SOW_Amend 3.pdf
PDF 15 MB Posted
- Solicitation number
- FA8051-25-R-2002
About this file
This is a Statement of Work (SOW) for an Advanced Meter Reading System (AMRS) Metering Implementation project at FE Warren Air Force Base in Wyoming. The solicitation (FA8051-25-R-2002) is a 100% set-aside for SBA Certified Women-Owned Small Business (WOSB) Program, with the Department of the Air Force Materiel Command Installation and Mission Support Center as the contracting agency.
The project requires the installation of 55 new AMRS-compliant electric meters and associated communication infrastructure across multiple base facilities. Key requirements include installing communication outlets, patch panels, fiber optic connections, and conducting comprehensive commissioning and testing. The contractor must provide detailed work plans, design documentation, and comply with specific technical specifications for meter installation, network connectivity, and cybersecurity standards. The project has a 365-calendar day period of performance, with critical milestones including work plan submissions, pre-construction meetings, 25% and 100% meter commissioning, and final as-built documentation. Proposal responses were originally due by 17 July 2025, but have been extended to 4 August 2025 through multiple amendments.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA8051-25-R-2002 - Amend4 FE Warren AFB 29 July25.pdf | ||
| Atch 1 - FE Warren SOW with Appendices 18 July 2025.pdf | ||
| Atch 9 - Additional QA Response 29 July 2025.xlsx | XLSX spreadsheet | |
| Q and A_Amend 3.xlsx | XLSX spreadsheet | |
| FOPR Amend 3.pdf | ||
| FA8051-25-R-2002 - Amend2 FE Warren AFB 15 July 2025.pdf | ||
| FA8051-25-R-2002 - Amend1 FE Warren AFB 10 July 2025.pdf | ||
| Atch 7 - FE Warren Sign In Sheet.pdf | ||
| Atch 1 - FE Warren SOW with Appendices 13 May 2025.pdf | ||
| Atch 4 - Provisions and Clauses.pdf | ||
| FA8051-25-R-2002 - FE Warren AFB 17 June 2025.pdf | ||
| Atch 5 - QA Sheet.xlsx | XLSX spreadsheet | |
| Atch 6 - EAL Template.xlsx | XLSX spreadsheet | |
| Exhibit 1 - CDRLs.pdf | ||
| Atch 2 - Wage Determination 2 June 2025.pdf | ||
| Atch 3 - Price Proposal Summary Sheet.xlsx | XLSX spreadsheet |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 1 3
FA805125R2002, FE Warren AFB Attachment 1
STATEMENT OF WORK (SOW)
Design-Build (D-B) Construction
AFCEC Advanced Meter Reading System (AMRS) Metering Implementation Project Location: FE Warren AFB, WY
Base Work Order Number> TBD
AFCEC Project Number> TBD
Contract Number> TBD
1 8 July 2025
1 . 0 Introduction
1 . 1 The work to be conducted under this requirement shall be done under the general conditions of the Contract and the Basic SOW contained therein. This contract shall be accomplished using the Design - Build (D-B) delivery method. The project objective is the remote data acquisition of all meter data from a centralized computer front end system utilizing the Modbus/TCP communications protocol over an ethernet network. The intent of the project is to bring all designated existing and proposed meters into compliance with Energy Policy Act of 2005 , EISA 2007, and the Meter Data Management Plan (MDMP). Compliant meters are defined in accordance with Appendix 3 - AMRS Meter Specifications.
1 . 2 The project involves specialized experience in both standard construction as well as communication systems / facility control systems. Equal expertise in both areas is needed to effectively execute this project. This applies to all aspects of this project from design, construction, submittals, commissioning and closeout. Vendors shall show in their proposal experience and expertise in both areas. Acceptance of final products will also require expertise in both areas.
1 . 3 The Air Force Advanced Meter Reading System (AMRS) Project Management Office (PMO) at Tyndall AFB, Florida is lead for all aspects of this project outside of requirements dictated by the Contracting Officer (CO). At all times any conflict or communication will flow through the points of contact provided in the AMRS PMO. The AMRS PMO is under the Air Force Civil Engineer Center (AFCEC) and the designated system owners for the Air Forces AMRS.
2.0 Scope of Work
2.1 Scope & Applicable Documents
This SOW sets forth the requirements for a D-B construction effort at FE Warren AFB, WY. The contractor shall manage and perform D-B construction work as defined in the contract. The contractor is the Designer of Record (DOR) as well as the Constructor of Record for D-B projects. As the DOR the contractor accepts specific responsibilities as described in Appendix 8 of the basic contract SOW. The Contractor is to provide the government with a Work Breakdown S tructure (WBS) (A006), Construction Work Plan (CWP) (A007 and A008 ), construction, and warranty for the Advanced Meter Reading System (AMRS) to meet the existing design and current Air Force (AF) S tandards. The Contractor shall prepare the WBS and CWP for the implementation of an AMRS that incorporates meters, meter reading systems, and data management capabilities at FE Warren AFB, WY in accordance with the Department of Energy (DOE), Federal Energy Management Program (FEMP) Guidance for Electric Metering in Federal Buildings, dated November 201 4.
2.1 . 1 Period of Performance
The Period of Performance (PoP) for this D-B construction effort is 365 calendar days.
2.2 Description of Work
As part of the proposed effort on this contract, the Contractor shall implement the following tasks for the completion of this project. This project shall be accomplished IAW the SOW Appendices 1 through 8 and CDRLs.
2. 2. 1 Work Plan Phase
The Contractor shall complete development of a WBS (A006) and CWP (A007) IAW defined levels of effort necessary to construct the project as detailed in Appendix 1 . The contractor shall be responsible for verifying voltages, amperes, CT ratios, physical space limitations, routing of lines, etc. , prior to ordering any items required for this project.
1 8 Ju ty 2025
Page 2 of 1 3
2. 2. 1 . 1 Hazardous Material Surveys
The contractor shall avoid disturbing all known and suspected hazardous materials in the post award base provided report.
2. 2. 2 Construction Phase
Upon CO approval, and after the final CWP approval, the contractor shall commence on-site construction activities. The CO will transmit the notice to proceed (NTP) to verify and formalize the start of construction activities. The contractor will coordinate an onsite pre-construction kick off meeting in which all stakeholders will be invited to attend and will set up a Microsoft Teams virtual meeting for other attendees that cannot make an in person meeting. The contractor shall complete the work as described below.
