SYSTEM FOR ANY NEW HYDONIC WATER SYSTEM,

SUCH AS A BOILER, USED IN THE NEW HVAC DESIGN. ANY REHEAT HYDRONIC

PIPING THAT IS REUSED IN THE NEW DESIGN IS TO BE FLUSHED PRIOR TO

INSTALLING THE WATER TREATMENT SYSTEM.

4. PROVIDE AND INSTALL A CARBON MONOXIDE DETECTION SYSTEM IN THE

MECHANICAL ROOM IN ACCORDANCE WITH UFC 3-600-01.

5. ALL NEW HVAC EQUIPMENT; PACKAGED EQUIPMENT, AIR HANDLER, CONDENSER,

BOILER, ETC., SHALL BE COMMISSIONED BY A CONTRACTOR INDEPENDENT FROM

THE PRIME. CONTRACTOR SHALL PROVIDE SUBMITTALS TO THE GOVERNMENT

FOR THE COMMISSIONING AGENT AND COMMISSIONING REPORTS.

33 TYP.

TYP.

TYP.

TYP.

3 TYP.

WEST ADDITION

LEGEND:

= NOT IN CONTRACT (NIC)

-A

UG

-2

AM

EN

DM

EN

T

RE

VI

SI

ON

S

MECH

BOILER

MECH

BREAK ROOM

JANITOR

MENS

ROOM

WOMENS

ROOM

VESTIBULE

CO

RR

ID

OR

VESTIBULE

120CORRIDOR

OPEN

OFFICE

OPEN

OFFICE

TOILET

COMM/ELEC

CLOSET

C.O.'S

OFFICE

ASS'T &

RECP

OPEN

OFFICE

OFFICE

OFFICE

CONFERENCE

ROOM

CHIEF'S

OFFICE

OFFICE

A/V CLOSET

OFFICE

PAVILION

MECH

BOILER

MECH

BREAK ROOM

JANITOR

MENS

ROOM

WOMENS

ROOM

VESTIBULE

CO

RR

ID

OR

VESTIBULE

120CORRIDOR

A

A

K-1728CHESAPEAKEC_LAVATORYVITREOUS CHINA K-4330KINGSTONC_TOILETSVITREOUS CHINA

"A"-2

AC-1

T

OPEN

OFFICE

OPEN

OFFICE

TOILET

COMM/ELEC

CLOSET

C.O.'S

OFFICE

ASS'T &

RECP

OPEN

OFFICE

OFFICE

OFFICE

CONFERENCE

ROOM

CHIEF'S

OFFICE

OFFICE

A/V CLOSET

OFFICE

FC-2

AutoCAD SHX Text J

AutoCAD SHX Text

VB1

AutoCAD SHX Text

FC4

AutoCAD SHX Text

VB2

AutoCAD SHX Text

VB2

AutoCAD SHX Text

VB2

AutoCAD SHX Text

VB2

AutoCAD SHX Text

VB2

AutoCAD SHX Text

VB2

AutoCAD SHX Text

VB1

AutoCAD SHX Text

FC1

AutoCAD SHX Text

VB4

AutoCAD SHX Text

FC3

AutoCAD SHX Text

VB1

AutoCAD SHX Text

FC2

AutoCAD SHX Text

FC2

AutoCAD SHX Text F1

AutoCAD SHX Text

VB1

AutoCAD SHX Text

VB1

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

HEAT

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

KL

AH

O M

A

PR

O

JE

C

T

IN

FO

R

M

AT

IO

N

D

ES

IG

N

F

IL

E

LO

C

AT

IO

N

R

EV

IS

IO

N S

M

AR

K

D

ES

IG

N

G R

O U

P:

D R

AW

N

B Y:

C H

EC

KE

D B

Y:

D

ES

IG

N

ED

B

Y:

D

AT

E D

ES

C

R

IP

TI

O

N

1 2 3 4 5

E

D

C

B

A

M

AN

AG

EM

EN

T

IN

FO

R M

AT

IO

N

1 2 3 4 5

E

D

C

B

A

IS

SU

E D

AT

E:

SHEET

SHEET NUMBER

SH

EE

T

TI

TL

E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

CONCEPT

W W

YK

R

EP

LA

CE

H

VA

C

SY

ST

EM

B2

M

AY

TE

PA

-S R

M

C B

AR

BO

ZA

ED-101

K

FR

EE

M

AN

L

SE

LH

O

R

ST

En gr

\D es ig n\ s\

\2

6\

0_ Su pp or t\0 _3

_D ra w in gs \M od el

PO

W

ER

LIG

HT

IN

G

DE

MO

LIT

IO

N

PL

AN

4 6

GENERAL NOTES

KEYED NOTES

1. CONTRACTOR MUST VERIFY THE ELECTRICAL FIELD REQUIREMENTS AND INSTALL

THE NEW EQUIPMENT IN A NEAT AND WORKMANSHIP MANNER PER CODE, UFC

SPECIFICATIONS AND TINKER AFB ELECTRICAL STANDARDS.

