This document is a Request for Information (RFI) for Project JLSS 25-0004 to Repair Sabre Street Pavement, issued by the government on September 19, 2025. The solicitation (FA671225B0003) contains 56 detailed questions and responses covering various aspects of the project, including pavement repair, storm drain work, utility relocations, hazardous material handling, and optional work items. Key project details include a 263-calendar day period of performance from October 10, 2025 to June 30, 2026, with base contract work (CLINs 0001-0003) and optional work (CLINs 1001-1010) that can be exercised separately.
The project involves pavement repair, including mill and overlay, subgrade repair, seal coating, and storm drain modifications at a federal installation. Contractors are responsible for creating work plans, obtaining permits, performing geotechnical investigations, handling potential hazardous materials in the IRP (Installation Restoration Program) area, and coordinating utility relocations. The government will provide reasonable outdoor storage space and coordinate utility shutdowns. Notably, funding is not guaranteed to be available at bid opening, with a potential award dependent on funds becoming available by September 30, 2025. The contractor will need to prepare detailed work plans, handle environmental testing, and comply with various technical and safety requirements specified in the conceptual drawings and specifications.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
September 19, 2025
Pre-Bid Request for Information (RFI) Solicitation: FA671225B0003
Project: JLSS 25-0004 Repair Sabre Street Pavement
A total of fifty-six (56) RFIs were received on this project. Listed below are the RFIs with the Government Response.
RFI #1: The Bid Package is missing Typical Specification Sections for Fencing, Concrete, Earthwork. By not including these sections allows bidders to provide residential grade materials, Such as gauge of fence fabric, and posts, Strength of concrete and Testing of concretes, Testing of compaction of soils, strength and type of geotextiles. Are these sections going to be included?
Government Response: Project specific Product and Execution Specifications are to be created as part of the Work Plan process. Refer to Statement of Work (SOW) Section 1.3 References, these references will be used to establish industry and government standards for the approval of the Work Plans.
RFI#2: Drawing C-1 Shows IRP area and states this area is to be assumed Hazardous Waste. It then continues to list potential Hazards. The project wants us to test this area after bid date. For estimating purposes, how do we assume how deep this hazard exists and to dispose of the hazard we don't know which Hazardous landfill to send it to or what it is going to cost us to haul or dispose. Example: South Corner of B129 shows inlet to be eliminated. The piping underneath remains and is shown to be extended to new Storm lines. We have no details of depth of piping and then no details of how much soil to be excavated for treating as Hazardous Materials. This could be a large area depending on depth of piping, since banks have to be assumed unstable and stepped back. Obviously if your extending the drain lines something has to be connected manually underground at this inlet location. Your obviously aware of the hazards and I am sure you have previous testing of materials and estimated depths. Do you have Previous testing data as-builts for B 129 showing depths of drains around building? All of this could be treated as Differing site conditions until you get more information from soil borings, but then you have to address the area as a change to the contract.
Government Response: The contractor is responsible for Creation of a Hazardous Waste Management Plan, Creation of the Work Plans, and performance of the work in the IRP area. Contractor needs to assume Hazardous material is present and will need to be properly disposed. Refer to Conceptual Drawing C-1 for location where Hazardous material can be expected.
CERCLA Administrative Records concerning the Former Drum Storage Area at Building 408 are public information and available at the following AFCEC website.
https://www.afcec.af.mil/News/Administrative-Record/
To access these records, choose “Continue to Site” Select “Pittsburgh ARB, PA” from the Installation List Select “SS-01 Building 408 Drum Storage Area” from the Site Filter list Select “Search” Lower on the page the search results contain information about this site.
Correspondence, Sampling Reports, Studies, Closure Information and other documents are available here.
https://www.afcec.af.mil/News/Administrative-Record/
RFI #3: Drawing C-1 shows a Vault used as sanitary Sewer Valve. The Drawing doesn't show this location, size, etc. The Point Elevation Data doesn't reference this anywhere either? Do you have Photos Or details of the size and equipment within that has to be removed for Pricing? Do you have as-builts for B129 and B130 that would show sewer lines and depths installed?
Government Response: Refer to note on Conceptual Drawing C-1 and Coded Notes on Conceptual Drawing C-3 for information on Sanitary Vault. Pictures of this structure are provided in the attached Photos for RFI Response. This structure housed a valve that was part of an Oil Water Separator System. This work does not include removal of an Oil Water Separator.
