Solicitation Amendment FA813726R00310001.pdf
PDF 8 MB Posted
- Solicitation number
- FA813726R0016
About this file
This is a Solicitation, Offer, and Award document (Standard Form 1442) for a construction order to install MNS (Meteorological Measurement System) and replace heat detectors (B976 model) at Tinker Air Force Base in Oklahoma. The project is identified as WWYK230170 and is classified as a Negotiated (RFP) Request for Proposal under NAICS code 236220 with a size standard of USD 45,000,000 in annual receipts.
The solicitation is issued by FA8137 AFSC PZIOC at Tinker AFB and requires sealed bids with one original copy due by 03:00 PM local time on June 19, 2026. The estimated project magnitude ranges from $1,000,000 to $5,000,000. Performance must begin within 10 calendar days and be completed within 330 calendar days of receiving the Notice to Proceed. The contract is firm fixed price for both design and construction services. A bid guarantee is required (marked as "YES"), and offers must remain valid for 120 calendar days following submission. The government plans to award a single construction order using Lowest Priced Technically Acceptable (LPTA) source selection procedures with technical and price evaluation. Offerors must submit technical proposals addressing capability and management, schedule and planning, compliance with design specifications, and detailed price proposals with supporting documentation including subcontractor quotes, take-off calculations, and manufacturer information. All proposals must conform to specified page formatting requirements (8.5 x 11 inches, Arial 12-point minimum, 1.5 line spacing) and include proprietary data markings and CUI designations. Award will be made to the lowest evaluated priced proposal meeting acceptability standards for technical requirements, terms and conditions, and all applicable federal contracting regulations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA813726R00310001
Section L - Instructions, Conditions, & Notices to Offerors or Quoters
Section L - Instructions, Conditions, and Notices to Offerers
1.0 General Instructions
1.1. The government plans to award a single construction order for the project described in the Order Proposal Request (OPR) in accordance with (IAW) the statement of work (SOW) drawings, and specifications. This ITO shall take precedence should there be any conflict between the Basic Ordering Agreement (BOA) and this ITO.
1.2. This acquisition will utilize Lowest Priced Technically Acceptable (LPTA) Source Selection procedures with technical proposals IAW the Multiple Award Contract (MAC)
BOA procedures and in accordance with FAR Part 15.3 as supplemented. This ITO provides general guidance for preparing proposals as well as specific instructions on the format and content of the proposal. The offerer's proposal must include all data and information requested by this ITO. Non-conformance with the instructions provided in this ITO may result in an offerer's proposal being determined ineligible for award. The offer shall be compliant with the requirements as stated in the OPR and its attachments for this construction project.
1.3. The offerer's completed proposal shall consist of the completed and signed OPR, to include any amendments issued, with a cover letter delineating any exceptions taken to the OPR terms and conditions with accompanying rationale. However, offerors are cautioned that any noncompliance with the terms and conditions of the OPR may cause their proposal to be determined ineligible for award.
1.4. Submit only one proposal for the project, if multiple proposals or proposal options are submitted, it may cause your submission to be technically unacceptable. Your proposal, to include work plan, price, and bid bond must be provided to this office not later than the response stated on the SF 1442, block 13a, or amendment if applicable.
1.5. The Procurement Contracting Officer (PCO) is the sole point of contact for this acquisition. Exchanges of information between government and offerers will be controlled by the PCO.
1.6. Email may be used to transmit the proposal and must include "Company Name, Source Selection Information - See FAR 2.101 and 3.104" in the subject line of the email. When submitting source selection information via email, file suppression utilities, to include but not limited to zip files, will not be accepted.
1.7. Do not provide any password protected files as part of the proposal. The electronic copies of the proposal shall be submitted in a format readable by Microsoft (MS)
Word 2007, 2010, or 2013, MS Excel 2007, 2010 or 2013, MS-Power Point 2007, 2010, or 2013, and MS-Project 2013, and Adobe Acrobat Portable Document Format
(PDF), as applicable. Do NOT submit any documents in PDF format that are copied as "images." When creating PDF files always create to enable textual search and copy functions.
1.8. The PCO will promptly notify offerors of any decision to exclude them from the competitive range, whereupon they may request and receive a debriefing IAW FAR
15.505. Offerers excluded from the competitive range may request a pre-award debriefing or they may choose to wait until after the source selection decision to request a post-award debriefing. However, offerers excluded from the competitive range are entitled to no more than one debriefing. The PCO will notify unsuccessful offerers in accordance with FAR 15.503. Upon such notification, unsuccessful offerers may request and receive a debriefing. Offerers desiring a debriefing must make their request
IAW the requirements of FAR 15.505 or 15.506, as applicable.