2. 2. 2. 1 On-Site Field Oversight The contractor shall provide the manpower, equipment, material, services, and transportation necessary to ensure oversight services throughout accomplishment of this contract. The contractor shall establish and maintain open communications between salient authorities associated with accomplishment of this contract.
2. 2. 2. 2 Temporary Utility Connections
The Contractor shall make all temporary connections and install distribution lines using best management practices and industry standards including but not limited to the temporary office space and/or laydown area, if permitted by the base.
2. 2. 2. 3 Delivery/Warranty
The Contractor shall complete all inspection and commissioning requirements prior to final commissioning. See Appendix 5 - AMRS Commissioning Plan & Test Procedure. Following final commissioning, the Contractor shall deliver to the Government signed and sealed as-built drawings (AutoCAD, and PDF) (A01 2) in both hard copy and reproducible format as well as O&M manuals for all installed devices. The warranty period shall begin as per Appendix 8 close out criteria. The Government Furnished Equipment (GFE) meters (i. e. , meters already installed in switchgear) shall have a warranty on workmanship and any new material purchased (i. e. , Ethernet card). The warranty shall be issued IAW FAR 52. 246-21 .
3 . 0 General Requirements
3 . 1 Qualified Personnel
The contractor shall ensure that only qualified, competent personnel carry out the tasks outlined in this SOW. Competent is defined as registered professional or, where registration is not applicable, trained, and/or certified in their respective field.
Contractor shall provide a minimum of one (1 ) Building Industry Consulting Service International (BICSI) Certified Technician(s), with a minimum of two (2) years' experience, to install, terminate, and test all communications infrastructure from the end device to the communication network patch panel. Only BICSI certified technicians shall install communication cabling and/or network infrastructure. Contractor shall provide a minimum of one (1 ) Licensed Professional Engineer (PE) with a minimum of ten (1 0) years' experience with advance meters in the appropriate mechanical, electrical, and plumbing disciplines. (1 ) Primary and (1 ) alternate S ite Superintendent that is a U. S . citizen. All contractors shall be US Citizens and able to speak English language fluently. S ite Superintendent will be required to obtain a base pass with escort and flight line privileges and be on site at all times when construction activities occur.
3 . 2 Air Force Property All materials gathered and/or developed in the performance of these tasks listed shall be returned to and become property of the AF; and shall not be used and/or distributed by the contractor without specific written permission of the Contracting Officer' s Representative (COR).
3 . 3 Verification and Validation of Existing Conditions The contractor shall be responsible for verification and validation of existing conditions and data, coordination of existing conditions in parallel with proposed requirements, and above and below-grade condition assessment IAW FAR 52. 236-3 -- site investigation and conditions affecting the work.
3 . 4 Work Plan and Construction Requirements
1 8 Ju ly 2025
Page 3 of 1 3
The project shall conform to all applicable Federal, S tate, and local laws, regulations and base-specific standards, and applicable Unified Facilities Criteria (UFC). Where there is a conflict between the referenced standards, the most stringent shall take precedence. All work accomplished by the contractor shall comply with these criteria unless a waiver is obtained from the AF when conditions warrant such consideration.
4.0 Government Furnished Material (GFM)
The Contractor upon request may be provided with documents, drawings, and general reference material. However, these requests must be submitted directly to CO and the COR and may be refused if deemed unavailable, unnecessary, security sensitive, or outside the scope of work. The following list is not intended to be all inclusive, but suggested examples@
A. Installation map.
B. Utility Maps showing key utility systems (electric, natural gas, steam, water, wastewater, industrial wastewater, compressed air, others as needed).
C. Installation specific information@ hazardous material reports, construction guides, device security guides, and
Internet Protocol (IP) network addresses.
All GFM utilized during any part of the performance of this project must be returned to the COR upon completion of this contract, unless expended as part of the project.
The following is a list of specific items of support that the base CE will provide@
4.1 Work Clearance Request (AF Form 1 03 )
The COR will assist the contractor with efforts to fully complete the Base Civil Engineering Work Clearance Request (AF Form 1 03 ). The base CE will locate underground utilities and issue the AF Form 1 03 to the contractor. The contractor shall have a completed and approved Form 1 03 prior to beginning any construction activities including clearing, grubbing, exploratory geophysical work, etc. Process these requests early to allow sufficient base coordination time for prudent planning and scheduling. Contractor shall coordinate with the base customer service. CE POC, and facility users for requested power outages, a minimum of twenty-one (21 ) calendar days in advance of the needed outage.
4.1 . 1 Base Work Clearance Request Specifics The Contractor shall obtain, coordinate, and process an AF Form 1 03 Work Clearance Request. The Contractor shall initiate the Form 1 03 at the Customer Service Desk. The Contractor shall coordinate with the appropriate base organizations to properly complete the form and get it approved. The contractor shall provide one copy of the AF Form 1 03 to the COR prior to commencement of any work for the project. The Contractor shall attach drawings to the Form 1 03 showing exact location and description of the work to be accomplished.
Escorts required to access communication rooms must be coordinated a minimum of fourteen (1 4) calendar days in advance.
Facility reserves the right to request personal documentation for contractors being escorted. Base COR can assist in discovery.
4.1 . 2 Base Dig Permits Any work involving disturbance of earth deeper than six (6) inches below current grade will require a Dig permit. The Dig permit shall be submitted at least twenty-one (21 ) calendar days prior to digging. The Contractor shall resubmit the Dig Permit every thirty (3 0) days to ensure all agencies remain aware of the ongoing work.
4.1 . 3 Base Utility Outages
The Contractor shall obtain and process a Utility Outage Form for each utility outage. The format for this form is base specific and be secured by the Contractor during the kickoff meeting. The Contractor shall initiate and coordinate signatures/approvals of the form with the Customer Service Desk or designated processing entity. Prior to submission, it is highly advised that the contractor coordinate with the individual facilities as to acceptable utility outage durations and dates. The base may or may not be able to accommodate the contractorJ s schedule without prior coordination with each facility and the base electric shop. The contractor shall submit the completed form a minimum of fourteen (1 4) calendar days prior to the requested outage date for non-mission critical facilities and a minimum of sixty (60) days for mission critical (MC) facilities. The plan must also include procedures for promptly repairing utility breaks/interruptions made or caused by the Contractor.