2. THE DRAWING WAS PREPARED FROM EXISTING DRAWINGS AND LIMITED ACCESS

FOR FIELD OBSERVATIONS. CONTRACTOR SHALL FIELD VERIFY EXISTING

CONDITIONS FOR ACCURACY.

3. THE CONTRACTOR SHALL VERIFY THE EXACT LOCATION AND QUANTITIES OF

EXISTING ELECTRICAL FIXTURES, EQUIPMENT, DEVICES AND COMPONENTS

AFFECTED BY THE PROJECT WORKS INCLUDING BUT NOT LIMITED TO ELECTRICAL

PANELBOARDS, DISCONNECTS, RECEPTACLES, SWITCHES, LIGHT FIXTURES,

CABLES, CONDUITS, AND DEDICATED RACEWAYS, ETC.

4. ANY ELECTRICAL FIXTURE, DEVICES, EQUIPMENT AND COMPONENTS

ENCOUNTERED DURING THE DEMOLITION IN AREAS AFFECTED BY THE

REPLACEMENT WORK (INCLUDING ANY ELECTRICAL FIXTURE, DEVICES,

EQUIPMENT OR COMPONENT NOT SHOWN ON THIS DRAWINGS) SHALL BE

PROTECTED FROM PHYSICAL DAMAGE DURING THE DEMOLITION AND

CONSTRUCTION PHASES OF WORK AND SHALL BE RETURN TO THEIR ORIGINAL

OPERABLE STATE (BASED AT TIME OF PROJECT COMMENCEMENT) UPON THE

COMPLETION OF THIS RENOVATION PROJECT.

5. CONTRACTOR SHALL REMOVE AND DISCARD ALL DEMOLISH ITEMS OFF SITE.

6. CONTRACTOR TO REPLACE EXISTING CONDUCTORS AND CONDUIT BACK TO THE

PROTECTIVE DEVICE WITHIN A PANELBOARD OR TO AN EXISTING SPLICE WITHIN AN

EXISTING J-BOX.

7. UNLESS NOTED OTHERWISE, ALL EXISTING EQUIPMENT SHALL REMAIN

OPERATIONAL.

8. REFER TO MECHANICAL DRAWINGS FOR DEMOLITION EQUIPMENT INFORMATION.

9. COORDINATE WITH OTHER TRADES FOR ADDITIONAL DEMOLITION WORK WITHIN

RENOVATED AREA.

DISCONNECT EXISTING POWER CONNECTION FOR THE HVAC UNITS FROM

PANELBOARDS AND/OR SAFETY SWITCHES. REMOVE ALL ASSOCIATED

ELECTRICAL COMPONENTS, PROTECTIVE DEVICES, DISCONNECTING MEANS,

CONTROL, POWER CONDUCTORS, AND CONDUITS.

DISCONNECT AND REMOVE THE EXISTING LIGHT FIXTURES INCLUDING EXIT

SIGNS, EMERGENCY LIGHTS AND ANY OTHER ASSOCIATED COMPONENT

BACK TO THE NEAREST J-BOX.

PANEL "A" WILL BE REPLACED FROM 150A. TO 200A. PANEL. ALL EXISTING

CIRCUITS WILL BE DISCONNECTED.

ED-101

POWER - LIGHTING DEMOLITION PLAN

SCALE: 1/8" = 1'-0"

2 2 2

2 2

2 2 2 2

2 2 2 2

2 2

2 2

2 2

2 2 2 2 2

2 2

2 2

2 2

2 2

2 22

2 2 2 2

2 2

2 2

2 2

2 2

LEGEND:

= NOT IN CONTRACT (NIC)

-A

UG

-2

AM

EN

DM

EN

T

RE

VI

SI

ON

S

"MDP"

PAVILION

"A"

