FA8125-13-Q-0057-0003.doc

DOC document 103 KB Posted

Attached to
Thermal Spray Coating Evaluation - Annual Federal contract opportunity
Solicitation number
FA8125-13-Q-0057
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

Amendment 0003

View the file

Other files for this federal contract opportunity

Other files attached to Thermal Spray Coating Evaluation - Annual, newest first.
File Type Posted
26Nov13(2)PWS_Thermal_Spray.docx DOCX document
FA8125-13-Q-0057-0002.doc DOC document
FA8125-13-Q-0057-0001.doc DOC document
Thermal_Solicitation.doc DOC document
2013_Wage_Determination.docx DOCX document
27Aug13PWS_Thermal_Spray.docx DOCX document
Appendix_B_Scheduled_GFP_Thermal_Spray_Coating_Evaluation_PMXG.xlsx XLSX spreadsheet
APPENDIX_C_Thermal_Spray_Coating_Evaluation_PMXG.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The set aside percentage 100.00% has been deleted.

The Acquisition Set Aside has changed from Small Business to No Preference / Not Listed.

SUPPLIES OR SERVICES AND PRICES

Global Changes

CLIN 0001 -- CLIN 4001

The contract type has changed from FFP to COST.

The NSN has changed from J099-AH-SER-VICE to J099-SM-SER-VICE.

CLIN 0001

The CLIN type priced has been deleted.

The CLIN extended description has changed from The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS). Period of Performance: 1 Dec 13 -30 Nov 14BEQ Testing Unit Price8 Bond Strength Testing $_______ 24 Single Layer Aerospace Coating Analysis $_______16 Dual Layer Aerospace Coating Analysis $_______8 Single Layer Aerospace Coating Analysis (include micro-hardness) $_____ 4 Dual Layer Aerospace Coating Analysis (includes micro-hardness) $_______4 Rockwell Hardness Testing $_______This is a Firm Fixed Price (FFP) Unit Price Line Item.Total FFP utilzing the BEQ provided: $______________CONTRACTOR IS SAM REGISTERED.REGISTRATION IS VALID UNTIL:CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)SEE CLAUSE 252.232-7006 to The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS). Period of Performance: 3 Jan 14 - 2 Jan 15This is a Firm Fixed Price (FFP) per Unit Line Item.Annual Best Estimated Quantity (BEQ) Testing Unit Price8 Bond Strength Testing $_______ 24 Single Layer Aerospace Coating Analysis $_______16 Dual Layer Aerospace Coating Analysis $_______8 Single Layer Aerospace Coating Analysis (include micro-hardness) $_______ 4 Dual Layer Aerospace Coating Analysis (includes micro-hardness) $_______4 Rockwell Hardness Testing $_______Total FFP utilizing the BEQ provided: $______________This is a Not to Exceed (NTE) CLIN. Funding for this line item will be determined by the government at the time of award.CONTRACTOR IS SAM REGISTERED.REGISTRATION IS VALID UNTIL:CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)SEE CLAUSE 252.232-7006.

The pricing detail quantity 1.00 has been deleted.

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Lot

THERMAL SPRAY COATING EVALUATIONS

COST

The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS).

Period of Performance: 3 Jan 14 - 2 Jan 15

This is a Firm Fixed Price (FFP) per Unit Line Item.

Annual Best Estimated Quantity (BEQ) Testing Unit Price

8 Bond Strength Testing $_______

24 Single Layer Aerospace Coating Analysis $_______

16 Dual Layer Aerospace Coating Analysis $_______

8 Single Layer Aerospace Coating Analysis (include micro-hardness) $_______

4 Dual Layer Aerospace Coating Analysis (includes micro-hardness) $_______

4 Rockwell Hardness Testing $_______

Total FFP utilizing the BEQ provided: $______________

This is a Not to Exceed (NTE) CLIN. Funding for this line item will be determined by the government at the time of award.

CONTRACTOR IS SAM REGISTERED.