The fourteen (1 4) calendar day minimum is for low importance (non-mission critical) facilities. For higher visibility and mission critical buildings, sixty (60) calendar day minimum notice will be required. Note that many of the mission critical facilities declare that real world security issues may cause last minute electric outage cancellations. Alternative work plan should be available as to not to delay progress if a last-minute power outage has to be cancelled. Power outage coordination should commence immediately upon Notice to Proceed (NTP) issued by the CO.
Page 4 of . 3
4. . . 3 . . Utility Markings
The Contractor shall contact utility owners to coordinate work and to identify, locate, and mark all utility lines in the vicinity of the project work site, including utility lines not owned by the base, prior to digging. The Contractor shall mark the limits of site work/excavation to indicate location, direction, length, and depth of site work/excavation in order to facilitate the utility owner4 s field marking of existing utilities. The Contractor shall maintain all utility markings for the duration of the project. The Contractor verifies the exact location of all known utility lines and structures within the affected area of the contract and for the protection of the same. Should damage occur to any utility line or structure, the Contractor shall provide prompt repair of the damage to return the item to its original working condition, to the satisfaction of the CO. The Contractor shall consult with the COR before any markings are placed in high-visibility areas, as designated by the Contract. In all high- visibility locations, the paint used to locate utilities shall be fully removed from site elements such as sidewalks, pavements, and plazas at the end of the project. Removal of the paint shall not result in damage to the site element. The use of other forms of marking, such as tape, may be used upon approval by the CO. Customer Service will provide a street address from Real Property records.
4.2 Material S torage
There is no designated Contractor S torage/Laydown provided at FE Warren. The Contractor is encouraged to use the TO job site for staging materials. The Contractor is advised that an off-base storage/staging area may be useful. The Contractor shall provide security for all materials and equipment. The Government has no liability for lost or stolen equipment and/or materials.
The COR will identify space on the jobsite or in a base contractor staging area where the contractor may deliver non-hazardous materials within the installation. Prior notification by the contractor is required.
4.3 Existing Engineering Plans, Etc.
The COR will provide the contractor with access to existing engineering plans, drawings, diagrams, aerial photographs, digitized map files, etc. , if available, to facilitate evaluation of the site(s), as needed or requested.
4.4 Kick-Off Meeting
The contractor shall host a kick-off meeting at the base to advise and coordinate on local procedures, safety and security requirements, and project coordination activities. The contractor and their team shall have in their possession for the kickoff meetingF a base map, the current SOW, and the facility manager list to coordinate access. The COR or base CE POC will arrange for a suitable kick-off meeting location with teleconferencing capabilities to ensure Contracting Officer (CO) and Air Force AMRS PMO participation via telecom. The COR or base CE POC will ensure the appropriate base agencies attend the kick-off meeting to provide necessary information or briefings to facilitate the success of the contract effort. At the project kick-off meeting the contractor shall provide to the AF a listing of project team members and contact information. The contractor shall also present a project schedule for discussion and finalization. At a minimum, the project schedule shall include milestones for completing the WBS (A006), CWP (A007, A008 ), construction, commissioning, and project closeout.
The contractor shall coordinate and perform a task meeting with site survey at the base to perform all due diligence required for the drafting of the WBS and CWP. The Kick-Off meeting will include the physical survey of all components of the SOW. The contractor shall schedule and attend an adequate number of days to accomplish all due diligence for this project. Additional time spent by the contractor post site survey, will be at the cost of the contractor and the leisure of the base. At the conclusion of the contractor site survey, an out brief will be hosted on site, by the contractor to discuss any information that was not able to be obtained during the site survey. The contractor shall prepare and distribute meeting minutes (A004) within five (5 ) days of the kick-off meeting.
4.5 Base Requirements
The COR will advise the contractor of the location and processes to obtain the following as neededF
a. Personnel identification badges, vehicle passes, and/or entry permits.
b. Information on base fire prevention/security practices and procedures.
c. Access to utilities (electrical, water, sewer, communications, etc. ) This includes a supply (e. g. , fire hydrant or standpipe) of large quantities of potable water.
d. Security escorts for work in restricted areas, if provided by the base.
e. Safety training classes for the purpose of allowing access within secure or hazardous areas.
Page 5 of 1 3
f. A paved area where equtpment can be cleaned.
g. A set of keys to locks as necessary and as the tndtvtdual tnstallatton, s access poltcy wtll allow. If keys are not permtsstble to be stgned out by the contractorl the COR shall nottfy the contractor as to the proper process for requesttng access.
h. A factltty manager ltst for those factltttes tn scope.
4.6 Contracttng Offtcer, s Representattve (COR)
The base CE wtll provtde a COR who wtll expedtttously revtew and certtfy the contractor, s progress by stgntng AF form(s) 3 064 and 3065 and monthly status reports for the contractor. (Note= tf the COR does not agree that the progress ts as represented by the contractorl he/she shall return the documents to the contractor for correctton. )
5.0 DELIVERABLES
Project deltverables shall be as shown tn the table below. A descrtptton of each deltverable follows.
TABLE OF DELIVERABLES
Document Tttle
Coptes Per Addressee
Deltvery Date
AF
CE
C
PM
Ba se
P
OC
CE
CO
El ec tro nt c Ha rd C op y
El ec tro nt c Ha rd C op y
El ec tro nt c
Ha rd
C op y
S tte Project Summary (SPS)
Qualtty System Plan (QSP)
Health and Safety Plan (HSP)
(A001 l A002l A003 )
1 4 calendar days after award (21 pg.
max per submtttal)
Ktck-off Meettng
21 calendar days after awardl on stte
Progress Meettngs Once a week after CWP submtttall teleconference
Meettng Mtnutes (A004) 1 0 1 0 1 0 2 calendar days after each meettng
Progress Schedule (AF 3064 or approved equtvalent)
21 calendar days after award or at the Ktck-off Meettngl whtchever ts later.