AC-1

CU-1

AHU-1

FC-2

FC-3

FC-1

FC-4

MECH

BOILER

MECH

BREAK ROOM

JANITOR

MENS

ROOM

WOMENS

ROOM

VESTIBULE

CO

RR

ID

OR

VESTIBULE

120CORRIDOR

OPEN

OFFICE

OPEN

OFFICE

TOILET

COMM/ELEC

CLOSET

C.O.'S

OFFICE

ASS'T &

RECP

OPEN

OFFICE

OFFICE

OFFICE

CONFERENCE

ROOM

CHIEF'S

OFFICE

OFFICE

A/V CLOSET

OFFICE

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

KL

AH

O M

A

PR

O

JE

C

T

IN

FO

R

M

AT

IO

N

D

ES

IG

N

F

IL

E

LO

C

AT

IO

N

R

EV

IS

IO

N S

M

AR

K

D

ES

IG

N

G R

O U

P:

D R

AW

N

B Y:

C H

EC

KE

D B

Y:

D

ES

IG

N

ED

B

Y:

D

AT

E D

ES

C

R

IP

TI

O

N

1 2 3 4 5

E

D

C

B

A

M

AN

AG

EM

EN

T

IN

FO

R M

AT

IO

N

1 2 3 4 5

E

D

C

B

A

IS

SU

E D

AT

E:

SHEET

SHEET NUMBER

SH

EE

T

TI

TL

E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

CONCEPT

W W

YK

R

EP

LA

CE

H

VA

C

SY

ST

EM

B2

M

AY

TE

PA

-S R

M

C B

AR

BO

ZA

E-101

K

FR

EE

M

AN

L

SE

LH

O

R

ST

En gr

\D es ig n\ s\

\2

6\

0_ Su pp or t\0 _3

_D ra w in gs \M od el

PO

W

ER

LIG

HT

IN

G

RE

NO

VA

TI

ON

P

LA

N

5 6

GENERAL NOTES

ELECTRICAL KEYED NOTES

1. CONTRACTOR MUST VERIFY THE ELECTRICAL FIELD REQUIREMENTS AND INSTALL

THE NEW EQUIPMENT IN A NEAT AND WORKMANSHIP MANNER PER CODE, UFC

SPECIFICATIONS AND TINKER AFB ELECTRICAL STANDARDS.

2. REFER TO MECHANICAL DRAWINGS FOR ADDITIONAL INFORMATION. VERIFY ALL

POWER CONNECTIONS AND INSTALLATION REQUIREMENTS WITH MANUFACTURERS

PRIOR TO ROUGH-IN.

3. THE CONTRACTOR SHALL VERIFY THE EXACT LOCATION AND QUANTITIES OF

EXISTING ELECTRICAL FIXTURES, EQUIPMENT, DEVICES AND COMPONENTS

AFFECTED BY THE PROJECT WORKS INCLUDING BUT NOT LIMITED TO ELECTRICAL

PANELBOARDS, DISCONNECTS, RECEPTACLES, SWITCHES, LIGHT FIXTURES,

CABLES, CONDUITS, AND DEDICATED RACEWAYS, ETC.

4. CONTRACTOR SHALL REPLACE EXISTING CONDUCTORS FOR THE LIGHTING

EQUIPMENT AND CONDUIT BACK TO THE POWER SOURCE OR TO EXISTING

JUNCTION BOX. NEW LIGHTING ANALYSIS WILL DETERMINE THE LIGHTING

DISTRIBUTION AND LUMENS REQUIRED PER UFC SPECIFICATIONS WITHIN THE

CONSTRUCTION AREA (EACH OFFICE AND HALLWAYS).

5. UNLESS NOTED OTHERWISE, ALL EXISTING EQUIPMENT SHALL REMAIN

OPERATIONAL.

6. CONTRACTOR MUST COORDINATE WITH THE FACILITY MANAGER AND/OR USER

FOR ANY POWER OUTAGES THAT COULD AFFECT THE NORMAL OPERATION OF THE

FACILITY.

7. ALL NEW EQUIPMENT MUST BE TESTED TO VERIFY THE PROPER FUNCTIONALITY

AND OPERATION. REFER TO ANSI/NETA ATS AND PROVIDE A WRITTEN REPORT FOR

GOVERNMENT REVIEW AND APPROVAL.

DESIGN NEW LIGHTING LAYOUT PER UFC AND BASE STANDARDS.

PROVIDE AND INSTALL NEW WALL PACK LIGHTING FIXTURE EQUAL TO

LITHONIA, MODEL TWH LED. MOUNT AT THE NORTH WALL AND CONNECT TO

THE EXISTING EXTERIOR LIGHTING CIRCUIT.