RFI #4: The SOW states that a work plan must be created in AUTOCAD including relevant specifications, submittals, and stamped by a professional Engineer, but the Specifications for the project address other plans but not an AutoCAD Work plan signed by a Professional Engineer. Is this a requirement for award?
Government Response: Contractor is to provide Work Plans as stated in the Statement of Work and as described on Conceptual Drawing C-1 in the Design Notes.
RFI #5: Soil Testing is addressed in the SOW and on the drawings. The Drawings indicate a sample should be taken every 250 CY's of Material. And Again this relates to the depth of excavations. If we sample 2.5 Feet deep we can sample every 10' x 10' Square feet, If we sample 5 foot deep, then a samples double by sampling every 5' x 10', and worse case if we working with sewer lines 10' deep our samples quadruple to very 5' x 5'.
This only adds cost to the bids especially since you are testing for many parameters.
Government Response: The Conceptual Drawings state in IRP Area Note: 3 The soil should be sampled in a grid with every representative square being 250 cubic yards… The dimensions in this question are stated in cubic feet.
RFI #6: Note 14 on the C-3 Drawing indicates an oil/water separator. Do you have any data on this vault such as sizing or gallon etc. For Pricing in advance, How are we to bid the content removal especially if mixed with oil nnd we don’t know how many gallons we are dealing with.
Government Response: Refer to RFI #3 Response. Wording of Coded Note 14 has been modified.
RFI #7: Drawings C-1 IRP Area Note 8c: PPE and Hazwoper 40 Hour Training: We assume this applies only to any person standing with the Hazardous soil area. Are you including equipment operators?
Government Response: Work to be performed in accordance with Federal OSHA Regulations 29 CFR 1920.120 Hazardous waste operations and emergency response.
RFI #8: Drawing C-5 General Note 1 "What to do for wider cracks?" Who is this question to? We assume this is for sealing asphalt, Typically USACE uses a mesh over wider cracks. They also typically estimate a quantity and the contractor bids the unit item and is only paid on completed quantities.
Government Response: Drawing C-5 General Note 1 "What to do for wider cracks?" was mistakenly left on the solicitation Conceptual Drawings. See revised Conceptual Drawing C-5 Dated 18Sept25. Clarifications are provided for asphalt surface sealing and crack sealing.
RFI #9: Drawing C-5 General Note 4 I am confirming we are pricing painting all lines etc twice in this contract. Once within 48 hours of paving and once after 1 month after paving.
Government Response: See revised Conceptual Drawing C-5 Dated 18Sept25. Clarifications are provided for line painting notes.
RFI #10: Drawing C-2 Undercut Subgrade Detail: "Area of Unsuitable Subgrade Remove as Directed" I don’t see any areas marked showing this area, so I assume this is a differing site condition. But also since we have no compaction standards, how is this determined? I see you are limiting this to only 3" Max, Typically AASHTO #1 is 2 - 4 inches thick, so you limiting yourself to 1 row of stones??? And then to make matters worse you suggest using a geogrid to reduce thickness. Geogrid is typically 2 to 3" itself depending on type and then choked in with stone. Are you changing the stone by using the geogrid? Does this save thickness?
Government Response: Refer to Paving Areas Legend on Conceptual Drawings C-2.
RFI #11: Specification Section shows the contractor completing the NPDES Permits and ESPCP plans, designing drawings attachments and submitting for approval, and waiting for comments revising and waiting for signature. Is this something you would do under temporary NTP so the time on construction doesn't start, since we have no contract over comments revisions and signatures?
Government Response: Erosion and Sedimentation Control Plans and approval are to be accomplished during the Work Plan creation part of the project.
RFI #12: Drawing C-1 Seems to show a specific area labeled for IRP. What data results locations, depths, analysis do you have on file already for this area?
Government Response: CERCLA Administrative Records concerning the Former Drum Storage Area at Building 408 are public information. Refer to RFI #2 Response for where to obtain this information.
RFI #13: Drawings C-3 Coded Note 12 States the underground primary line may interfere with properly grading "Replace Line if necessary" Our electrical subcontractor stated that during the site visit to encase the line in concrete. Please clarify what route you would like priced up for the bid. If you are enclosing in concrete, you should state strength and height and width and whether you need concrete under the conduits.
Government Response: Refer to attached revised Conceptual Drawing C-2 Detail 8, dated 18Sep25. A Primary Electrical Duct Bank detail was added here.
