This pre-solicitation notice seeks proposals for a cost-plus-fixed-fee indefinite delivery/indefinite quantity contract to provide operations support and studies services to the United States National Data Center. The Air Force Technical Applications Center requires a contractor to maintain, sustain, and enhance software and hardware systems for geophysical data processing, configuration management, database administration, and scientific programming. The contractor must also integrate third-party systems and conduct engineering and scientific studies to optimize data analysis capabilities. The period of performance is six years with an anticipated award date of September 2019. Offerors must hold a Top Secret facility clearance and register in the System for Award Management to be eligible. The incumbent contractor is the Air Force Technical Applications Center.
Attachment 7 - Draft PWS for Task Order 01
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT
FA7022-19-R-0001, US NDC OSS II PWS, 22 Jun 2018
TO FA7022-19-F-xxxx, 22 Jun 2018
PERFORMANCE WORK STATEMENT (PWS)
FOR
United States National Data Center (US NDC)
Operations Support and Studies (OSS) II
Task Order (TO) FA7022-19-F-xxxx
FY 20 Operations Support
AFTAC/SDA
22 Jun 2018
FA7022-19-R-0001, US NDC OSS II PWS, 14 Jun 2018
TO FA7022-19-F-xxxx, 22 Jun 2018
Revision Number Date Revision Description
Revision 0 22 Jun 2018 Pre solicitation draft only for TO 01
TO FA7022-19-F-xxxx, 22 Jun 2018
1 DESCRIPTION OF SERVICES
1.1 INTRODUCTION
1.2 BACKGROUND
1.3 SCOPE
1.4 PERIOD OF PERFORMANCE
2 SPECIFIC TASKS
3 SERVICES SUMMARY (SS)
4 GOVERNMENT FURNISHED PROPERTY AND SERVICES
4.1 SERVICES
4.2 FACILITIES
4.3 UTILITIES
5 GENERAL INFORMATION
5.16 DELIVERABLES
APPENDIX A – ACRONYMS AND ABBREVIATIONS LIST
APPENDIX B - ESTIMATED WORKLOAD DATA
APPENDIX C - APPLICABLE PUBLICATIONS & INSTRUCTIONS
APPENDIX D - MAPS AND/OR SITE PLANS ...... ERROR! BOOKMARK NOT DEFINED.
APPENDIX E – CONTRACTOR SUPPORT STAFF DESCRIPTIONS ........................ ERROR!
BOOKMARK NOT DEFINED.
TO FA7022-19-F-xxxx, 22 Jun 2018
SECTION 1
1 DESCRIPTION OF SERVICES.
1.1 Introduction.
1.1.1 This is a non-personal services contract. The Government will neither supervise contractor employees nor control the method by which the contractor performs the required tasks. The contractor shall manage its employees and guard against any actions that are of the nature of personal services, or give the perception of personal services. The contractor shall notify the
Contracting Officer (CO) immediately if they perceive any actions constitute personal services.
These services shall not be used to perform any Inherently Governmental Functions.
1.1.2 This task order is subordinate to Indefinite Delivery/Indefinite Quantity (IDIQ) basic contract
FA7022-19-R-0001, 22 Jun 2018. This task order provides operations support to AFTAC and the US
NDC for FY 20. All paragraphs in the basic contract master PWS are applicable and included in this
PWS except as noted below. Paragraphs in this document that are changed take precedence over the original PWS paragraph.
1.1.2.1 For this task order PWS, the following basic contract master PWS paragraphs and sections listed below are in effect. Changes or additions to any PWS paragraphs and tables are included below under the appropriate headings.
Basic contract PWS reference Subparagraphs
1.2 Background 1.2.1 – 1.2.5
1.3 Scope 1.3.1; 1.3.3 – 1.3.5.10
1.4 Period of Performance 1.4.1 – 1.4.1.1
2 Specific Tasks
2.1 US NDC O&M Tasking Statements (O&M Funded) 2.1.1 – 2.1.6.9
2.3 Program Support (O&M Funded) 2.31. – 2.3.1.1.3;
2.3.2 – 2.3.3
3 Services Summary (SS)
4 Government Furnished Property and Services 4.1 – 4.5
5 General Information 5.1 – 5.16
Appendix A
Appendix B
Appendix C
1.2 Background.
1.2.7 This task order is for all O&M Labor, O&M ODC, O&M CDRLs, and O&M Travel only, applicable to the base contract PWS Paragraphs identified in the table in Paragraph 1.1.2.1 above.
Negotiated rates apply; however, level of effort is negotiated.