PROVIDE AND INSTALL NEW LED LIGHT FIXTURE EQUAL TO LITHONIA MODEL

UFIT, 4000K, 80 CRI, 5000LM, (TWO WITH INTEGRAL BATTERY BACKUP).

PROVIDE AND INSTALL NEW LED TROFFER LIGHT FIXTURE EQUAL TO LITHONIA

MODEL 2BLT4 (OR 2BLT2 ACCORDINGLY, 4000K, 80CRI, 5000LM.

PROVIDE AND INSTALL NEW AHU PER MANUFACTURER SPECIFICATIONS. NEW

RGS CONDUIT, HEAVY DUTY DISCONNECT AND ANY OTHER ASSOCIATED

COMPONENT MUST BE WEATHERPROOF RATED.

PROVIDE AND INSTALL NEW AHU PER MANUFACTURER SPECIFICATIONS. NEW

RGS CONDUIT, HEAVY DUTY DISCONNECT, VFD, SUPPORS AND ANY OTHER

ASSOCIATED COMPONENT MUST BE WEATHERPROOF RATED.

PROVIDE AND INSTALL NEW PANELBOARD "MDP" PER UPDATED LOAD

CALCULATIONS. "MDP" TO BE RATED AT 208Y/120V., 3-PHASE, 4-WIRE.

PROVIDE AND INSTALL NEW PANELBOARD "A" PER UPDATED LOAD

CALCULATIONS. "A" TO BE RATED AT 208Y/120V., 3-PHASE, 4-WIRE.

E-101

POWER - LIGHTING RENOVATION PLAN

SCALE: 1/8" = 1'-0"

3 3

TYP.

TYP.

TYP.

1 TYP.

= NOT IN CONTRACT (NIC)

-A

UG

-2

AM

EN

DM

EN

T

RE

VI

SI

ON

S

"MDP"

PAVILION

F

F

E

E

E E

"A"

E

AC-1

H/S

H/S

E

E

E E

E

CU-1

AHU-1

MECH

BOILER

MECH

BREAK ROOM

JANITOR

MENS

ROOM

WOMENS

ROOM

VESTIBULE

CO

RR

ID

OR

VESTIBULE

120CORRIDOR

OPEN

OFFICE

OPEN

OFFICE

TOILET

COMM/ELEC

CLOSET

C.O.'S

OFFICE

ASS'T &

RECP

OPEN

OFFICE

OFFICE

OFFICE

CONFERENCE

ROOM

CHIEF'S

OFFICE

OFFICE

A/V CLOSET

OFFICE

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

KL

AH

O M

A

PR

O

JE

C

T

IN

FO

R

M

AT

IO

N

D

ES

IG

N

F

IL

E

LO

C

AT

IO

N

R

EV

IS

IO

N S

M

AR

K

D

ES

IG

N

G R

O U

P:

D R

AW

N

B Y:

C H

EC

KE

D B

Y:

D

ES

IG

N

ED

B

Y:

D

AT

E D

ES

C

R

IP

TI

O

N

1 2 3 4 5

E

D

C

B

A

M

AN

AG

EM

EN

T

IN

FO

R M

AT

IO

N

1 2 3 4 5

E

D

C

B

A

IS

SU

E D

AT

E:

SHEET

SHEET NUMBER

SH

EE

T

TI

TL

E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

CONCEPT

W W

YK

R

EP

LA

CE

H

VA

C

SY

ST

EM

B2

M

AY

TE

PA

-S R

M

R R

EY

N

O

LD

S

F-101

R R

EY

N

O

LD

S

L

SE

LH

O

R

ST

En gr

\D es ig n\ s\

\2

6\

0_ Su pp or t\0 _3

_D ra w in gs \M od el

FI

RE

P

RO

TE

CT

IO

N

DE

MO

LIT

IO

N

RE

NO

VA

TI

ON

P

LA

N

6 6

GENERAL NOTES

KEYED NOTES

1. SCOPE OF WORK: SCOPE OF FIRE PROTECTION WORK IS WITHIN THE BOUNDARY

SHOWN, GENERALLY 16 FT FROM THE BUILDING, AND CONSISTS OF THE

FOLLOWING TASKS:

1.1. PROTECT THE EXISTING FIRE SPRINKLER SYSTEM DURING EXECUTION OF

THIS PROJECT.

1.2. DEMOLISH THE EXISTING CONVENTIONAL FIRE ALARM SYSTEM, RETURNING

PANELS AND DEVICES TO THE GOVERNMENT.

