XQPZ 12-0107

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this ammendment is to:

A. Incorporate Attch 1 - SOW (rev1), dated 29 Aug 2018.

B. Incorporate revised Attch 6 - Wage Determination, updated 08/03/2018.

C. Delete CLIN 0002 and CLIN 0003. All w ork is included in CLIN 0001.

D. Revise Section M to delete CLIN 0002 and CLIN 0003.

E. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 7

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 30-Aug-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA700018R0011

X 9B. DATED (SEE ITEM 11)

27-Jul-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

30-Aug-2018

CODE

10 CONS - FA7000

BRINKER, S.

8110 INDUSTRIAL DRIVE, STE 200

PKA

USAF ACADEMY CO 80840-2315

FA7000 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

FA700018R0011

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The Issued By organization has changed from

10 CONS - FA7000

KEELER, DOUGLAS 8110 INDUSTRIAL DRIVE, STE 20

USAF ACADEMY CO 80840-2315

to

10 CONS - FA7000

BRINKER, S.

8110 INDUSTRIAL DRIVE, STE 200

PKA

USAF ACADEMY CO 80840-2315

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0001

The CLIN description has changed from Rpr 4 Elevators to ADA-Falcon St, Rpr to Rpr 4 Elevators to

ADA-Falcon Stadium.

The CLIN extended description has changed from:

The contractor shall furnish all labor, materials, and equipment necessary to Repair/Install 4 Elevators to ADA at

Falcon Stadium to install those portions of the project falling within the area designated as “REPAIR & REPLACE

CONSTRUCTION” as shown on the design drawings provided to EXCLUDE minor construction.

To:

The contractor shall furnish all labor, materials, and equipment necessary to Repair/Install 4 Elevators to ADA at

Falcon Stadium in accordance with the project Statement of Work, drawings, specifications and other project documents.

CLIN 0002

The CLIN description has changed from Rpr 4 Elevators to ADA-Falcon St, MC to Reserved.

The contractor shall furnish all labor, materials, and equipment necessary to Repair/Install 4 Elevators to ADA at

Falcon Stadium to install those portions of the project falling within the area designated as “NEW MINOR

CONSTRUCTION” shown on the design drawings provided.

The signal code A has been deleted.

The FSC code Z2JZ has been deleted.

The PROG code C20 has been deleted.

The NAICS code 236220 has been deleted.

The MDAP/MAIS Code 000 has been deleted.

CLIN 0003

The CLIN description has changed from Rpr 4 Elevators to ADA-Falcon Sta, asbu to Reserved.

The contractor shall furnish all labor, materials, and equipment necessary to create As-Built CAD drawings to

USAFA standards per Statement of Work, Paragraph 7 PROJECT CLOSEOUT.

The signal code A has been deleted.

The FSC code Z2JZ has been deleted.

The PROG code C20 has been deleted.

The NAICS code 236220 has been deleted.

The MDAP/MAIS Code 000 has been deleted.

SECTION F - DELIVERIES OR PERFORMANCE

The following Delivery Schedule for CLIN 0002 has been deleted:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

365 dys. ADC 10 CES - F4BQ00

CONSTRUCTION MANAGEMENT

8120 EDGERTON DRIVE

USAF ACADEMY CO 80840

719-333-4876

FOB: Destination

F4BQ00

The following Delivery Schedule for CLIN 0003 has been deleted:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

365 dys. ADC 10 CES - F4BQ00

CONSTRUCTION MANAGEMENT

8120 EDGERTON DRIVE

USAF ACADEMY CO 80840

719-333-4876

FOB: Destination

F4BQ00

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Attch 01 - XQPZ 120107

SOW

9 29-JUN-2018

Attachment 2 Attch 02 - Construct

DWGS

64 29-JUN-2018

Attachment 3 Attch 03 XQPZ 120107

Specifications

927 29-JUN-2018

Attachment 4 Attch 04 XQPZ 120107

GeoTech Report

51 29-JUN-2018

Attachment 5 Attch 05 XQPZ 120107

Enviromental Standards

Attachment 6 Attch 06 XQPZ 120107

Davis Bacon Building

6 17-JUL-2018

Attachment 7 Attch 07 XQPZ 120107

Experience Form

1 17-JUL-2018

Attachment 8 Attch 08 Financial

Reference

1 17-JUL-2018

to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Attch 01 - SOW(rev1) 15 29-AUG-2018

Attachment 2 Attch 02 - Construct

DWGS

64 29-JUN-2018

Attachment 3 Attch 03 XQPZ 120107

Specifications

927 29-JUN-2018

Attachment 4 Attch 04 XQPZ 120107

GeoTech Report

51 29-JUN-2018

Attachment 5 Attch 05 XQPZ 120107

Enviromental Standards

Attachment 6 Attch 06 - WD CO180032 6 03-AUG-2018

Attachment 7 Attch 07 XQPZ 120107

Experience Form

1 17-JUL-2018

Attachment 8 Attch 08 Financial

Reference

1 17-JUL-2018

SECTION M - EVALUATION FACTORS FOR AWARD

The following have been modified:

EVALUATION FACTORS FOR AWARD

M-1 BASIS FOR CONTRACT AWARD:

1. This is a competitive best value source selection in which the Government intends to award a contract resulting from this solicitation to the responsible, technically acceptable offeror with the lowest evaluated price whose proposal meets all solicitation requirements. FAR 15.101-2(b) states tradeoffs will not be made and no additional credit will be given for exceeding acceptability. By submission of its offer, the offeror accedes to all solicitation requirements, including terms and conditions, and representations and certifications, in addition to those identified as evaluation factors or subfactors. Offerors must clearly identify any exception to the solicitation terms and conditions and provide complete accompanying rationale. The evaluation process shall proceed as follows:

2. The following factors will be evaluated:

Factor 1: Price

Factor 2: Technical

A. Initially the government will review all proposals to determine if each timely received proposal meets the requirements of the RFP, drawings, specifications, and government standards and regulations pertaining to the specifications. Failure to meet the requirements of this solicitation may, at the Government’s sole discretion, result in the proposal being determined unacceptable, being ineligible for award and eliminated at this point from the competition and further consideration.