REGISTRATION IS VALID UNTIL:

CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)

SEE CLAUSE 252.232-7006

FOB: Destination

NSN: J099-SM-SER-VICE

PURCHASE REQUEST NUMBER: F3YCEB3036AQ01

SIGNAL CODE: A

ESTIMATED COST

CLIN 1001

The CLIN extended description has changed from The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS). Period of Performance: 1 Dec 14 thru 30 Nov 15BEQ Testing Unit Price8 Bond Strength Testing $_______ 24 Single Layer Aerospace Coating Analysis $_______16 Dual Layer Aerospace Coating Analysis $_______8 Single Layer Aerospace Coating Analysis (include micro-hardness) $_____ 4 Dual Layer Aerospace Coating Analysis (includes micro-hardness) $_______4 Rockwell Hardness Testing $______This is a Firm Fixed Price (FFP) Unit Price Line Item.Total FFP utilzing the BEQ provided: $______________CONTRACTOR IS SAM REGISTERED.REGISTRATION IS VALID UNTIL:CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)SEE CLAUSE 252.232-7006 to The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS). Period of Performance: 3 Jan 15 - 2 Jan 16This is a Firm Fixed Price (FFP) per Unit Line Item.Annual Best Estimated Quantity (BEQ) Testing Unit Price8 Bond Strength Testing $_______ 24 Single Layer Aerospace Coating Analysis $_______16 Dual Layer Aerospace Coating Analysis $_______8 Single Layer Aerospace Coating Analysis (include micro-hardness) $_______ 4 Dual Layer Aerospace Coating Analysis (includes micro-hardness) $_______4 Rockwell Hardness Testing $_______Total FFP utilizing the BEQ provided: $______________This is a Not to Exceed (NTE) CLIN. Funding for this line item will be determined by the government at the time of award.CONTRACTOR IS SAM REGISTERED.REGISTRATION IS VALID UNTIL:CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)SEE CLAUSE 252.232-7006.

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Lot

OPTION
THERMAL SPRAY COATING EVALUATIONS

COST

The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS).

Period of Performance: 3 Jan 15 - 2 Jan 16

This is a Firm Fixed Price (FFP) per Unit Line Item.

Annual Best Estimated Quantity (BEQ) Testing

Total FFP utilizing the BEQ provided: $______________

This is a Not to Exceed (NTE) CLIN. Funding for this line item will be determined by the government at the time of award.

CONTRACTOR IS SAM REGISTERED.

REGISTRATION IS VALID UNTIL:

CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)

SEE CLAUSE 252.232-7006

FOB: Destination

NSN: J099-SM-SER-VICE

ESTIMATED COST

CLIN 2001

The CLIN extended description has changed from The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS). Period of Performance: 1 Dec 15 thru 30 Nov 16BEQ Testing Unit Price8 Bond Strength Testing $_______ 24 Single Layer Aerospace Coating Analysis $_______16 Dual Layer Aerospace Coating Analysis $_______8 Single Layer Aerospace Coating Analysis (include micro-hardness) $_____ 4 Dual Layer Aerospace Coating Analysis (includes micro-hardness) $_______4 Rockwell Hardness Testing $_______This is a Firm Fixed Price (FFP) Unit Price Line Item.Total FFP utilzing the BEQ provided: $______________CONTRACTOR IS SAM REGISTERED.REGISTRATION IS VALID UNTIL:CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)SEE CLAUSE 252.232-7006 to The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS). Period of Performance: 3 Jan 16 - 2 Jan 17This is a Firm Fixed Price (FFP) per Unit Line Item.Annual Best Estimated Quantity (BEQ) Testing Unit Price8 Bond Strength Testing $_______ 24 Single Layer Aerospace Coating Analysis $_______16 Dual Layer Aerospace Coating Analysis $_______8 Single Layer Aerospace Coating Analysis (include micro-hardness) $_______ 4 Dual Layer Aerospace Coating Analysis (includes micro-hardness) $_______4 Rockwell Hardness Testing $_______Total FFP utilizing the BEQ provided: $______________This is a Not to Exceed (NTE) CLIN. Funding for this line item will be determined by the government at the time of award.CONTRACTOR IS SAM REGISTERED.REGISTRATION IS VALID UNTIL:CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)SEE CLAUSE 252.232-7006.

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Lot

OPTION
THERMAL SPRAY COATING EVALUATIONS

COST

The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS).

Period of Performance: 3 Jan 16 - 2 Jan 17

This is a Firm Fixed Price (FFP) per Unit Line Item.

Annual Best Estimated Quantity (BEQ) Testing

Total FFP utilizing the BEQ provided: $______________

This is a Not to Exceed (NTE) CLIN. Funding for this line item will be determined by the government at the time of award.

CONTRACTOR IS SAM REGISTERED.

