This Statement of Work (SOW) details a pavement repair project for the Pittsburgh Air Reserve Station (ARS) in Pennsylvania, focusing on Sabre Street and potential optional repair areas. The base bid involves comprehensive pavement rehabilitation between Buildings 129 and 130 and along Building 420, including demolition of existing asphalt, utility modifications, storm drainage system installation, and new paving with proper grading. The project requires extensive site investigation, hazardous waste management planning, and environmental compliance, with soil sampling and testing mandatory in the Non-Residential Use Installation Restoration Program (IRP) site area.

The project is divided into two primary tasks: Task 1 involves developing detailed work plans with preliminary and final submissions, including AutoCAD drawings and professional engineering review, while Task 2 focuses on actual construction implementation. Optional contract areas include pavement mill and overlay or seal coating for multiple additional parking lots and street sections. Critical requirements include completing the base project within 60 calendar days after work plan approval, performing asphalt paving only between April 1 and November 1, and adhering to various federal, state, and local regulatory standards. The total project performance period is 263 calendar days, with a projected design notice to proceed on 10/10/2025.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Repair Sabre Street Pavement Project Number JLSS 25-0004

PITTSBURGH IAP ARS, PA

26 August 2025

1.1 BACKGROUND

The portion of Sabre Street between Buildings 129 and 130 and the section along Building 420 was last maintained by milling and installing an asphalt overlay in 2005.

Overall, these paving areas were rated as Poor or Fair in 2021 during the last Pavement Condition Index (PCI) survey. Last winter during the coldest days of the year several areas were showing uplifting and differential settlement, creating a situation where the asphalt can be ripped apart by snowplows catching these edges. This situation indicates the excessive surface cracking is allowing water to enter the subbase and subgrade causing them to fail. Because of improper pavement sloping in this area, the water is becoming trapped under the pavement. Because of the severity of this damage the entire pavement system (including aggregate subbase) must be replaced in order to properly support any new layers of asphalt placed here.

1.2 SCOPE OF WORK

A. Provide a complete Work Plan for the repair of the asphalt pavement on Sabre Street as described in the following sections. Work Plan to have a Preliminary Submittal, Final Submittal, be created in AutoCAD, include relevant specifications, and be stamped by a professional engineer licensed in the state of Pennsylvania.

B. Test the Material/Soil located in the Non-Residential Use Installation Restoration Program (IRP) (refer to drawing C-1) site area to determine if/what contaminates are present and prepare a Hazardous Waste Management Plan in accordance with Conceptual Drawings and Specification, stating how work will be performed in this area. Required Minimum Sampling to include: TCLP RCRA metals and mercury, TCLP VOCS, TCLP SVOCS, TCLP pesticides, TCLP herbicides, pH/corrosivity, Flash Point, Reactivity (sulfide and cyanide), Oil & Grease or TPH, PCBs, TOX, and Free Liquids.

C. The contractor shall repair the asphalt pavement system on Sabre Street and, if awarded, repair optional pavement areas at Building 419 Drive, Building 415 Parking Lot, Building 208/209/210 Parking Lot (Lot E), Building 125 Parking Lot, Carter Street, Building 120 Parking Lot, Upper Defense Avenue & Sergeants Way, and Alpha Street & Herman Avenue. Guidance for this design is shown on the attached Conceptual Drawings C-1, C-2, C-3, C-4, C-5, and Conceptual Specification and as described below.

1. Sabre Street – Base Bid

a. Demolish and dispose (as per work plan) of existing asphalt paving, subbase, soils, storm drain structures, utilities and other miscellaneous obstructions in this area.

b. Locate and modify existing utilities in this area which obstruct construction. This includes but is not limited to raising/lowering valve boxes, manholes, and inlet structures. Water, Electric, Sewer, Communications and Gas lines run through this site, which must be addressed on the Work Plans. The Contractor is responsible for verifying all utility locations prior to beginning work. The use of a Utility Locating Service who uses ground penetrating radar is recommended. Pennsylvania One-call system (Pennsylvania 811) does not cover the utilities on base.

c. Install new storm drainage system for pavement between buildings 129 and 130 which will include piping, inlets, and manholes needed to convey water to existing collection system. Connect roofing downspouts and miscellaneous drainage to existing collection system. The government’s intent is to remove as many of the storm structures as possible, especially the redundant and abandoned structures. The Contractor is to ensure connections to existing storm water generating sources are maintained and they remained tied into the existing storm water system.