1.9. If an offerer believes that the requirements in these instructions contain an error, omission, or are otherwise unsound, the offerer shall immediately notify the PCO in writing with supporting rationale as well as the remedies the offerer is asking the PCO to consider as related to the omission or error. The offeror is reminded that the government reserves the right to award this effort based on the initial proposal, as received, without discussions. This reservation includes matters of additional submittals of the initial proposal.
1.10. If this OPR is amended, all terms and conditions that are not amended remain unchanged and in full force and effect. Offerers shall acknowledge receipt of any amendment and provide confirmation upon submission of the offerer's proposal. Any unacknowledged amendments in the offerer's proposal will render the offerer ineligible for award.
1.11. Proposals and modifications to proposals shall be submitted in via previously mentioned method addressed to the contracting specialisVcontracting officer at the address shown on OPR and showing the time and date specified for receipt, the OPR number, and the name and address of the offerer.
1.12. The government intends to award without exchanges; therefore, the proposal should contain the offerer's best terms. However, the government reserves the right to conduct exchanges if deemed in its best interest. Exchanges are interactions between the PCO and the offerer and may address any aspect of the proposal. Offerer responses to exchanges will be considered in making the award selection decision.
1.13. Each page containing proprietary information should be so marked.
1.14. Each page should contain the legend "CUI SOURCE SELECTION INFORMATION-SEE FAR 2.101 and 3.104" at the bottom of each sheet.
1.15. Page Size and Format
1.15.1. A page is defined as each face of a sheet of paper containing information. When both sides of a sheet display printed material, it shall be counted as two pages.
Page size shall be 8.5 x 11 inches, not including foldouts. Page line spacing shall be 1.5 lines. Except for the reproduced sections of the solicitation document, the text size shall be no less than Arial 12 points. Tracking, kerning, and leading values shall not be changed from the default values of the word processing or page layout software.
Use at least 1-inch margins on the top and bottom and 3/4-inch side margins. Pages shall be numbered sequentially by volume. These page format restrictions shall apply to responses to Evaluation Notice (ENs). These limitations shall apply to both electronic and hard copy proposals.
1.15.2. Legible tables, charts, graphs and figures shall be used wherever practical to depict organizations, systems and layout, implementation schedules, plans, etc. These displays shall be uncomplicated and shall not exceed 11 x 17 inches in size. Foldout pages shall fold entirely within the volume, and count as a single page. Foldout pages may only be used for large tables, charts, graphs, diagrams and schematics, not for pages of text. The following limitation only applies to the Technical Volume. Text intended for evaluation within all figures, charts, tables, and graphs, to include imbedded images, shall be no less than Arial 8-pt. These limitations shall apply to both electronic and hard copy proposals. Any text within figures, charts, tables, and graphs which do not meet this requirement will not be considered in the evaluation. These limitations shall apply to both electronic and hard copy proposals.
2.0. Factor 1 - Technical
2.1. In the Technical Volume of the proposal, address your proposed approach to meeting the minimum performance or capability requirements of the technical requirements identified in the OPR. The technical proposal should be specific and complete. Legibility, clarity, and coherence are very important. Your responses will be evaluated against the technical subfactors defined in Section M - Evaluation Factors for Award. Using the instructions provided below, provide as specifically as possible the actual methodology you would use for accomplishing/satisfying the technical subfactors. All the requirements specified in the OPR are mandatory. By your proposal submission, you are representing that your company will perform all the requirements specified in the OPR. Mere recitation of the OPR requirements, or phrases that refer to the government's SOW, without sufficient supporting information as to how work will be accomplished will not be accepted. Narratives shall provide detail of sufficient level to allow one skilled in engineering and the building trades to make a sound decision as to the technical viability of the proposal. The technical volume shall include:
a) Technical Volume Cover Sheet. The technical order volume shall include a cover sheet containing date, OPR number, project number and title, offerer contact information, and assertion the proposal meets the mandatory completion date stated in the OPR.
b) Project Narrative. The project narrative shall clearly demonstrate the offerer's understanding of the project scope by including the following information:
1) Project synopsis (description)
2) Proposed method of accomplishing the work
3) Type of site field verification performed
4) Anticipated user impacts
5) Protection of government property during construction
6) Supplemental drawings/sketches
7) In-house design calculations
8) Estimating notes
9) Take-off calculations to justify quantities used in proposal (includes Subcontractor's calculations)
10) Manufacturer supplied drawings / calculations
11) Catalog/product technical information
12) Assumptions
13) Clarifications and exceptions
14) Supporting documentation
2.2. Technical Subfactor 1: Capability and Management
2.2.1. Describe capability and commitment to support an on-site management team, including a sole source of responsibility for both design and construction of this project
IAW Section 3.12. Contractor Personnel Requirements and 3.12.5.1 to 3.12.3.2 Design Program Manager within the SOW.