Updated form shall be submttted the 1 4 days after the end of the pertodl monthly
(21 pg. max per submtttal)
Progress Report (AF 3065 or approved equtvalent) 1 0 1 0 1 0 1 4 days after the end of the pertodl monthly
Page 6 of 1 3
TABLE OF DELIVERABLES
Document Title
Copies Per Addressee
Delivery Date
CE
tro ni c Ha rd C op y
El ec tro ni c Ha rd C op y
El ec tro ni c
Ha rd
C op y
(21 pg. max per submittal)
Monthly S tatus Report (MSR)
(A005 )
1 4 days after the end of the period, monthly
(21 pg. max per submittal)
Work Breakdown S tructure (WBS)
(A006)
0 45 days after Kick-off Meeting or sooner
WBS Review Conference 1 4 calendar days, or sooner, after
WBS Submittal via teleconference
The Government will provide review comments within 1 4 calendar days of WBS Submittal
Draft CWP - (Draft CWP)
(A007)
0 1 4 calendar days, or sooner, after
WBS Approval
Draft CWP Review Conference
1 4 calendar days, or sooner, after CWP Submittal
The Government will provide final comments within 1 4 calendar days of Draft CWP Submittal
Final CWP - (Final CWP)
(A008 )
1 4 calendar days, or sooner, after receipt of Government review comments
Pre-Construction Meeting On site 1 4 calendar days, or sooner, after NTP issued
Production or Delivery Problem Report 1 0 1 0 1 0 Same day of issue or occurrence
Weekly Logs including installation photographs (AF Form 1 477 or approved equivalent)
(A009)
Submitted weekly showing daily progress. Shall include photos ofN CT install, phasor display, voltage & amperage reading for each phase, interior wiring of meter enclosure to include CT shorting block
Meter ID and IP Request
(A01 0)
Prior to Notice to Proceed
Page 7 of 1 3
TABLE OF DEL NERABLES
Document Title
Copies Per Addressee
Delivery Date
CE
tro ni c Ha rd C op y
El ec tro ni c Ha rd C op y
El ec tro ni c
Ha rd
C op y
Meter Pre Commissioning 25 %
Meter Final Commissioning 1 00%
(A01 1 )
1. 25 % of meters have been installed? configured? security settings applied? patch cable from patch panel to switch installed by CS? screen shots/cable tests completed? and port configured by CS. Contractor to coordinate all above items
2. 1 00% of meters as noted above
Transfer & Acceptance of Military Real Property (DD 1 3 54) and start of warranty period letter
Within 7 calendar days after Final Commissioning
As-Built Drawing? * signed and sealed ( AutoCAD? and PDF) / O&M Manuals
(A01 2)
With Final Commissioning Report
5.1 Management? Planning and Reporting Requirements
The S ite/Project Summary (A003 ) shall be as described in the basic SOW. The contractor shall prepare and submit a Contractor Quality System Plan (A002) and Health and Safety Plan (A001 ). No construction activities will begin until the CO approves all plans.
5.2 Contract Progress Schedule (AF 3064)
The contractor shall submit a signed AF 3064 (or approved equivalent)? contract progress schedule? depicting an overall contract progress schedule for the main elements of work for the period of performance (PoP) as described in the table of deliverables above as part of the WBS (A006) and updated in MSR (005 ). The contractor shall provide a line graph depicting actual construction progress (solid line) versus scheduled construction progress (dotted line) throughout the PoP. The COR will sign the AF 3064 and send to the CO for approval. The contractor shall propose a timeline for government approval in regard to the PoP for the contract? including WBS/CWP delivery and construction work upon coordination with Base Comm POC and Base Energy Manager (BEM). Construction work shall begin as each submittal for the phases of work are approved.
ContractorN s progress schedule shall identify the major elements of work and the PoP for each element? including the WBS/CWP submission. The WBS/CWP schedule shall allow the government approximately fourteen (1 4) calendar days for review and approval. See Appendix 4 - Flow Chart/Work Flow Milestones
5.3 Contract Progress Report (AF 3065 )
Page 8 of 1 3
The contractor shall submit AF 3065 as described in the table of deliverables above initially in the WBS (A006) and updated in MSR (005 ). This report shall be signed by the contractor' s on-site representative in the remarks section of the AF 3 065 . The work elements and percentages of the total job identified on the AF 3 065 shall be identical to the work elements and percentages on the AF 3064. The Contractor shall evenly disperse general conditions including overhead and profit to each of the work elements scheduled over the duration of the project. General conditions can include many different cost categories.
Some typical general conditions are contractor labor, document reproduction, telephone, various supplies, shipping, equipment/vehicle rental, travel, vehicle operating costs, on-site office trailer rent, dumpsters, etc. The total value of the work elements in the schedule of values@ including costs for material and equipment delivered for installation on the project, and labor and construction equipment loaded construction activities, shall total to one-hundred percent (1 00%) of the value of the contract. All progress payment amounts will be derived from and tied to the work elements listed in the schedule of values and demonstrated performance of those elements.
If the contractor is more than five percent (5 %) behind schedule, the contractor shall note in the remarks section the reason why and what is being done to get back on schedule. The COR will sign the AF 3065 and send for coordination and approval by the CO. If the contractor requires reimbursement of a high dollar value item, the item shall be identified on the AF 3065 , an appropriate percentage applied, and the item must be received and stored on site.
Each invoice shall be accompanied by an AF 3064 and AF 3 065 which are signed by the COR or the government inspector.
The AF 3064, AF 3065 , and invoice shall all cover the same period it was submitted for.
5.4 Monthly S tatus Report (MSR)
The MSRs (A005 ) shall communicate activities accomplished during the previous period, document discussions, identification of problems, proposed solutions, corrective actions taken, outstanding issues, and record issues or concerns. The MSR shall include a financial tracking table containing columns with the following headingsE A. Task breakout B. Current project status (summary of work completed during this month and to be completed during the upcoming reporting period using milestones in the submitted IMS).
C. Task value D. Effort % complete E. Dollars % expensed to date F. Dollars earned this month G. Dollars earned to date H. Expected work activities for the following month and any significant anticipated risk to project schedule, the Contractors mitigation procedures and potential impact against IMS.
