This is a Performance Work Statement (PWS) for the removal and disposal of an obsolete Cascade Wind Tunnel (CWT) system at the U.S. Air Force Academy Department of Aeronautics.
The contractor must completely dismantle, remove, and dispose of the CWT, its associated HVAC unit, and in-room ductwork located in the basement of the Aeronautics Laboratory (Building 2410) at USAF Academy, Colorado Springs. The main tunnel section measures approximately 20 feet in length and 8 feet in height, weighing an estimated 8,000–12,000 pounds. Key performance requirements include fluid evacuation of all oils, coolants, and hydraulic fluids; dismantling and removal without causing structural damage; safe tracing and disconnection of all mechanical and electrical utility connections using Lock-Out/Tag-out (LOTO) procedures; site cleanup and debris removal; and compliance with all applicable Air Force instructions, local, state, federal, and environmental laws and regulations. The contractor is solely responsible for obtaining all required permits, licenses, and certifications, including refrigerant recovery and fluid disposal. The contract period is 21 calendar days from award. Work shall be performed on-site during normal government hours (Monday–Friday, 7:30 a.m. to 4:30 p.m. Mountain Time), with weekend work available by prior COR approval at no additional cost. The contractor must submit a complete list of personnel requiring base access at least five business days prior to work commencement, and all personnel must obtain Real ID-compliant identification. Travel costs are non-reimbursable. Three deliverables are required: a Project & Safety Plan due 2 business days after award, certified weight tickets from the scrap facility due within 48 hours of disposal, and a Final Completion Report due upon project completion. The contractor must coordinate all activities with a concurrent Lab Renovation Contractor operating in the same facility per FAR clause 52.236-8.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PWS - Cascade Wind Tunnel Removal
PERFORMANCE WORK STATEMENT
CASCADE WIND TUNNEL (CWT) REMOVAL
U.S. Air Force Academy Department of Aeronautics
9 July 2026
JEFFREY M. LAYNG, Capt, USAF | Services Acquisition Lead (SAL) Approval Design Workshop Project POC / U.S. Air Force Academy Department of Aeronautics
Table of Contents
1. Background
2. Scope of Work
3. Performance Requirements
4. Government-Furnished Information & Property
5. Period of Performance
6. Place of Performance
7. Coordination with Other On-Site Contractors
8. Deliverables
1. Background
The United States Air Force Academy (USAFA) Department of Aeronautics (DFAN) requires the removal of an obsolete Cascade Wind Tunnel (CWT), associated duct work, and HVAC unit located in the basement of the Aeronautics Laboratory (Building 2410). The objective of this acquisition is to provide the solution and services necessary to break down and transport the CWT and related equipment to local abandonment/scrapping and will result in a room cleared for other functional opportunities.
2. Scope of Work
The Contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, supervision, certifications, and other items and non-personal services necessary to completely dismantle, remove, and dispose of the obsolete Cascade Wind Tunnel (CWT), including its associated HVAC unit and in-room ductwork, located in the Aeronautics Laboratory. The Contractor shall ensure the safe termination of all associated utility connections and leave the workspace clear of all equipment and dismantling debris.
3. Performance Requirements
3.1. Fluid Evacuation. The Contractor shall ensure the draining of all system fluids, including any oils, coolants, or hydraulic fluids, prior to disassembly.
3.2. Dismantling and Removal. The Contractor shall disassemble and remove the CWT, mounting frames, HVAC unit, and ductwork from the premises without causing structural damage to the facility. This includes the removal of all associated hardware, fasteners, and support structures from the floors, walls, and ceiling.
3.3. Utility Safing. The Contractor shall safely trace, disconnect, Lock-Out/Tag-out (LOTO), terminate, cap, and secure all mechanical and electrical utility connections formerly supplying the CWT and HVAC systems.
3.4. Site Cleanup and Disposal. The Contractor shall remove all dismantling debris. The Contractor is responsible for disposing of the equipment as scrap and providing the Government with certified weight tickets.