RFI #14: Drawings C-3..we understand your new 18" storm piping and the new inlet and rebuild of the two existing inlets. We not sure the details of the bottom elevations of the rebuild inlets and the size and elevations of the existing stormpipes which seem to be existing tying into these existing inlets. The left most rebuild inlet seems to have pipes coming in and out of this existing inlet and without sizes, directions of flow, elevations. We are not sure this inlet has the capacity to drain enough. We would like to see the existing Drawing in which your made your changes on top. Have you done calculations of volumes?
Government Response: Contractor is to determine this information in the Work Plan creation portion of the project.
RFI #15: Reference: Specification Section 01 10 00.00 06 – Work Restrictions Question: Section 01 10 00.00 06 (Work Restrictions) requires the contractor to provide a Superintendent, SSHO, and QC Manager. Please confirm whether these roles must be filled by three separate individuals or if one individual may serve multiple roles if properly qualified.
Government Response: This solicitation does not include Specification Section 01 10 00. The Conceptual Design Set Specification 01 14 00 Work Restrictions do not include this reference.
RFI #16: Reference: Solicitation / Bid Schedule Question: The solicitation establishes a period of performance of 180 calendar days. Please confirm whether this duration applies to the base scope only (CLINs 0001–0003).
Government Response: Per the solicitation, the PoP for CLINs 0001-0003 and 1001 -1010 is 263 Calendar Days, 10 Oct 2025 to 30 Jun 2026. The start date of 10 Oct 2025 is estimated until the Notice to Proceed (NTP) is issued. Per the Statement of Work (SOW), the 263 calendar days takes into account winter paving restrictions.
RFI #17: Reference: Solicitation / Bid Schedule Question: If one or more Option CLINs (1001–1010) are exercised, please confirm whether additional contract time will be provided through modification, or if the expectation is that all base and option work must be completed within the same 180-day period.
Government Response: Per the Statement of Work (SOW), all exercised options are to be completed within 55 (fifty-five) calendar days after receipt of the Notice to Proceed for each specified option. With the contract having a 263 calendar day period of performance, the contract PoP end date is currently planned as June 30, 2026. This end date is estimated and will be based on the Notice to Proceed on the Design. An extension to the contract period of performance end date, upon the option exercising, is not anticipated.
RFI #18 Reference: Conceptual Drawing Set – Sheet C-1 Notes Question: The conceptual drawings (Sheet C-1) state that survey information is approximate and soil suitability is assumed at 80%. Please confirm whether soil boring data is available for the project area. If no reports are available, please confirm that bidders may assume “normal” excavation/backfill with no rock unless otherwise noted.
Government Response: Refer to attached As-built drawing AD 39-01-13_Sheet 02 of 30_TEST BORINGS_1966FEB, Boring #8, #6, and #9 are within 150 LF of the New Storm Drain in the Conceptual Drawings. Attachment 9
RFI #19: Reference: Bid Schedule / Conceptual Notes Question: The bid schedule includes SF values for repair areas but does not provide breakout of deteriorated underlayment/base course quantities. Please confirm whether the Government has established baseline quantities for removal and replacement of base material, or whether bidders should carry their own assumptions subject to field-measured quantities after award.
Government Response: Unsuitable subgrade repair will be paid by the unit price in CLIN 0003. Refer to Conceptual Drawing C-2 for assumed locations and details for Subgrade Repair. Actual quantities will be determined in field by agreement between the government and contractor. The Solicitation contains FAR 52.211-18 Variation in Estimated Quantity. If quantities should require adjustment that were based on quantity take-offs from the issued contract, a modification as an equitable adjustment will be issued to finalize any overruns or underruns within the 15%. CLIN 003 is the only unit price item on this contract.
RFI #20: Reference: Specification reference – Allegheny County permitting Question: Specifications reference Allegheny County Health Department permitting for asbestos/abrasive blasting, but no testing results are provided. Please confirm whether asbestos-containing material (ACM) or lead-based paint (LBP) is present within the project limits, and if so, provide documentation to define required abatement scope.
Government Response: The government is not aware of ACM or LBP in this project’s scope of work.
RFI #21: Reference: Pre-bid Site Visit Record Question: Please provide the official sign-in sheet from the pre-bid site visit to confirm attendees.