1.3 Scope.
1.3.1. The scope of work of this TO is to provide maintenance, sustainment, configuration management, database and system administration, development, testing and integration of geophysical data processing software, hardware, and geophysical data from both traditional and non-traditional sources into the US NDC system that includes the operational subsystem, alternate
TO FA7022-19-F-xxxx, 22 Jun 2018
SECTION 1
subsystem, training subsystem, sustainment/development subsystem, and special purpose/special access subsystems.
1.3.3 This TO Performance Work Statement (PWS) captures Contractor tasks and responsibilities for the Operations and Maintenance (O&M) of US NDC as described in the
US NDC Phase-3 System Requirements Document (SRD) dated 19 Sep 2007. Upon acceptance of the US NDC Modernization Geophysical Monitoring System (GMS), the US NDC
Modernization SRD shall replace the Phase-3 SRD. Specifically, the Contractor tests, integrates, implements, and sustains a data acquisition, data processing, and data archival hardware and software system that meets all the requirements stated in the US NDC SRD.
1.4 Period of Performance.
1.4.2 The Period of Performance for this TO shall be 1 Nov 2019 – 30 Oct 2020.
TO FA7022-19-F-xxxx, 22 Jun 2018
SECTION 2
2 SPECIFIC TASKS.
2.3.1.3 Task Order Start Date Meeting
A Task Order Start Date meeting shall be conducted ten (10) days before the actual performance start date of TO, and shall include the discussions on the Contractor’s readiness and capability to assume full responsibility for work under TO 01, FY 20 Operations Support. This TO Start meeting can be held in conjunction with the Pre-Contract Start Date meeting under contract PWS
Paragraph 2.3.1.1.3.
FA7022-19-R-0001, US NDC Ops Support PWS, 14 Jun 2018
TO FA7022-19-F-xxxx, 22 Jun 2018
SECTION 3
3 SERVICES SUMMARY (SS).
The contract service requirements are summarized in performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimally acceptable levels of service required for each requirement. The Services Summary (SS) provides information on contract requirements and the expected level of contractor performance to be successful.
These thresholds are critical to mission success. Procedures as set forth in the applicable
Inspection clause in the contract will be used to remedy all deficiencies. The Government retains the right to inspect any item included in the contract.
Only performance objectives #1 thorough #9 from the basic contract master PWS apply to this task order.
Performance Objective
PWS
PARA
Performance Threshold
SS # 1.
Timely response to call for 24/7 on-call support responding to call within 15 minutes
2.1.1.1 Quarterly: 90% of the time within 15 minutes.
The remaining 10% within 30 minutes.
SS # 2.
Resolution of 24/7 on-call support problems within 60 minutes of initial notification
2.1.1.1 Quarterly: 95% of the time, issue is resolved via
phone or contractor is on site working the problem within 60 minutes. The remaining 5% within 90 minutes.
SS # 3.
Timely response to Urgent CRs resolving within 72 hours of approval notification
2.1.1.2;
2.1.1.3
Quarterly: 100% of the time, unless otherwise authorized by the COR.
SS # 4.
Timely response to station update
(SU) CRs for new stations development within three (3) business days of approval to work notification.
2.1.1.2;
2.1.1.3
Quarterly. 80% of the time. The remaining 20%, complete development within five (5) business days. In the event of more than one (1) new station
SU CR per week, the PM/COR will provide a priority and the contractor shall complete at least one CR per each successive three (3) business day period.
SS # 5.
Timely response to station update
(SU) CRs for existing stations used in Automated Processing (Spotlight or Pipeline), development within five (5) business days of approval to work notification.
2.1.1.2;
2.1.1.3
Quarterly. 80% of the time. The remaining 20%, complete development within seven (7) business days. In the event of more than one (1) update existing automated processing SU CR per week, the PM/COR will provide a priority and the contractor shall complete at least one CR per each successive five (5) business day period.
TO FA7022-19-F-xxxx, 22 Jun 2018
SECTION 3
Performance Objective
PWS
PARA
Performance Threshold
SS # 6.
Timely CR Post Operations
Verification, complete post operations verification within one
(1) week of promotion to the operational system.
2.1.1.2;
2.1.1.3
Quarterly. 50% of the time. The remaining 50%, complete post operations verification with two (2) weeks of promotion of the CR to the operational system.
SS # 7.
Timely CR Post Operations
Validation, complete post operations validation within 30 days of promotion to the operational system
2.1.1.2;
2.1.1.3
Quarterly. 50% of the time. The remaining 50%, complete post operations validation within 60 days of promotion of the CR to the operational system.
SS # 8.
Timely submission of all Data
Deliverables in accordance with
PWS and CDRL schedule. CDRLs
A001 – A014.
2.1 –
2.2.2;
2.3.3;
4.4; 5.12
Quarterly. 95% of the time. The remaining 5% submitted no more than five (5) business days after established due date.
