Attachment 6 - Questions_Answers_Comments.pdf
PDF 123 KB Posted
- Attached to
- USAFA - Cascade Wind Tunnel Removal
- Solicitation number
- FA700026Q0058
About this file
This is a Questions, Answers, and Comments document for federal solicitation FA700026Q0058, concerning the removal of the Cascade Wind Tunnel (CWT) at the United States Air Force Academy (USAFA). The document addresses contractor inquiries regarding project scope, site conditions, and operational parameters for the demolition work.
Key project details include: no asbestos is present on site; all conduit must be removed, but only specific ductwork (circled in provided photos) requires removal; the HVAC unit contains R22 refrigerant and must be handled accordingly; the housekeeping pad supporting the HVAC unit should remain in place; and wall penetrations do not require filling after pipe removal. The facility has no basement, and doorways measure 7 feet tall by 6 feet wide. Contractors must complete the project within a 21-day window from the start date (excluding time for temporary badge acquisition) and are permitted to work 6am to 6pm on weekdays with temporary badges, though outside hours may be arranged with coordination. Fire suppression sprinklers will be shut off prior to work commencement through coordination with USAFA facilities. No restrictions apply to demolition tools, and dismantling methodology is flexible provided work is performed safely without damaging the building and in accordance with the Performance Work Statement. USAFA will remove all aircraft from the wind tunnel room prior to contractor mobilization, and additional construction projects may occur simultaneously within the building.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA700026Q0058
USAFA Cascade Wind Tunnel Removal
Attachment 6 – Questions, Answers, & Comments
1. Question: Is there any asbestos?
Answer: There is no Asbestos. See Attachment 5 – Asbestos Inspection Report (2016)
2. Question: Where should the supply and return pipes be capped?
Answer: Anywhere. There are shut off valves in the Machine Shop.
3. Question: Does all conduit come down?
Answer: Yes
4. Question: Is all ductwork to be removed?
Answer: Just the ductwork circled in photo 4 of Attachment 7 – Additional Photos, not the ductwork shown to the right in photo 4 of Attachment 7 - Additional Photos.
5. Question: Does it matter how the CWT is dismantled?
Answer: Safely without damaging the building and in accordance with any guidance in the Performance Work Statement (PWS); otherwise, no.
6. Question: Is there refrigerant in the HVAC unit?
Answer: Yes, R22
7. Question: Is there anything below the floor (i.e. a basement)?
Answer: No
Cascade room
8. Question: Will the sprinklers be shut off prior to the vendor beginning work?
Answer: Yes, the fire suppression sprinkler will be off with coordination with the USAFA CE Alarm Maintenance shop. Once vendor is chosen, there will be a coordination meeting between the fire dept, CE, the vendor, and the aero lab.
9. Question: Does the housekeeping pad that the HVAC unit sits on need to be removed?
Answer: No, USAFA wants to keep the housekeeping pad.
10. Question: Does the hole in the wall need to be filled after the pipe is removed?
Answer: No
11. Question: What are the measurements of the doorways?
Answer: 7ft tall and 6ft wide.
12. Question: What demo tools will contractors be allowed to use? (demo saw, acetylene torch, grinders, etc.)
Answer: No restrictions on tool use
13. Question: Does this project need to be completed within the 21-day window from start date?
Answer: Yes! (This 21-day window does not include additional time needed to obtain temporary badges.)
14. Question: What hours will contractors be able to work onsite each day?
Answer: Temporary badges (T-badges) will be issued—6am to 6pm on weekdays. If you would like to work outside the duty day hours, coordinate ahead of time.
Additional Remarks:
a. All planes inside the cascade wind tunnel room will be removed by USAFA prior to start of work.
b. There may be additional construction projects going on in the building at the same time, as stated in the PWS.