3.5. Regulatory Compliance. The Contractor is solely responsible for identifying, obtaining, and maintaining all permits, licenses, and certifications required to perform this work. The Contractor shall strictly abide by all applicable Air Force instructions and local, state, federal, and environmental laws, codes, and regulations—including environmental handling (e.g., refrigerant recovery, fluid disposal) and occupational safety standards—throughout the duration of the project.
4. Government-Furnished Information & Property
4.1. Site Data & Dimensions. The estimated dimensions of the main tunnel section are approximately 20 feet in length and 8 feet in height, with an estimated weight of 8,000- 12,000 lbs. These are estimates only; the contractor is responsible for verifying all measurements and weights.
4.2. Technical Documentation. The Government will provide the Contractor with any available technical drawings, specifications, and maintenance manuals for the CWT upon contract award.
4.3. Staging Area. The Government will provide a designated laydown area for staging equipment and dismantled components during the period of performance.
5. Period of Performance
The period of performance for this contract will be twenty-one (21) calendar days from the date of contract award.
6. Place of Performance
6.1. The work shall be performed on-site at:
Aeronautics Laboratory 2410 Faculty Drive USAF Academy, CO 80840
6.2. Duty Hours: The Government’s normal hours for site access are Monday – Friday, 7:30 a.m. to 4:30 p.m. Mountain Time, excluding federal holidays. Work outside these hours, including on weekends, may be authorized with prior coordination and approval from the Contracting Officer’s Representative (COR) at no additional cost to the Government.
6.3. Base Access and Security. All contractor personnel shall undergo a background check to obtain base access. The contractor must submit a complete list of all personnel requiring base access to the Contracting Officer’s Representative (COR) at least five (5) business days prior to the scheduled start of work. All contractor personnel must present a valid Real I.D.-compliant identification (or second approved form of government-issued identification) at the Pass and Registration Office to be issued their entry credentials prior to starting performance.
6.4. Travel Costs. No separate reimbursement will be authorized for contractor travel or commuting expenses.
7. Coordination With Other On-Site Contractors
7.1. Joint Occupancy & Cooperation. The Contractor is advised that a separate, concurrent government contract may be active for the USAFA Lab Renovation within the same facility (Building 2410) during the performance period of this contract.
7.2. Scheduling Coordination. In accordance with RFO 52.236-8 (Other Contracts), the Contractor shall coordinate all on-site activities, staging of materials, deliveries, and utility interruptions with the Lab Renovation Contractor and the Government Contracting Officer’s Representative (COR).
7.3. Workspace Conflicts: The Contractor shall not commit or permit any act which will interfere with the performance of work by any other contractor. In the event of a scheduling or physical workspace conflict, the Contractor shall immediately notify the COR for a final determination on priority of work deliverables.
8. Deliverables The contractor shall provide the following deliverables to the COR for final project acceptance:
Deliverable Description Due Date
Project & Safety Plan A brief outline of the dismantling approach, safety measures, and schedule.
2 business days after contract award
Certified weight tickets Official weight tickets from the scrap yard or recycling facility verifying disposal.
Within 48 hours of disposal
Final Completion Report A brief statement confirming all equipment has been removed, utilities safed, and the site cleaned of dismantling debris.
Upon project completion
| __________________________________________________________________________________________ |
| 1. Background |
| 2. Scope of Work |
| 3. Performance Requirements |
| 4. Government-Furnished Information & Property |
| 5. Period of Performance |
| 6. Place of Performance |
| 7. Coordination With Other On-Site Contractors |
| 7.1. Joint Occupancy & Cooperation. The Contractor is advised that a separate, concurrent government contract may be active for the USAFA Lab Renovation within the same facility (Building 2410) during the performance period of this contract. |
| 7.2. Scheduling Coordination. In accordance with RFO 52.236-8 (Other Contracts), the Contractor shall coordinate all on-site activities, staging of materials, deliveries, and utility interruptions with the Lab Renovation Contractor and the Government ... |
| 7.3. Workspace Conflicts: The Contractor shall not commit or permit any act which will interfere with the performance of work by any other contractor. In the event of a scheduling or physical workspace conflict, the Contractor shall immediately notify... |
| 8. Deliverables |