2.2.2. Describe how your organization will manage, supervise, and coordinate the subcontractor's work and who in the organization will be responsible for this management and coordination that is required IAW all Section 3.12.6 of the SOW.
2.2.3. Describe how warranty support, unforeseen site conditions, design errors, etc. will be handled by your organization IAW the Warranty of Construction Clause FAR
52.246-21and the Differing Site Condition Clause FAR 52.236-2.
2.2.4. Provide a Team List of the primary point of contacts IAW Section 3.12 Contractor Specific Requirements within the SOW.
2.3. Technical Subfactor 2: Schedule and Planning.
2.3.1. The offerer shall include a proposed construction schedule that meets or improves the mandatory completion date stated in the OPR. The offerer's proposed schedule shall demonstrate a reasonable and realistic sequence of activities which represent all work to be performed throughout the entire order performance period, while considering the major work elements from the detailed price proposal, as well as submittal reviews, mobilization, material delivery times, anticipated weather delays, and final inspection/closeout IAW Section 3.6.1 of the SOW.
2.3.2. In developing the schedule, note that there will be submittals; milestones (such as final inspections); and construction-related permits/requests (such as Outage/
Closure Requests or Excavation Permits) that will require longer lead times for Government coordination/approval listed in the of section 3.6.2 of the SOW.
2.3.3. Specific timelines for staging area approvals, airfield waivers, outage requests and other Government approvals are provided in the SOW Section 3.6.2 in table listed as "Delivery Schedule & Submittals".
3.0. Factor 2 - Price
3.1. In the price volume, the offeror shall provide a fully supported price proposal. Compliance with these instructions is mandatory and failure to provide all the required data may result in an offerer being determined ineligible for award. The offeror shall provide a detailed price proposal describing each element of the design and construction effort. Design and construction price shall be provided IAW the contract line item (CUN) structure as requested in the OPR. The order proposal shall provide the following supporting documentation so that the government team can evaluate the reasonableness of your proposed price. All pricing information shall be addressed
ONLY in the Price Proposal and Order Documentation volumes. Work hour estimates, and material kinds and quantities may be used in other volumes only as appropriate for presenting rationale for alternatives or design and trade-off decisions.
3.2. The Pricing Volume shall include the following:
a) Price Volume Cover Sheet. The price volume shall include a cover sheet containing date, OPR number, project number and title, offerer contact information, CUN prices and the total price.
b) Detailed Price Proposal
1) Design Price proposals shall include proposed labor categories, labor hours per category, and labor rates per category. The design price shall be submitted as a total design price with a breakout of design and non-design price that demonstrates compliance with DFARS 236.606-70, Statutory Fee Limitation.
2) Construction price proposals shall be broken out/subtotaled per the divisions defined by the Construction Specifications Institute (CSI) Master Format System. The offerer shall submit construction price proposals utilizing AF Form 3052, Construction Price Estimate Breakdown, or a contractor generated equivalent that provides the same information.
3) Construction price proposals shall be detailed enough for government reviewers to determine the contractor's understanding of the work to be performed and that the proposal is complete (includes all work items included in the order). Price proposals shall be broken down to at least CSI Level IV.
c) Price Supporting Documentation. The offerer shall provide supporting documentation which demonstrates how the offerer arrived at the proposed price. Documentation the offeror shall submit are listed below. This includes but is not limited to:
1) Subcontractor quotes
2) Supplemental drawings/sketches
3) In-house design calculations
4) Estimating notes
5) Take-off calculations to justify quantities used in proposal (includes subcontractor calculations
6) Manufacturer supplied drawings/calculations
7) Catalog/product technical information
8) The government reserves the right to ask for additional details during the evaluation of offerer's proposals for the purpose of clarification. Any request that would result in a proposal change will be accomplished through formal discussions.
d) Price Assumptions
e) Clarifications and Exceptions
f) Subcontractor quotes. Pricing for subcontracted work shall comply with the following requirements:
1) Subcontractor quotes shall provide the same level of detail and include supporting documentation as described in section 3.2(b), "Detailed Price Proposal".
2) Subcontractor quotes should be based on the best value offered from at least two vendors.
3) Contractor shall provide a copy of the quotes as part of the proposal package.