I. Problems and/or concerns with background and recommendations for potential solutions including those outside of the current contract.
J. RFI' s and statuses K. Updated submittal register L. Safety issues of concern over the past month M. Links to a site and catalog containing the photographic log as submitted during the previous period operations.
A narrative from the contractor shall include Each invoice shall be accompanied by an AF 3064, AF 3 065 and a MSR. The AF 3064, AF 3065 , MSR and invoice shall all cover the same period it was submitted for.
5.5 Pre-Construction Meeting
It is the responsibility of the contractor to coordinate the date and time of the Pre-Construction meeting. The meeting will be contingent on base and AFCEC availability, and scheduled by the contractor fourteen (1 4) calendar days or sooner, after issuance of the NTP. The contractor shall be responsible for establishing the agenda in coordination with AFCEC and COR and providing agenda handout and attendance sign-in sheet at the meeting. During the meeting, the contractor shall, at a minimum, present a complete overview of the CWP including reviewing the schedule, and highlighting any issues (review periods, Page 9 of 1 3 material submittals etc. ) which are key to maintaining the schedule. The contractor shall take meeting minutes to include recording of the attendance list (A004).
5.6 Progress Meetings
The contractor shall perform progress meetings as described in the table of deliverables. These meetings shall include all relevant base POC' s and contracting personnel on an as needed basis. These meetings will cover the progress made in the past period and shall include any pertinent issues which could affect future contract progress. The following items may be covered9
A. Meeting attendees and contact information
B. Project percent complete (actual and scheduled)
C. RFI' s and statuses
D. Material submittals and statuses
E. Two week look ahead
F. Schedule
G. Safety
H. Resolution of existing issues
I. New business
J. Review of redline drawings
5 . 7 Format of Deliverables An electronic copy of all deliverables shall be provided formatted for use on the latest version and compatible with the government' s version of Microsoft Word Excel Adobe Acrobat and AutoCAD. All deliverables shall also be dated. The contractor shall provide samples of the deliverables upon request.
5.8 Work Plan Submittal Requirements
In addition to the requirements of applicable UFC' s each design package shall include the following9
5 . 8 . 1 Executive summary with statement of work and all modifications.
5 . 8 . 2 Table of contents
5 . 8 . 3 Minutes and sign-up sheets of all meetings pertaining to the development of the design.
5 . 8 . 4 Previous government review comments and contractor responses.
5 . 8 . 5 All appropriate engineering calculations.
5. 8 . 6 Design drawings. Design drawings shall be submitted in line with the WBS and CWP submittals as noted in Appendix 8 . Review of these shall be done under the associated submittal and review conference.
Base CAD S tandards
• Drawings shall be submitted as an independent drawing set IAW with the current A/E/C CAD S tandards published by the CAD/BIM Technology Center. CAD/BIM Center Link9 https9 //cadbimcenter. erdc. dren. mil/default. aspx?p=a&t=1 &i=7.
• A/E/C CAD S tandard Annotation levels/layers shall be set to AutoCAD Index Color #7. (E. g. A-ANNO-TEXT).
Each A/E/C discipline (plans elevations utilities sections etc. ) shall be represented in a Model file. Model files are drawn at full scale and shall maintain a consistent origin throughout all Model file drawings. Architectural units shall be used for all interior model files and shall maintain the x y coordinate location and origin (0 0) of the model file provided by the Government. Decimal units shall be used for all exterior drawings (e. g. site plans utilities etc. ) and shall maintain the x y coordinate location and origin (0 0) of installation base map drawings.
• A Sheet file submission shall form the basis for all plotting and exporting functions. Relative paths shall be used for all Model file references attached to a Sheet set file. Each Layout (AutoCAD Paper Space) in a Sheet file shall be discipline specific with each discipline' s layers visible without manipulation by the user upon opening and be ready to plot. AutoCAD Layer Filters for each AEC discipline shall be created and their visibility set within each Sheet File Layout (AutoCAD Paper Space) viewport. See Figure 2-1 Sheet File composition in A/E/C CAD S tandard.
• S tandard sheet file size shall be ANSI D& unless noted otherwise in the contract. Model and Sheet file naming conventions shall comply with A/E/C CAD S tandard& Section 2. .. Title blocks and cover sheets developed by the Contractor or provided by the Government shall be present in the Sheet file Layout (AutoCAD Paper Space) for all Model files submitted and in the Model file Layouts for single drawing submissions. Minimum information includes the contract number& project number& project title& discipline& drawing number& and date. Plot page shall be set to AutoCAD DWG to PDF. pc3 Name and acad. ctb plot style table.
• Drawings shall be absent of extraneous information by utilizing the AutoCAD Purge command prior to saving.
• Each drawing file shall have point of contact information provided in the Summary tab of the Drawing Properties. At a minimum& the ContractorB s company name& phone number& and email address shall be provided.
• All drawings must be converted to PDF for review and acceptance by AFCEC.
5. 8 . 7 Work Breakdown S tructure The WBS shall illustrate the concept of the project and validate that the requirements are clearly understood (A006). It shall include at a minimum the project scope& background& and general descriptions of each major work element by facility. The WBS shall provide a clear distinction between the conceptual and execution phases of the work. The Contractor shall prepare and submit a WBS that provides representative conceptual level drawings and specifications necessary to define the extent and methods to be used for the construction activities.
The WBS shall identify appropriate materials& equipment& and any other data which the contractor proposes as items requiring government approval in line with UFC 3 -7.0-05 . Contractor shall prepare and submit a schedule for the submittals that ensure construction work is not delayed. The WBS shall be adequately detailed to an extent wherein& the implementation of the project work is conceivable& and constructible& with the project scope being sufficiently defined to accommodate coordination with the base and AFCEC.
The WBS shall addressg
• Meter types proposed i. e. & manufacturer& model& operating characteristics& etc. demonstrating full compliance with requirements and the Buy American Act.
• Meter wiring diagram
• Meter enclosure with all required devices
• Preparatory site work for meter installation
• Communication equipment& cable routing& and termination type.