B. Price Factor: Next, the government will rank all proposals that have adhered to the solicitation requirements by price (from lowest to highest total evaluated price), including any option prices if applicable. For proposal evaluation purposes, the contract line item number (CLIN) will be evaluated as follows:

CLIN 0001 = Total Evaluated Price (TEP)

The government intends to award based on the total of CLIN 0001. The lowest total of CLIN 0001 shall constitute the lowest price offer.

Multiple contracts will not be awarded as a result of this solicitation.

C. Technical Factor: Next, starting with the lowest priced TEP offeror the Government will evaluate technical proposals for technical acceptability on an Acceptable/Unacceptable basis. ALL Technical Subfactors must be rated “Acceptable” to be considered technically acceptable. To be eligible for award, an offeror must have an

“Acceptable” rating in every non-priced subfactor either on the basis of the initial proposal, or as a result of discussions, if conducted.

The Technical Subfactors will be assigned a rating of Acceptable/Unacceptable as defined in accordance with DoD

Source Selection Guide Procedures, Table C-1, listed below:

Technical Acceptable/Unacceptable Ratings

Rating Description

Acceptable Proposal meets the requirements of the solicitation.

Unacceptable Proposal does not meet the requirements of the solicitation.

Technical proposals will be evaluated based on the following two subfactors:

i. Subfactor 1: Experience - To be rated “Acceptable” the offeror must provide sufficient information on Attachment

07 to substantiate the offeror’s demonstrated previous experience as follows:

The prime offeror must submit information for a single project (e.g. single task order, single purchase order, single contract, etc.) performed or managed by the prime offeror as either a prime contractor or subcontractor clearly demonstrating to meet ALL of the following criteria:

a. Project shall be ongoing or completed within the past five (5) years from the issuance date of the solicitation

b. Project contract value of $1,000,000.00 or more

c. Project was construction at existing site or facility (NOT completely new construction)

d. Project includes ALL of the incidental construction work: Electrical work, excavation/earthwork, concrete work, landscaping and/or revegetation, utility work.

Experience for a project performed by a proposed subcontractor that the offeror may use for performance of the solicited requirement will NOT be considered, and will be rated “Unacceptable.”

AND

In order for the Government to assign a rating, the project information must be verified with the provided point of contact by the evaluation team, via phone or email. At a minimum, the Government will use the offeror's provided point of contact, phone or email to verify the project was performed by the named contractor and to verify that the minimum experience requirements stipulated above (a-c) were included in the project in order to determine if the experience requirements have been met. If the point of contact cannot be reached through reasonable attempt, a rating of Unacceptable will be assigned. In making a determination, the Government reserves the right to use both the information provided in the offeror’s proposal and information obtained from other sources available to the Government, to include, but not limited to, the Past Performance Information

Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), or other databases; the Defense Contract Management

Agency; and interviews with Program Managers, Contracting Officers, and Fee Determining Officials.

ii. Subfactor 2: Conveyance Contractor License - The government requires the offeror to provide a licensed

Conveyance Contractor in the State of Colorado. To be rated “Acceptable” the offeror must provide a copy of its or a proposed subcontractor’s current, valid Conveyance Contractor License issued by the State of Colorado, Colorado Department of Labor and Employment Division of Oil & Public Safety. The license must be an active license and have been acquired prior to the closing date of this solicitation in order to be rated “Acceptable.”

The Government will verify the license is current, valid and issued by the State of Colorado, Colorado

Department of Labor and Employment Division of Oil & Public Safety.

3. Upon evaluation, if the lowest priced TEP evaluated proposal is rated “Acceptable” for all Technical Subfactors, the offer is considered technically acceptable and represents the best value for the Government, and the evaluation process stops at this point. Award will be made to that offeror without further consideration of any other offers. If the lowest priced TEP evaluated proposal is not rated “Acceptable” for all Technical Subfactors, the next lowest priced offeror will be evaluated and the process will continue (in order by price) until an offeror is rated “Acceptable” for all Technical Subfactors or until all offerors are evaluated. If all offerors are evaluated and none are rated "Acceptable", the Government reserves the right to enter discussions or cancel the solicitation at that point.

4. Offerors are cautioned to submit sufficient information and in the format specified in Section L. Offerors may be asked to clarify certain aspects of their proposal.

5. The government intends to award a contract without discussions with respective offerors. The government, however, reserves the right to conduct discussions if deemed in its best interest. Communication conducted to resolve minor or clerical errors will not constitute discussions and the contracting officer reserves the right to award a contract without the opportunity for proposal revision. The government reserves the right to award one or no contract at all, depending on the quality of proposals submitted. Failure to propose for any item in the

Schedule B may, at the Government’s sole discretion, cause the offeror’s proposal to be rejected as unacceptable.

(End of Summary of Changes)