REGISTRATION IS VALID UNTIL:

CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)

SEE CLAUSE 252.232-7006

FOB: Destination

ESTIMATED COST

CLIN 3001

The CLIN extended description has changed from The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS). Period of Performance: 1 Dec16 thru 30 Nov 17BEQ Testing Unit Price8 Bond Strength Testing $_______ 24 Single Layer Aerospace Coating Analysis $_______16 Dual Layer Aerospace Coating Analysis $_______8 Single Layer Aerospace Coating Analysis (include micro-hardness) $_____ 4 Dual Layer Aerospace Coating Analysis (includes micro-hardness) $_______4 Rockwell Hardness Testing $_______This is a Firm Fixed Price (FFP) Unit Price Line Item.Total FFP utilzing the BEQ provided: $______________CONTRACTOR IS SAM REGISTERED.REGISTRATION IS VALID UNTIL:CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)SEE CLAUSE 252.232-7006 to The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS). Period of Performance: 3 Jan 17 - 2 Jan 18This is a Firm Fixed Price (FFP) per Unit Line Item.Annual Best Estimated Quantity (BEQ) Testing Unit Price8 Bond Strength Testing $_______ 24 Single Layer Aerospace Coating Analysis $_______16 Dual Layer Aerospace Coating Analysis $_______8 Single Layer Aerospace Coating Analysis (include micro-hardness) $_______ 4 Dual Layer Aerospace Coating Analysis (includes micro-hardness) $_______4 Rockwell Hardness Testing $_______Total FFP utilizing the BEQ provided: $______________This is a Not to Exceed (NTE) CLIN. Funding for this line item will be determined by the government at the time of award.CONTRACTOR IS SAM REGISTERED.REGISTRATION IS VALID UNTIL:CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)SEE CLAUSE 252.232-7006.

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Lot

OPTION
THERMAL SPRAY COATING EVALUATIONS

COST

The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS).

Period of Performance: 3 Jan 17 - 2 Jan 18

This is a Firm Fixed Price (FFP) per Unit Line Item.

Annual Best Estimated Quantity (BEQ) Testing

Total FFP utilizing the BEQ provided: $______________

This is a Not to Exceed (NTE) CLIN. Funding for this line item will be determined by the government at the time of award.

CONTRACTOR IS SAM REGISTERED.

REGISTRATION IS VALID UNTIL:

CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)

SEE CLAUSE 252.232-7006

FOB: Destination

ESTIMATED COST

CLIN 4001

The CLIN extended description has changed from The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS). Period of Performance: 1 Dec17 thru 30 Nov 18BEQ Testing Unit Price8 Bond Strength Testing $_______ 24 Single Layer Aerospace Coating Analysis $_______16 Dual Layer Aerospace Coating Analysis $_______8 Single Layer Aerospace Coating Analysis (include micro-hardness) $_____ 4 Dual Layer Aerospace Coating Analysis (includes micro-hardness) $_______4 Rockwell Hardness Testing $_______This is a Firm Fixed Price (FFP) Unit Price Line Item.Total FFP utilzing the BEQ provided: $_____________CONTRACTOR IS SAM REGISTERED.REGISTRATION IS VALID UNTIL:CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)SEE CLAUSE 252.232-7006 to The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS). Period of Performance: 3 Jan 18 - 2 Jan 19This is a Firm Fixed Price (FFP) per Unit Line Item.Annual Best Estimated Quantity (BEQ) Testing Unit Price8 Bond Strength Testing $_______ 24 Single Layer Aerospace Coating Analysis $_______16 Dual Layer Aerospace Coating Analysis $_______8 Single Layer Aerospace Coating Analysis (include micro-hardness) $_______ 4 Dual Layer Aerospace Coating Analysis (includes micro-hardness) $_______4 Rockwell Hardness Testing $_______Total FFP utilizing the BEQ provided: $______________This is a Not to Exceed (NTE) CLIN. Funding for this line item will be determined by the government at the time of award.CONTRACTOR IS SAM REGISTERED.REGISTRATION IS VALID UNTIL:CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)SEE CLAUSE 252.232-7006.

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Lot

OPTION
THERMAL SPRAY COATING EVALUATIONS

COST

The Contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and personal protective equipment necessary to evaluate thermal spray coatings at the Contractor's site. The Contractor shall be responsible for ensuring that all of the services provided under this contract are in accordance with the terms and conditions outlined herein and this Performance Work Statement (PWS).

Period of Performance: 3 Jan 18 - 2 Jan 19

This is a Firm Fixed Price (FFP) per Unit Line Item.

Annual Best Estimated Quantity (BEQ) Testing

Total FFP utilizing the BEQ provided: $______________

This is a Not to Exceed (NTE) CLIN. Funding for this line item will be determined by the government at the time of award.

CONTRACTOR IS SAM REGISTERED.