• General coordination plan showing the contractor is solely responsible for planning access and execution of the scope of the project to include the coordination of power outages
5. 8 . 8 Draft Construction Work Plan Following the AF approval of the WBS& the Contractor shall prepare and submit to the Government a CWP that provides information necessary to complete construction. The draft CWP (A007) shall illustrate the contractorB s construction plan to execute the work. The draft CWP shall be in a complete& buildable state& pending final comments by the government. The CWP will define final specifications to be used for construction& provide necessary facility level drawings with system amperages and voltages to guide the construction& define submittal requirements necessary to address base needs& define construction management and reporting requirements& and provide a detailed schedule of construction activities.
The CWP shall include (at minimum) the following drawings and documentsg
• Building metering implementation plan showing new meter locations and type
• A prioritized list of metering components by location and utility type
• A construction schedule graphically depicting the schedule of events sufficiently clear to show how each sub-task shall be performed. This shall include activity& milestones and a critical path in executing this project.
Page 11 of 1 3
• Coordination of all utility interruptions
• Coordination of the schedule with AFCEC) COR) Base Comm) etc.
• Breakout of required materials by facility to include voltage and amperage
• Configuration and test plan for network equipment
• Detailed coordination plan showing the contractor is solely responsible for planning access and eixecution of the scope of the project to include the coordination of power outages
• Major project completion risk factors and mitigation processes to manage the risk to acceptable levels. This may include materials ordering and delivery) key manpower resources or similar items.
5. . . 9 Final CWP
The Final CWP (A00.) shall include all completed drawings and specifications (listed per para 5 . 7. )) as well as a Submittal Register with a complete list of required submittals. It shall incorporate all final Government comments.
5.9 Meter ID and IP request
Upon approval of the CWP and before Notice to Proceed) contractor shall submit an IP request in the format included in SOW Appendiix 2. Contractor also shall submit a RFI requesting the latest approved security configuration guide for the proposed electric meters.
5.10 Meter Pre Commissioning
The Contractor shall submit to the government) pre-commissioning documentation. Format is up to the contractor but shall address items listed in Appendiix 5 - 5 . 2 and eixamples in Appendiix 6) for installation and start-up of the meter/device. A 25 % pre-commissioning is submitted (A01 1 ) to ensure the Contractor is installing and formatting all devices and associated cabling correctly) and avoid rework as the remaining 75 % of meters are to be installed. Approval of the twenty-five percent (25 %) pre-commissioning inspection is with Base CE and AMRS personnel. The Contractor will address any outstanding items noted in the Pre-Commissioning Punch List generated by the government) within thirty (3 0) days of receipt of notice. The contractor shall not schedule any additional work until all Punch List items have been corrected to prevent the need for re-work. Any punch list items not able to be corrected during the Pre- Commissioning inspection) will need clear photographic documentation submitted to AFCEC to establish the corrections have been complete.
5.11 Meter Final Commissioning
The Contractor shall conduct a one hundred percent (1 00%) Final Commissioning) Appendiix 5 - Commissioning Plan & Test Procedure) with AMRS personnel and COR and publish the findings in a final commissioning report (A01 1 ). Within seven (7) days after the final commissioning) the Contractor shall present a completed DD Form 1 3 54) Transfer and Acceptance of Real Property to the BCE or other appropriate organiization for signature and acceptance) if required. Progress payments are tied to the submission and acceptance of the DD Form 1 3 54.
5.12 Meter Labeling
A meter ID will be provided by the government) upon submission of a post award RFI) and a physical label will be adhered to the meter by the contractor. The details of the physical label areas followedP AMRS Meter ID# XXXXNNNNNNEMNN) must be white on black phenolic) at least 1 -inch ix 3 inches) and permanently attached to the meter. The AMRS Meter ID breakdown isP
• XXXX = GLHN = FE Warren Base Code
• NNNNNN = the building number (add leading izeroes if necessary)
• EM = meter type (E = electric) G = gas) W = water) S = steam)
• NN = Meter sequence number for the building (e. g. ) 01 ) 02) etc. )
5 . 1 3 Meter S ite Commissioning
Page 12 of 1 3
The contractor shall follow commissioning procedures as furnished in Appendix 5 , AMRS Commissioning Plan & Test Procedure. At the final commissioning, the Contractor shall present a Meter Commissioning Test Procedure Checklist (A01 1 ) and the manufacturers supplied meter calibration certificates.
5 . 1 4 Duty Hours/Base Access
The Contractor shall complete work between the hours of 0730 and 1 600 local time excluding Saturdays, Sundays, and Federal Holidays. Any work outside of these hours must be pre-coordinated with the COR at the base. Inclement weather, operational delays, and security related delays might affect the ContractorB s work periods. All commercial vehicles requiring access on the base will require inspection.
The Contractor may be required to temporarily stop work for operational requirements, special events, installation exercises, or while Distinguished Visitor (DV) familiarization visits/tours are conducted.
Family DaysG As of 01 November 2024, the approved 2025 Family Days for FE Warren AFB areG 2 January, 1 7 January, 1 4 February, 23 May, 20 June, 07 July, 29 August, 1 0 October, 1 0 November, 28 November, 26 December and 02 January 2026.
It is the contractorB s responsibility to continue to verify with the COR any changes to said dates.
Other days the installation is closed or minimally mannedG it is the contractorB s responsibility to continue to verify with the COR any changes.
5.1 4. 1 Base Contractor Vehicles
The company name shall be prominently displayed on all Contractor vehicles operated at the base. The Contractor may obtain entry passes at the base Visitors Center for vehicles needed to transport materials and equipment. The Contractor will be required to present proof of insurance, driverB s license, vehicle registration, and other documentation as needed to obtain vehicle entry pass. Entry to restricted areas of the base will require a vehicle pass and additional clearances. All commercial vehicles requiring access on the base will require inspection.