SS # 9.
All final Data Deliverables are delivered on time and require no administrative or technical clarifications or corrections. CDRL
A001 – A014
2.1 –
2.2.2;
2.3.3;
4.4; 5.12
Quarterly. 95% of the time. The remaining 5% delivered, clarified or corrected, within 5 business days of due date.
TO FA7022-19-F-xxxx, 22 Jun 2018
SECTION 4
4 GOVERNMENT FURNISHED PROPERTY AND SERVICES.
4.1 Services.
The Government will provide the necessary services for the contractor staff to provide the services outlined in individual task orders to include help desk support, IT security, trash, janitorial, and other services that are provided to Government personnel in AFTAC.
4.2 Facilities.
The Government will provide the necessary workspace for the contractor staff to provide the services outlined in individual task orders to include desk space, telephones, computers, and other items necessary to maintain an office environment, if the services provided are on-site (AFTAC headquarters). If the services are being performed at the contractor facility, no facilities will be provided.
4.3 Utilities.
The Government will provide the necessary utilities for the contractor staff to provide the services outlined in individual task orders to include electricity, heating, cooling, and water, if the services provided are on-site (AFTAC headquarters). If the services are being performed at the contractor facility, no utilities will be provided.
TO FA7022-19-F-xxxx, 22 Jun 2018
SECTION 5
5 GENERAL INFORMATION.
5.16 Deliverables.
Reports and other data required in task order PWS shall be submitted IAW the Contract Data
Requirements List (CDRL) in Exhibit A of the master contract.
APPENDIX A – ACRONYMS AND ABBREVIATIONS LIST
Acronym/Abbreviation Definition
AF Air Force
AFB Air Force Base
AFTAC Air Force Technical Applications Center
ALT Alternate Operations Subsystem
CAGE Commercial and Government Entity
CDRL Contract Deliverable or Data Requirements List
CFR Code Federal Regulation
CI Configuration Item
CM Configuration Management
CMB Change Management Board
CMP Configuration Management Plan
CO Contracting Officer
CONOPS Concept of Operations Defense Workforce Certification Application
COR Contracting Officer’s Representative
COTS Commercial Off-the-Shelf
CR Change Request
CSCI Computer Software Configuration Item
CSD Contract Start Date
DAA Designated Approving Authority
DAL Data Accession List
DBA Database Administration
DBDD Database Design Description
DCN Document Change Notice
DMP Data Management Plan
DoD Department of Defense
DWCA Defense Workforce Certification Application eCRMA Enterprise-wide Contractor Manpower Reporting Application
FAQs Frequently Asked Questions
FAR Federal Acquisition Regulation
FSP Forward Supply Point
FY Fiscal Year
GAFB Goodfellow Air Force Base
GFP Government Furnished Property
GMS Geophysical Monitoring System
GOTS Government Off-the-Shelf
HWCI Hardware Configuration Item
IA Information Assurance
IAW In accordance with
ICD Interface Control Document
IDC International Data Center
IEC International Electrotechnical Commission
IEEE Institute of Electrical and Electronics Engineers
IMS International Monitoring System
ISO International Standards Organization
IT Information Technology
JTR Joint Travel Regulations
LMI Logistics Management Information
MSR Monthly Status Reports
NDA Non-Disclosure Agreement
NISPOM National Industrial Security Program Operating Manual
NTNF National Technical Nuclear Forensics
O&M Operations and Maintenance
ODC Other Direct Costs
OPR Office of Primary Responsibility
OPS Operational Subsystem
OPSEC Operations Security
OSHA Occupational Safety and Health Act
OSS Operations Support and Studies
PAFB Patrick Air Force Base
PBSA Performance Based Service Acquisition
PCO Procurement Contracting Officer
PDAL Product Drawings and Associated Lists
PI Principle Investigator
PM Program Manager
PMRs Program Management Reviews
PoP Period of Performance
PPL Program Parts List
PSD Power Spectral Density
PWS Performance Work Statement
QA Quality Assurance
QASP Quality Assurance Surveillance Plan
QMP Quality Management Plan
R&D Research and Development
RDBMS Relational Database Management System
RMP Risk Management Plan
ROC Remote Operations Center
RTC Rational Team Concert
S//NF Secret//Not Releasable to Foreign Nationals
S//REL Secret Releasable To
SAS Seismic Analysis Software
SCM Software Configuration Management
SDA System Development Directorate, Treaty Monitoring Systems
Division
SDP Software Development Plan
SE Systems Engineering
SEATools Special Event Analysis Tools
SEP Systems Engineering Plan
SRD System Requirements Document
SS Services Summary
SSDD System/Subsystem Design Description
SSS System/Subsystem Specification
STIG Security Technical Implementation Guidelines
SU Station Update
SUS Sustainment Subsystem
SVD Software Version Description
TO Task Order
TDOC Time Dominant Operations Center
TDY Temporary Duty
TI Technical Instruction
US NDC US National Data Center
USAEDS United States Atomic Energy Detection System
USAF United States Air Force
APPENDIX B - ESTIMATED WORKLOAD DATA
The historical workload data provided is for informational use only and is based upon historical data. Contractors shall propose based on their own technical approach.