1.3. DESIGN AND PROVIDE A NEW ADDRESSABLE COMBINATION FIRE ALARM AND

MASS NOTIFICATION SYSTEM COMPLYING WITH UFC 3-600-01, UFC 4-021-01

AND TINKER AFB FIRE PROTECTION STANDARD.

1.4. PROVIDE LISTED FIRE STOPPING ASSEMBLIES PROTECTING PENETRATIONS

OF FIRE RATED BARRIERS.

2. THE DRAWING WAS PREPARED FROM EXISTING DRAWINGS AND LIMITED ACCESS

FOR FIELD OBSERVATIONS. NOT ALL FLOOR TO CEILING SYSTEMS FURNITURE

WALLS SHOWN. ALL FIRE ALARM DEVICES MAY NOT BE SHOWN ON THIS DRAWING.

THE CONTRACTOR SHALL FIELD VERIFY THE EXACT LOCATION AND QUANTITIES OF

EXISTING FIRE ALARM EQUIPMENT, DEVICES AND COMPONENTS INCLUDING BUT

NOT LIMITED TO CONTROL PANELS, ALARM TRANSCEIVER, PULL STATIONS,

NOTIFICATION APPLIANCES, SMOKE DETECTORS, HEAT DETECTORS, AND DUCT

SMOKE DETECTORS, ETC.

3. ALL FIRE ALARM SYSTEM DEVICES AND PANELS SHALL BE REMOVED AND

RETURNED TO THE GOVERNMENT. THEY SHALL BE PROTECTED FROM PHYSICAL

DAMAGE DURING THE DEMOLITION . THE REMAINDER OF THE SYSTEM IS TO BE

DEMOLISHED.

4. CONTRACTOR SHALL REMOVE OFF SITE AND PROPERLY DISPOSE OF ALL

DEMOLISH ITEMS NOT TO BE RETURNED TO THE GOVERNMENT.

5. COORDINATE WITH OTHER TRADES FOR WORK WITHIN AREA OF RENOVATION.

EXISTING FIRE SPRINKLER RISER.

CONCEALED DUCT DETECTR

F-101

FIRE PROTECTION - DEMOLITION AND RENOVATION PLAN

SCALE: 1/8" = 1'-0"

LEGEND:

LIMITS OF FIRE PROTECTION WORK

AREA NOT IN CONTRACT

N.I.C.

00 4' 8'1' 2'

-A

UG

-2

AM

EN

DM

EN

T

RE

VI

SI

ON

S

"MDP"

PAVILION

"A"

AC-1

H/S

H/S

CU-1

AHU-1

"MDP"

PAVILION

"A"

AC-1

H/S

H/S

F

F

F

F

F

MECH

BOILER

MECH

BREAK ROOM

JANITOR

MENS

ROOM

WOMENS

ROOM

VESTIBULE

CO

RR

ID

OR

VESTIBULE

CORRIDOR

OPEN

OFFICE

OPEN

OFFICE

TOILET

COMM/ELEC

CLOSET

C.O.'S

OFFICE

ASS'T &

RECP

OPEN

OFFICE

OFFICE

OFFICE

CONFERENCE

ROOM

CHIEF'S

OFFICE

OFFICE

A/V CLOSET

OFFICE

OFFICE

RTS

D

D

D

DD

D

D

D

D

D

D

D

D

D

D

D

D

D

DD

D

D D

D

D

D

D

D

D

D

D

D D

D

D D

D

D

D

D

D

D

D

F

RTS

FIRE ALARM CONTROL PANEL

FA TRANSCEIVER PANEL

MANUAL PULL STATION

WATER FLOW SWITCH

VALVE TAMPER SWITCH

SPOT SMOKE DETECTOR

DUCT SMOKE DETECTOR

REMOTE TEST STATION

NOTIFICATION HORN/STROBE

ANTENNA - OMNI DIRECTIONAL

FIRE ALARM LEGEND

DEVICE SUBSCRIPT:

D - EXISTING TO DEMOLISHED / REMOVED

E - EXISTING TO REMAIN

AutoCAD SHX Text

TRAN

AutoCAD SHX Text

FACP

AutoCAD SHX Text

TRAN

FACP

01-210116-G101-G101.pdf
Sheets and Views
G101
02-210116-A101-A101.pdf
Sheets and Views
A101
03-210116-MD101-MD101.pdf
Sheets and Views
MD101
04-210116-ED101-ED101.pdf
Sheets and Views
ED101
05-210116-E101-AE101.pdf
Sheets and Views
AE101
06-210116-F101-FD101.pdf
Sheets and Views
FD101

File details come from the government source that posted it. Updated .