Appendices
1. FE Warren AFB Scope
2. AMRS Meter ID and IP Sheet
3. AMRS Meter Specifications
4. AMRS Flow Chart/Work Flow & Milestones
5. AMRS Commissioning Plan & Test Procedure
6. AMRS Commissioning Document Examples
7. FE Warren AFB Building Floor Plans
8. Contract General Provisions
CDRLS
CDRL A001 - Health and Safety Plan
CDRL A002 - Quality System Plan
CDRL A003 - S ite Project Summary
CDRL A004 - Meeting Minutes
CDRL A005 - Monthly S tatus Report
CDRL A006 - WBS Submittal
CDRL A007 - Draft CWP Submittal
CDRL A008 - Final CWP Submittal
CDRL A009 - Weekly Progress Log
Page 13 of l 3
CDRL AOl O - Meter ID and IP Request
CDRL AOl l - Pre and Full Commissioning Report
CDRL AOl 2 - As Built Drawings
OOW Appendices 1 - 8
'B DW Appendix 1
EM= Electric Meter
ER = Electrical Room
CR = Communications Room
GM= Gas Meter
MC = Mission Critical (Long Lead Time for Power Outage)
MDP= Main Distribution Panel
MR=Mechanical Room
OND= Outside Normal Duty (Power Outage Scheduling)
SIG = Switch Gear
SEM= Solar Electric Meter
XFMR= Transformer
Item 1
Install New AMRS Compliant Electric Meter and Communication
The Contractor shall purchase and install 55 new AMRS compliant electric meters and CTs (Table FEW1 )d The Contractor shall furnish all materialsf equipmentf labor and miscellaneous items necessary to install the new metersd The Contractor shall install 55 new communication outletsf LAN receptacle plug-insf and associated equipment to establish remote communications to the patch panel associated with the nearest Air Force network switch or other noted locationd Cable used for communications outlets shall be Blue sheathedf four pairf 23 AWGf solid copper conductorf CAT6f UTPf CMPf and UL Verifiedd Assume all communication runs are <328 feetf to include patch cablesf unless otherwise notedd Fiber communication runs are annotated in Table FEW1 d All voltage and amperage noted in Table FEW1 is the responsibility of the contractor to field verify prior to design.
Table FEWl
Meter Count /
Quantity
Facility
Facility Name
Meter
MDP &
Location
CR
Location
Notes
MC
SECURITY POLICE
OPERATIONS
EM1
Basement 480/277 V 1 200 Amp
See Floor Plan
MDP in Basement¥ access through Boiler roomf Exterior double door
3 7
MC
OND
90 SFS INVESTIGATIONS
208 /1 20 V 600 Amp
See Floor Plan
AM RR Aoopn c D 1 - RScop
1 1 U Y 2025 E WARRE E A F
MC
OND
HEADQUARTERS
NUMBERED AIR FORCE
EM'
200 &' 20 V ' 100 Amp See Floor
Plln
FMn MSgt Iemaen 73070077-543 & Capt Jsoesse 73070077-574
4 ' 50 BASE THEATER EM'
I00 Amp
See Floor Plln
POCn Mr Tsrmsy 730700774387 Rseqursd fsr COMM Accsss
' 5 '
OND RECREATION CENTER EM2
I00&277 V I00 Amp
Plln s
' 52
MC
OND
HEADQUARTERS
NUMBERED AIR FORCE
I00&277 V I00 Amp s
7 207
AIRMAN & FAMILY
READINESS CENTER EM'
200 &' 20 V I00 Amp
2' 2
CHAPEL ANNEX
Bassmset 200 &' 20 V I00 Amp
9 2' 1 BASE PERSONNEL EM'
225 Amp n 0 2' I FTAC EM'
I00 Amp n n
DORM
200 &' 20 V ' 100 Amp n 1
200 &' 20 V ' 100 Amp
See Floor n 3
MC
{A&CS&SFG&CES&MXS&MW&AR
MY
200 &' 20 V ' 200 Amp n 4
2II
200 &' 20 V ' 100 Amp
See Floor n 5 2I1
AFOSI
200 &' 20 V I00 Amp
See Floor
Escort Reeuured n 6
WING HEADQUARTERS
000 Amp
COMM… See Floor Plln ELEC… Fed †rom B1 ' 00
2 EMs IMDP ' lnd
MDP130
MDP 2 us †ed †rom
MDP ' Ittru drysplc3
FM Reeuured †or Accesssenter lt Front Door on Rlndlll AVe n 7
WING HEADQUARTERS
EM2
I00 Amp
See Floor Plln
FM Reeuured †or Accesssenter lt Front Door on Rlndlll AVe n 8
Œ0 FSS STORAGE
' 25 Amp n 9
1 ' I
GYMNASIUM
100 Amp
1 ' 1
BASE ENGINEER
MAINTENANCE SHOP
I00 Amp
1 1 U Y 0 5 E WARRE E A F
3 ' 7
#0 CES STRUCTURE SHOP
1000' 10 V I00 Amp
3 ' 0
BASE ENGNNEER
MANNTENANCE SHOP
I000177 V I00 Amp
3 ' 0
I00 Amp
3 10
ADMNNNSTRATNON
I00 Amp
3 13
100 Amp
3 15
ANRMAN DNNNNG HALLS
' 100 Amp
3 31
FNRE STATNON
115 Amp
3 31
FNRE STATNON
' 000 Amp
See Floor Plln
ERxisxng PM5553 xn new gelr on Fxre ixie ZEM01)
3 3 3
TELECOMM FACNLNTY
' 100 Amp
See Floor Plln
Noste Fusurt AMRS Strvtr Locaston - POC Jacob Barrows 730-007--4-4
3 35
EXPLOSNIVE ORDNANCE
DNSPOSAL
Acctss strougt factitsty iocastd tn ssoragt bat
500 Amp
3 I0
S SQUADRON OPERATNONS
000 Amp
3 I'
PMEL
' 100 Amp
I0'
RECREATNON CENTER
Upssatrs 1000' 10 V 000 Amp
I55
OND
CHNLD DEIVELOPMENT
CENTER
' 100 Amp
I75
FREEDOM HALL & HAWC
1000 Amp
36 I05 LCH OPS TNG FAC EM'
000 Amp
Plln >
1 1 U Y 0 5 E WARRE E A F
37 II5 20 CES HVAC EMI
1040I 10 V 400 Amp
Plln ;
74 I
BASE ENGSNEER
MASNTENANCE SHOP -
Power Pro
EMI
I00 Amp
4 84
HEADQUARTERS CENTER
400 Amp
BASE ENGSNEER
PAVEMENTS AND
GROUNDS FACSLSTY
4400177 V I 100 Amp
I 185
SHOPP MSSSSLE SERVSCE
1000 Amp
I 145
20 LRS VEHSCLE MNX
I 100 Amp
I 150
BASE OPERATSONS
4400177 V See Floor
I 170
VEHSCLE MASNTENANCE
SHOP
Rm 1 1 9 4400177 V I00 Amp
I 174
LRS CMD SECTSON
100 Amp
I 144
BASE SUPPLY0MPF
I 100 Amp
FSBER - cue so run lenfsh
I 145
HAZMART SUPPLY
PHARMACY
Fed from B1 m24
I 121
MC MSSSSLE OPS BLDG EMI
4400177 V 400 Amp
I 124
TECH TNG LAB0SHOP
Seeure Faetuttwx eapture at
XFMR
I00 Amp
I 50I
MC VEHSCLE HEAT PARKSNG EMI
4400177 V I I00 Amp
I 501
400 Amp
I 50I
I00 Amp
I 755
YOUTH CENTER
I00 Amp
SSI 04
FEEDER I
Plln|
FSBER so I 150
See Floor Plln }or Snnslll Nosen
SSI 04
MC FEEDER 1 EM1
Plln| See Floor Plln }or Snnslll Nosen
OND FIBER to
1 250
Item 2
Item
Patch Panels
The Contractor shall purchase and install 1 8 new AMRS compliant network patch panels (Table FEWPP1 ) in the communications room associated with the building.