Government Response: The Pre-Bid Site Visits Sign-In Sheets and Hand-Out Discussion Document is available as an Attachment on the Solicitation SAM posting. The link to the posting is -https://sam.gov/workspace/contract/opp/4d4be741a8fe432aaa8a34b61e72d04b/view
RFI #22: Reference: Government / Owner Question: Please provide Government photos of the job site and existing conditions for bidders who could not attend the site visit.
Government Response: See attached titled, Photos for RFI Responses dated 18Sep25. Attachment 10
RFI #23: Reference: Solicitation Terms Question: Please confirm whether this project is exempt from Pennsylvania state sales tax.
Government Response: Please reference FAR Clause 52.229-3 Federal, State, and Local Taxes. The contract price shall include all applicable Federal, State, and Local Taxes and Duties.
RFI #24: Reference: Conceptual Drawing Set – Sheet C-2 Notes Question: Sheet C-2 notes that approximately 20% of the subgrade is expected to be unsuitable when uncovered. Please confirm whether bidders should include 20% unsuitable subgrade repair with underdrain as a baseline assumption, or whether this will be paid based on actual measured conditions.
Government Response: Refer to RFI #19 Response.
RFI #25: Reference: Conceptual Drawing Set – Sheet C-1 IRP Notes Question: Sheet C-1 identifies portions of the work area within the IRP (former B408 Drum Storage) with potential hazardous contamination. Please confirm:
1. Whether the Government will perform or furnish the required pre-excavation soil sampling, or if this is the contractor’s responsibility.
2. If soils test hazardous, whether disposal at a TSDF will be handled under a contract modification or should be included in the base bid as an allowance.
Government Response: Contractor is responsible for pre-excavation soil sampling and disposal of hazardous materials. Refer to RFI #2 Response for additional information.
https://sam.gov/workspace/contract/opp/4d4be741a8fe432aaa8a34b61e72d04b/view
RFI #26: Reference: Conceptual Drawing Set – Sheet C-3 Utilities Question: Drawings show multiple active utilities (electric, storm, sanitary, gas, comms) in the work area.
Please confirm:
1. Whether relocation of active utilities is limited to Option CLIN 1001 (Relocate Primary Electric Duct Bank), with all other relocations handled as unforeseen conditions.
2. Whether shutdowns and tie-ins will be scheduled and coordinated through base CE by the Government.
Government Response: Conceptual Drawings include numerous work items that affect existing and new utilities.
The government’s intention is to adjust all utilities that impede the new grading in this area. The government will coordinate the shutdowns required for utility tie-ins, once requested by the contractor.
RFI #27: Reference: Conceptual Drawing Set – Sheet C-1 Question: Sheet C-1 requires the contractor to camera the storm drain system in the regraded area. Please confirm whether the contractor is responsible for cleaning/repairing all storm lines encountered, or only those portions to be incorporated into the final design.
Government Response: The contractor is to camera the storm drain system in the regraded area. Cleaning of the storm system during camera work will be required for proper evaluation of the system’s condition. The government’s intention is that the entire storm drain system in the regraded area will be eliminated, repaired, or replaced. This may not be possible for storm drains that cross the boundary in and out of the regraded area.
RFI #28: Reference: Conceptual Design Notes Question: The design notes reference a previously used sanitary sewer valve vault requiring removal and fill.
Please confirm whether:
1. Any residual equipment inside must be removed.
2. Contents require environmental testing prior to disposal.
Government Response: Refer to note on Conceptual Drawing C-1 and Coded Notes on Conceptual Drawing C-3 for information on Sanitary Vault. Pictures of this structure are provided in the attached Photos for RFI Response. This structure housed a valve that was part of an Oil Water Separator System. This work does not include removal of an Oil Water Separator.
RFI #29: Reference: Contractor/Visitor Access Memo (1 Jan 2025) Question: The Contractor/Visitor Access Memo (1 Jan 2025) requires DBIDS cards and possible escorts for entry into restricted areas. Please confirm whether escort services will be Government-furnished or whether contractors should include associated escort costs/time in their bids.
Government Response: If escort services are needed into restricted areas, the Government will provide the escorting.
RFI #30: Reference: Specification Section 01 – General Requirements Question: Please confirm whether the Government requires the GC to provide an on-site field office/trailer for contractor use.
Government Response: The government does not require a field office for the contractors or governments use.
RFI #31: Reference: Specification Section 01 14 00 – Work Restrictions Question: Section 01 14 00 states, “Restrooms are not provided by 911th Airlift Wing.” Please confirm whether the Government requires contractor-furnished restroom facilities to include only standard portable toilets, or if ADA-accessible units, wash stations, or climate-controlled trailers are also required.