ITEM
LABOR CATEGORY
(See Appendix E for descriptions)
ESTIMATED
QUANTITY
(Hours/Year)
O&M TASKS
1 Database Engineering 3133
2 System Administration 7990
3 Software Configuration Management (SCM) 4230
4 Scientific Programming 19112
5 Computer Scientist 2506
6 Subject Matter Experts 2820
7 Program Manager 3133
8 Scientific Manager 470
43,394
Additional contractor workload metrics
1. 24x7 on-call support calls—67 calls handled by contractor over period of 1 Jan 2016 through
31 Mar 2018 for an average of 2.5 calls per month.
2. 238 mission-related software and hardware CRs promoted from 1 Mar 2017 to 31 Mar 2108 for an average of 18 CRs per month.
3. 139 new station and existing station CRs promoted from 1 Mar 2017 to 31 Mar 2108 for an average of 11 station update CRs per month. An additional 119 station update CRs have been promoted to support the TDOC effort from 1 Mar 2017 to 31 Mar 2108 for an average of 9 TDOC station update CRs per month.
4. Post-ops verifications—331 post-ops verifications have been handled by contractor over period of 1 Oct 2016 through 31Mar 2018 for an average of 55 post-ops verifications per calendar quarter.
APPENDIX C - APPLICABLE PUBLICATIONS & INSTRUCTIONS
Compliance with all publications, regulations and operating instructions provided by the
Government is required when: They pertain to the procedures for materials expediting herein and where the contractor is authorized by the PWS to accomplish the work specified in the publication, regulation or operating instructions. The publications prescribe USAF policies, use of materials, procedures and processes applicable to the work requirements. The contractor is required to acquire and work on the latest version of the publication.
The following documents were used as references in the development of this PWS. All
AFTAC/SDA controlled documents will be available for review via a Bidders Library. Access to the Bidders Library will be by appointment and the Library will be available upon release of the
Request For Proposal.
Compliance
United States National Data Center (US NDC) System Requirements Document
(SRD), 19 Sep 2007 (Available upon request to AFTAC/SDA)
United States National Data Center Network Definition Document (S//NF), Latest
Version. (Available upon request to AFTAC/SDA)
National Industrial Security Program Operating Manual (NISPOM) DoD 5220.22-M;
February 28, 2006. (Available via on-line sources)
Formats and Protocols for Continuous Data CD-1.0, Feb 2002 (Available upon request to AFTAC/SDA)
Formats and Protocols for Continuous Data CD-1.1, Dec 2001 (Available upon request to AFTAC/SDA)
AFMAN 33-363, Management of Records, AFI 33-364, Records Disposition-
Procedures and Responsibilities, 1 March 2008 Certified Current as of 21 July 2016 incorporating SecAF guidance memo of 02 Jun 2017
AFI 33-322, Records Management Program, 4 Jun 2012 Certified Current as of 25
May 2017 incorporating SecAF guidance memo of 26 Apr 2018
Guidance
MIL-STD-973, Configuration Management (Available via on-line sources)
United States National Data Center (US NDC) Change Management Board (CMB)
Process Guide, Latest Revision (Available upon request to AFTAC/SDA)
Institute of Electrical and Electronics Engineers (IEEE) 12207.0, Information
Technology - Software Life Cycle Processes (Available via on-line sources)
IEEE 12207.1, Information Technology - Software Life Cycle Processes - Life Cycle
Data (Available via on-line sources)
IEEE 12207.2, Information Technology - Software Life Cycle Processes -
Implementation Considerations (Available via on-line sources)
International Standards Organization (ISO) 9001, Quality Management Principles
(Available via on-line sources)
ISO/International Electrotechnical Commission (IEC) 90003, Guidelines for the
Application of ISO 9001 to Computer Software (Available via on-line sources)
Concept of Operations (CONOPS) for the US National Data Center (S//REL), Latest
Revision (Available upon request to AFTAC/SDA)
AFMAN 17-1303, Cybersecurity Workforce Improvement Program (Available via on-line sources)
DoD 8570.01-M, Information Assurance Workforce Improvement Program, 19 Dec
2005 with Change 4 dated 10 November 2015 incorporated (Available via on-line sources)
File details come from the government source that posted it. Updated .