APPENDIX_C_Thermal_Spray_Coating_Evaluation_PMXG.docx
DOCX document 32 KB Posted
- Attached to
- Thermal Spray Coating Evaluation - Annual Federal contract opportunity
- Solicitation number
- FA8125-13-Q-0057
About this file
Appendix C
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA8125-13-Q-0057-0003.doc | DOC document | |
| 26Nov13(2)PWS_Thermal_Spray.docx | DOCX document | |
| FA8125-13-Q-0057-0002.doc | DOC document | |
| FA8125-13-Q-0057-0001.doc | DOC document | |
| Thermal_Solicitation.doc | DOC document | |
| 2013_Wage_Determination.docx | DOCX document | |
| 27Aug13PWS_Thermal_Spray.docx | DOCX document | |
| Appendix_B_Scheduled_GFP_Thermal_Spray_Coating_Evaluation_PMXG.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
05 April 2013
APPENDIX C
FOR
THERMAL SPRAY COATING EVALUATIONS FOR 76 PMXG
PRE FILE NO: OC-ALC/SEG 13-236
PREPARED BY: OC-ALC/SEG
SECTION I - GENERAL REQUIREMENTS
A. Safety Program Requirements. The contractor will implement a safety program that ensures protection of Government personnel and property. The program will consist of, as a minimum:
1. Mishap notification/reporting as defined in paragraph B. below.
2. A Safety Program that addresses, as a minimum, the subjects listed in Safety Program Elements, Section II and to be used during performance of the work described in the contract.
B. Mishap Notification.
1. The contractor shall notify the procuring Safety Office or a designated Government Representative (GR) within one (1) hour of all mishaps or incidents. A written report of the mishap/incident shall be sent within three calendar days to the GR, who will forward it to the Procuring Safety Office. For information not available at the time of initial written report, the contractor shall provide the remaining information no later than 20 calendar days after the mishap, unless extended by the Safety Office.
2. Mishap notifications shall contain, as a minimum, the following information:
| a. | Contract, Contract Number, Name and Title of Person(s) Reporting |
| b. | Date, Time and exact location of accident/incident |
| c. | Brief Narrative of accident/incident (Events leading to accident/incident) |
| d. | Cause of accident/incident, if known |
| e. | Estimated cost of accident/incident (material and labor to repair/replace) |
| f. | Nomenclature of equipment and personnel involved in accident/incident |
| g. | Corrective actions (taken or proposed) |
| h. | Other pertinent information |
3. If requested by the designated government representative, the contractor shall immediately secure the mishap scene/damaged property and impound pertinent maintenance and training records, until released by the Procuring Safety Office.
C. The safety provisions of this contract, shall apply to any subcontracts/subcontractors.
1. Safety requirements listed herein that do not concern contractor’s operations or services shall be considered self-deleting as mutually agreed by the contractor and the procuring office.
SECTION II - SAFETY PROGRAM ELEMENTS
The contractor’s Safety Program shall clearly define procedures, personnel qualifications, facilities and required equipment necessary to fulfill the following elements:
Element/Requirement Referenced Benchmark
OSHA Standards for General Industry 29 CFR 1910
SECTION III - BIBLIOGRAPHY OF PUBLICATIONS/DIRECTIVES
These publications/directives and all supplements/changes thereto apply to the extent required by the provisions of Sections I, and II.
AFI 91-204 Sep 08 Safety Investigations and Reports
29 CFR 1910 OSHA Standards for General Industry
File details come from the government source that posted it. Updated .