Government Response: Contractor is responsible for providing standard sanitary restroom facilities for their own employees. The government does not have special requirements for these facilities.
RFI #32: Reference: Conceptual Drawing Set – Sheets C-2, C-5 / Bid Schedule Question: The conceptual drawings provide approximate SF areas (e.g., 38,500 SF seal coat and 700 SF mill & pave at Carter Street; 8,600 SF subgrade repair with underdrain) but do not provide breakout quantities for major items. For consistency of subcontractor/vendor pricing, please confirm Government-established bidding quantities or provide corrected values for:
1. Mill & overlay SF and assumed asphalt thickness.
2. Seal coat SF and assumed coverage rate (gal/SY).
3. Unsuitable subgrade replacement – confirm CLIN 0003 scope includes excavation, geotextile, stone, and underdrain.
4. Storm drainage – LF of pipe and number of inlets/catch basins to be replaced or added.
5. Striping/wheel stops – counts or confirmation that restriping is in-place of existing.
6. Crack sealing – baseline LF or assumed density.
If no baseline is available, please confirm that bidders may carry their own assumptions with the understanding that actual measured quantities will govern after award.
Government Response: Unsuitable subgrade repair will be paid by the unit price in CLIN 0003. CLIN 003 is the only unit price item on this contract. Refer to RFI #19 Response for additional information on unit price item.
RFI #33: Reference: Conceptual Drawing Set – Sheet C-2 Details Question: The conceptual drawings reference multiple pavement section details but do not clearly assign them to option areas. For example:
- Mill & overlay – remove 3.5", replace with 3.5" (1.5" wearing + 2" binder).
- Full-depth replacement – 10" subbase, 5" binder, 2" wearing.
- Seal coat – SF provided but no depth/thickness guidance.
Please confirm the intended pavement section depths for each option (Base and Options 1–10). If multiple sections may apply within an option, please indicate assumed percentages or limits of each.
Government Response: Refer to Legend – Paving Areas on Conceptual Drawing C-2. Additional information for Surface and Crack sealing is provided on the attached revised Conceptual Drawing C-5. Refer to revised Conceptual Drawing C-2 where the Asphalt Mill and Overlay was changed.
RFI #34: Reference: Bid Schedule / Utility Plans Question: Please clarify the intended scope of work for Option CLIN 1001 (Relocate Primary Electric Duct Bank). Should bidders assume a full remove-and-replace of existing duct bank in its current alignment, or will relocation/re-routing be required? Please confirm whether new manholes, splicing, or terminations are part of this CLIN.
Government Response: The government’s intention is for the contractor to modify this duct bank the minimum amount required to allow for the new pavement grading stated on Conceptual Drawing C-3. Modifications to duct bank should be done in accordance with industry standards as referenced in the Statement of Work.
RFI #35: Reference: Bid Schedule / Drainage Notes Question: Please clarify the required scope under Option CLIN 1002 (Repair Storm Drain Cross- Connection). Is this intended to include video inspection and minor excavation/repair, or should bidders assume installation of new storm piping?
Government Response: Refer to Coded Notes 10 and 11 on Conceptual Drawing C-3. Storm line installation for this item will be required.
RFI #36 Reference: Conceptual Drawing Set – Sheet C-4 (Striping) Question: Please confirm whether restriping under the option CLINs is limited to repainting existing striping layouts in place, or if upgrades to current ADA/UFAS standards (e.g., stall dimensions, signage, ramps) are required.
Government Response: Upgrades to parking and roadway line layouts are not intended under the Option CLINs.
RFI #37: Reference: Conceptual Design Notes Question: Conceptual drawings require a Preliminary Plan and a Final Plan to be submitted for Government approval. Please confirm Government review durations for each submission. Will the standard 30 calendar days apply, or is a shorter review period anticipated?
Government Response: Refer to section 1.4 in the Statement of Work. The government requires 21 calendar days for review of the Preliminary Work Plan. The planning purposes the government included 7 calendar days for review of the Final Work Plan, which assumes the Final Work Plan is acceptable as submitted.
RFI #38: Reference: Specification Section 01 / Pavement Notes Question: Seal coat and asphalt placement are typically limited by temperature thresholds. Please confirm whether seasonal/weather restrictions will allow schedule extensions if paving/seal coat work cannot be performed within the 180-day period of performance due to weather conditions.