4) In the event that the minimum of two (2) acceptable vendors cannot be obtained (only one supplier, potential suppliers/subcontractors are unresponsive or respond with
'no bid', etc.), a justification for the single quote shall be submitted as a part of the proposal package.
3.3. Offerer's pricing proposal will be evaluated for reasonableness, balance, and realism. Unreasonable and/or unrealistic proposed prices, initially or subsequently, may be grounds for eliminating a proposal from competition. Additionally, unbalanced pricing may pose an unacceptable risk to the government and may render an offerer's proposal ineligible for award. The offers should be sufficiently detailed to demonstrate their price reasonableness and balance. The burden of proof for credibility of proposed prices rests with the offerer.
3.4. The Government will evaluate proposals for price realism to determine whether proposed prices are based on an adequate understanding of contract requirements and to ensure the proposed price does not pose an unacceptable risk to performance. Offerers shall provide sufficient rationale describing how prices were developed (such as assumptions, historical data, projections, expertise, management decisions, etc). All proposed prices shall be sufficient and adequately proposed to ensure performance is not at an unacceptable risk with prices proposed too low
3.5. The government will evaluate proposals for reasonableness to include completeness. For completeness, offerers must propose pricing for all CUNs except for those labeled as "not separately priced (NSP)". Normally, price reasonableness is established through adequate price competition, but may also be determined through proposal analysis techniques. The burden of proof for credibility of proposed prices rests with the offerer. Offerers shall provide sufficient rationale describing how prices were developed (such as assumptions, historical data, projections, expertise, management decisions, etc.).
3.6. The government will evaluate proposals for balance. The offerer is cautioned against submitting an offer that exhibits unbalanced pricing. Unbalanced pricing may increase performance risk and could result in payment of unreasonable or unrealistic prices. An offer could be so grossly unbalanced that acceptance of the offer would be tantamount to allowing an advanced payment. For this acquisition, balanced pricing is determined with respect to CUN pricing variance. Offerers shall provide rationale for any proposed CUN price increase greater than 5% from one year to another, or any proposed CUN price decrease from one year to another. Unexplained price variances from year-to-year could suggest unbalanced pricing. It is in the Offeror's best interest to provide explanations or supporting rationale for any significant annual CUN price variances.
3.7. The government will evaluate the proposals for compliance with DFARS 236.606-70, Statutory Fee Limitation, as applicable, if design is part of the contract requirement. If applicable, the offerer shall clearly state the design and non-design fees in accordance with DFARS 236.606-70.
3.8. FAR Part 15 applies to this acquisition. IAW FAR 15.403-3-1 (b), prices based on adequate price competition do not require submission of certified cost or pricing data.
In accordance with FAR 15.403-3(a), however, information other than certified cost or pricing data may be required to support price reasonableness. FAR 15.403-3(a)(1) provides for obtaining information other than certified cost or pricing data if needed to determine price reasonableness. Therefore, the FAR does not preclude the requirement for obtaining other than certified cost or pricing data under certain circumstances and the government reserves the right to obtain data as appropriate. Should the PCO determine proposed prices to appear unreasonable or the possibility that an offerer does not fully understand the requirement, the offerors may be required to support price reasonableness via other than certified cost or pricing data. If, after receipt of proposals, the PCO determines that there is insufficient information available to determine price reasonableness and none of the exceptions in FAR 15.403-1 apply, the offerer shall be required to submit certified cost or pricing data.
3.9. All dollar amounts shall be rounded to the nearest cent. All rates shall be rounded to four decimal places to the right of the decimal point.
3.10. Provide assumptions regarding usage of all government property as reflected in your pricing proposal.
4.0. Order Volume
4.1. The purpose of this volume is to provide information to the government for preparing the order document and supporting file. The offerer's proposal shall include a signed copy of the Model Order.
4.2. The offerer shall provide required information to complete clauses as required. Offerers shall ensure that all clauses and provisions that require ''fill-in" information are appropriately completed, including the proposed prices associated with the contract line items in the Schedule of the OPR.
4.3. Bid Guarantee (Bond): A bid guarantee (minimum of 20% of proposal) is required IAW FAR 28.101-1. Failure to furnish a bid guarantee in the proper form and amount may be a cause for rejection of your bid.
4.4. The proposal acceptance period (validity) is specified on the SF 1442, block 13d of the model contracVsolicitation. The offerer shall make a clear statement in the proposal documentation that the proposal is valid until this date.
4.5. The offerer shall provide a statement the offerer has completed the annual representations and certification electronically via the SAM website at https://www.sam.gov/