REGISTRATION IS VALID UNTIL:

CONTRACTOR SHALL SUBMIT INVOICES IN ARREARS OF SERVICES THROUGH WIDE AREA WORK FLOW (WAWF)

SEE CLAUSE 252.232-7006

FOB: Destination

ESTIMATED COST

DELIVERIES AND PERFORMANCE

The following Delivery Schedule item for CLIN 0001 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC

POP 01-DEC-2013 TO

30-NOV-2014

N/A
F3YCEB

KELLI MUNTZ

76 MXW/OBWK

3001 STAFF DR STE S69

TINKER AFB OK 73145

405-736-7540

FOB: Destination

F3YCEB

To:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC

POP 03-JAN-2014 TO

02-JAN-2015

N/A
N/A

The following Delivery Schedule item for CLIN 1001 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC

POP 01-DEC-2014 TO

30-NOV-2015

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC

POP 01-DEC-2015 TO

30-NOV-2016

N/A
N/A

The following Delivery Schedule item for CLIN 2001 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC

POP 01-DEC-2015 TO

30-NOV-2016

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC

POP 01-DEC-2016 TO

30-NOV-2017

N/A
N/A

The following Delivery Schedule item for CLIN 3001 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC

POP 01-DEC-2016 TO

30-NOV-2017

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC

POP 01-DEC-2017 TO

30-NOV-2018

N/A
N/A

The following Delivery Schedule item for CLIN 4001 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC

POP 01-DEC-2017 TO

30-NOV-2018

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC

POP 01-DEC-2018 TO

30-NOV-2019

N/A
N/A

The following have been modified:

NOTES

CONTRACT HOLIDAYS

(a) The prices/costs in Section B of the contract holiday observances; accordingly, the Government will not be billed for such holidays, except when services are required by the Government and are actually performed on a holiday. Holidays in addition to those reflected in this contract, which are designated by the Government, will be billable provided the assigned Contractor employee was available for performance and was precluded from such performance.

(b) The following days are contract holidays: New Years Day, Martin Luther King, Jr. Day, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day and Furlough Days.

TRUCK ENTRY GATE” NOTICE

IMPORTANT DELIVERY INFORMATION

Tinker Air Force Base has constructed a “Truck Entry Gate” (Gate 33), which is located at the corner of 59th Street and Air Depot Blvd (southwest corner of the base). The gate will be opened beginning 15 September 2004.

Gate 33 shall be used for all deliveries by truck to this base.

(Trucks will not be allowed to gain access through any other gate.)

Since your firm’s delivery on this order is affected, please advise your delivery carrier to use the new gate. This should minimize the impact of your delivery.

DELIVERIES TO BUILDING 3001 (B / 3001)

Be advised that delivery vehicles destined for B / 3001 are prohibited from using “Staff Drive”.

Delivery vehicles may make deliveries only in designated unloading areas.

Since your firm’s delivery may be affected, ensure that your delivery carrier receives proper instructions on delivery / unloading requirements for B / 3001. Unloading in designated unloading areas will minimize any inconvenience, and, attendant ramifications, which may accrue, to your delivery / delivery carrier for failure to adhere to this requirement.

LIST OF ATTACHMENTS

FORM NR

DESCRIPTION

DATE

NR OF PAGES

Performance Work Statement

26 Nov 13

Appendix B

28 Mar 13

Appendix C

22 Nov 11

Wage Determination 2005-2432

19 Jun 13

(End of Summary of Changes)

The following items are applicable to this modification:

AMENDMENT SUMMARY

FIRST: A revised Performance Work Statement (PWS) dated 26 Nov 13 hereby supersedes the previous PWS dated 27 Aug 13 in Solicitation FA8125-13-Q-0057. The title of Table 1 was changed. Paragraph 1.2. Services was modified. Paragraph 1.2.1. Additional Testing was added.

SECOND: The proposal submission date indicated on page 1 of FA8125-13-Q-0057 is hereby changed

From: 17 Oct 13

To: 9 Dec 13 THIRD: The following changes were made to CLIN’s 0001, 1001, 2001, 3001, 4001:

Changed: Period of Performance from 1 Dec XX – 30 Nov XX TO 3 Jan XX – 2 Jan XX

Added: This is a Firm Fixed Price (FFP) per Unit Line Item

Changed: BEQ Testing TO Annual Best Estimated Quantity (BEQ) Testing

Added: This is a Not to Exceed (NTE) CLIN.

Added: Funding for this line item will be determined by the government at the time of award.

FOURTH: All terms and conditions remain unchanged and in full effect.

File details come from the government source that posted it. Updated .