AMRS compliant network patch panelT 1 C ' rack mounted, CAT6 , 1 1 0 style T- 5 68 B
Table FEWPPl
Facility #
3 7 207 21 2 21 4 262 3 1 4 3 1 7 3 20 3 23 401 485 665 781 8 34 930 1 235 1 270 1 294
Installation Notes:
1. See Appendix 3 - AMRS Meter Specification for installation guidelines
2. All removed equipment will be returned to the government.
3. Mission critical, denoted as MC, facilities shall require late night or weekend outages and have longer lead times for power outage scheduling.
4. Outside normal duty hour OND shall require late night or weekend outages
5. Security notation is intended to inform the contractor that additional layers of security apply to this facility and may cause access for work to move slower than traditionally expected. These facilities should be coordinated in advance for access. The facility manager must be aware at all times of the contractor“ s presence in the facility.
6. It is the sole responsibility of the contractor to coordinate and schedule all power outages through base Civil Engineering work order process. Multiple facility outages can be coordinated on the same day within reason pending staff availability and mission critical activities. This is typically done when several facilities are fed from the same switch or transformer. Each outage will need to be coordinated with the electrical shop and base communications squadron.
7. When installing communications cable within buildings, all cabling must be installed in accordance with the Base Communication S tandard and Appendix 3 AMRS Meter Specification for installation guidelines.
8. No meter shall be connected to the AF network until government provided security settings and firmware upgrades have been installed.
9. If trenching is specified in the design, the contractor must submit a Work Clearance Request, AKA "Dig
Permit", AF Form 1 03 to the base point of contact.
1 0. The final connection to the Air Force switch may have to be performed by the base communications organization. In that event, a six (6) foot patch cord labeled "AMRS EMxxx" shall be left connected to the patch panel in the comm room, third party to make the final connection. It is the responsibility of the contractor to coordinate the installation of the patch cable with the base communication squadron. At that time, the security settings should be installed on the meter, by the contractor, and the communications squadron should be notified, by the contractor, that the port on the switch can be configured for CECOINE.
1 1 . All underground conduit shall be PVC Schedule 40 or Schedule 80 in accordance with UFC 3 -550-01 Exterior Electrical Power Distribution and be installed a minimum of 3 6 inches deep.
1 2. Contractor shall be required to secure flight line badge for the site superintendent whom shall be present for all work occurring on the flight line.
1 3 . Final bleeding and purging of gas lines/ gas meter is the responsibility of the contractor.
1 4. The contractor shall include a spreadsheet in the pre and final commissioning, to annotate the current register reading on any meter with a register removed under this scope. Contractor shall ensure the reading is taken before the meter is decommissioned/removed.
1 5 . All electric meters shall be installed in an interior location unless otherwise noted or approved in the CWP.
1 6. See Appendix 8 for Base Restricted Access Area Requirements 1 7. Execution of work tasks organized in a manner as to limit impact on building occupants and government support staff. This shall include scheduling personnel and preparing equipment needed to complete the tasks, including reasonable contingencies, with minimum site visits
'B DW Appendix 2
Base XVZ AM RS M eter Configuration Data
Step 1 : Green h i gh l i gh t i s completed by contractor, and submitted to AFCEC.
Step 2: AFCEC wi l l request orange h i gh l i gh t to be completed by base CS, and reviewed by AFCEC.
Step 3: Vel l ow h i gh l i gh t i s completed by contractor after i n stal l .
B DG F R
M E ER
R M
V
V E MA E M DE DE CE AME
S E R A
MBER
C MM
R M
A C A E
S C
R MAC
ADDRESS
S B E
GA E AV
S B E
MAS
Core ode
1 0 1 E R 42 E l ectrr c Sch n e r ier I ON 8650 D KF X000054E 01 LW-1 905 B 289 -02 CR 1 1 0 E 42 00. 60. 78. 0B . B 4. 54 1 0. 200. 4. 1 1 1 0. 200. 4. 1 255 . 255 . 255 . 0 1 72
'B DW Appendix 3
AMRS Meter Specifications v. 1 1 . 21 . 2024
Appendix 3
1 .1 AMRS Electric Meter Specifications The AMRS Compliant Electric Meter shall meet Department of Defense cybersecurity standards as well as the following requirements:
• Electric meters shall meet or exceed the ANSI C1 2. 1 -2022, 0. 2 accuracy class standard
• Current transformers (CTs) shall meet or exceed the accuracy class of their associated electrical meter onboard memory
• Onboard Ethernet communications, 1 0/1 00 base with RJ45 connector or receptacle
• Modbus/TCP communication protocol is required
• Front display with ability to display all measured values
• Minimum of one (1 ) external RS 485 serial communications port
• Minimum of two inputs that shall count pulses from other devices
• Electric meter enclosure shall be designed and constructed in accordance with UL508 A to ensure safety and reduce the risk of…