Government Response: If the Period of Performance for asphalt and sealing work falls within the Weather Restriction period the contract will be extended.
RFI #39: Reference: Staging / Specification Section 01 Question: Are there designated staging and storage areas, or must the contractor secure off-site storage if the assigned area is insufficient?
Government Response: The government will provide sufficient reasonable outdoor space for contractor’s material/equipment storage. Location and size to be coordinated during Work Plan approval process.
RFI #40: Reference: Permitting / Specification Section 01 Question: Who is responsible to apply for, acquire, and pay for permits?
Government Response: The contractor is responsible for all necessary permits.
RFI #41: Reference: Testing / Specification Section 01 Question: Who is responsible to contract with geotechnical testing agencies and who is responsible for paying for any required testing.
Government Response: The contractor is responsible for all geotechnical investigation.
RFI #42: Are the necessary funds anticipated to be available at bid opening?
Government Response: At this time, funding will not be available at Bid Opening. If funds become available by September 30, 2025 or sooner, an award will be made.
RFI #43: Please confirm whether restroom facilities will be accessible to the crew or if temporary accommodations will be required.
Government Response: Reference Attachment 3 Conceptional Design Set Specifications, Section 01 14 00 Work Restrictions.
RFI #44: Can you identify which permits will be required for the scope of this project?
Government Response: The government will provide Hot Work Permits and Work Authorization Requests (Permit) as needed, all other permits required by other regulatory bodies are the responsibility of the contractor. Refer to Specification Sections 01 59 50 Safety Requirements and 00 41 00 Environmental Requirements for additional notification and coordination requirements (ie. Notify County Fire Department of Confined Space Entry). Local Township building permits are not required on this Federal Installation.
RFI #45: Are there any scheduled site shutdowns, holidays, or special event restrictions?
Government Response: Reference Attachment 3 Conceptional Design Set Specifications, Section 01 14 00 Work
RFI #46: Are permits required? If so, who is responsible?
Government Response: The government will provide Hot Work Permits and Work Authorization Requests (Permit) as needed, all other permits required by other regulatory bodies are the responsibility of the contractor. Refer to Specification Sections 01 59 50 Safety Requirements and 00 41 00 Environmental Requirements for additional notification and coordination requirements (ie. Notify County Fire Department of Confined Space Entry). Local Township building permits are not required on this Federal Installation.
RFI #47: Is there a designated area for material/equipment storage?
Government Response: The government will provide sufficient reasonable outdoor space for contractor’s material/equipment storage. Location and size to be coordinated during Work Plan approval process.
RFI #48: What are the working hours?
Government Response: Reference Attachment 3 Conceptional Design Set Specifications, Section 01 14 00 Work
RFI #49: Please confirm thickness of wearing course for mill & overlay?
Government Response: Conceptual Drawings have been revised to include 2” thickness of mill and overlay. Refer to revised Conceptual Drawing C-2.
RFI #50: Please confirm how many coats of sealant are required & provide a product specification.
Government Response: Conceptual Drawings have been revised to provide additional sealing information. Refer to revised Conceptual Drawing C-5.
RFI #51: What is required for the crack filling?
Government Response: Conceptual Drawings have been revised to provide additional crack sealing information.
Refer to revised Conceptual Drawing C-5.
RFI #52: What is the required method of eradicating the paint lines on the existing concrete & asphalt surfaces?
Government Response: All painted lines no longer required should be completely removed. Method of removal to be specified in the Work Plan.
RFI #53: Please provide photos of all areas of new work.
Government Response: Refer to attachment titled Photos for RFI Responses.
RFI #54: Can more information be provided on contaminated soils?
Government Response: Refer to RFI #2 Response.
RFI #55: Is it the governments intent that the work for any awarded options be performed immediately following the based bid project, or are the base bid project and options to be performed concurrently?
Government Response: The government does not require one or the other.
RFI #56: At the initial pre-bid site visit, it was mentioned that photographs of the existing electrical duct bank (that may need relocated per Option 1) may exist. Can those photos or any as-built documentation for that duct bank be provided to the contractors for bidding?
Government Response: Refer to attachment titled Photos for RFI Responses. The As-Built drawings for the Primary Electric Line duct bank in question shows concrete encasement and a depth of 30” from surface to top of concrete encasement. The attached photo does not appear to confirm this depth is accurate.
-End of RFIs-