d. Per 25PA Code Chapter 102 - Projects with Earth Disturbance must develop and implement Erosion and Sedimentation Control Plans.

i. Projects with earth disturbance between 5,000 square feet and 0.99 acres must develop, implement, and maintain a project specific Erosion and Sedimentation Pollution Control Plan (ESPCP). The plan must be submitted to Allegheny County Conservation District (ACCD) for approval and municipality/county notification forms should be completed.

ii. Project with earth disturbance greater than 1 acre are also required to acquire a National Pollutant Discharge Elimination System Permit (either PAG-02 or individual permit) through ACCD including but not limited to: the development and implementation of a Post Construction Storm Water Management Plan (PCSMP), E&S Plan, Notification Forms, Notice of Intent, etc.

e. Perform all earthwork necessary for establishing a minimum 2% grade in full depth replacement areas. A portion of this excavation is located in an IRP site which has previously tested positive for contaminated soil. The contractor is to meet the requirements stated on Conceptual Drawing C-1 for this work.

f. Most existing subbase in this area consists of slag material. Properly dispose of any slag material that is not being reused as subgrade. Per drawing set GTP 850-073 Overlay Base Roads Dated 31 March 2004 the typical existing pavement section on the base generally includes 5” +/-asphalt and 10” +/- of aggregate subbase (slag).

g. Install new paving system in areas laid out on Conceptual plans. Paving to consist of a combination of full depth repair and mill and overlay areas.

h. Install crack and surface sealing in areas laid out on Conceptual plans.

i. Remove and replace chain link fence and gate or guardrail as shown on Conceptual drawings at southwest corner of Building 130.

j. Install new bollards and concrete median barrier as shown on Conceptual drawings in vicinity of Building 129.

k. Paint parking lot striping to establish parking spaces, handicap parking spots, install wheel stops, and other traffic control requirements.

2. Contract Option 1 - Relocate Primary Electric Duct-bank – Refer to coded notes on Conceptual Drawing C-3. Northeast corner of Building 130, duct-bank is to be modified to allow proper sloping of the pavement.

3. Contract Option 2 - Repair Storm Drain Cross Connection - Refer to coded notes on Conceptual Drawing C-3. Northeast corner of Building 130, Storm sewer flows to an unknown location. Once investigative tasks are performed determine how to tie this storm sewer into the existing system properly.

4. Additional Contract Options - Asphalt Mill and Overlay – This work is to include milling of existing asphalt and replacement with an overlay. Associated work is to include placement of concrete collars around existing manholes and inlets, sealing of pavement edges and all joints, and replace pavement marking disturbed by this work.

a. Option 3 - Building 419 Parking

b. Option 5 - Building 208/209/210 Parking Lot (Lot E)

c. Option 6 - Building 125 Parking Lot

5. Additional Contract Options - Seal Coat – use a rejuvenating sealer on newer asphalt and sand sealer on older areas, replace the pavement markings that are disturbed by this work.

a. Option 4 - Building 415 Parking Lot

b. Option 7 - Carter Street

c. Option 8 - Building 120 Gym Parking Lot

d. Option 9 - Upper Defense Avenue & Sergeants Way

e. Option 10 - Alpha Street & Herman Avenue

6. Maintenance and Protection of Traffic will be required to protect workers and base employees during all construction activities, provide details on how this will be accomplished in the work plans.

D. The scope of work has been organized into two (2) discrete tasks.

Task 1: Complete a design and work plan. Including Hazardous Waste Management Plan.

Task 2: Construct and make operational, all improvements as defined in the scope of work in this project.

1.3 REFERENCES

A. All references to and citing of government and industry standards and codes must show the date of the reference used. It is not acceptable to state “use of latest or current issue” or state “install per code” in lieu of delineating portions of the code in application to installations, assemblies, and materials. All work shall be in accordance with the latest versions of the following; however, final determinations of code compliance shall be made by the Base Civil Engineer.

1. All DoD Unified Facility Criteria see http://www.wbdg.org and any Air Force Engineering Technical Letters (ETL) see http://www.e-publishing.af.mil

2. Military Handbook 1013/10

3. Allegheny County Plumbing Code

4. EPA and PA DEP Regulations

5. International Building Code

6. PA Dept of Labor & Industry

7. National Electrical and Plumbing Codes,

8. NFPA Codes

9. Applicable industry standards such as ASHRAE and ASME.

10. Erosion and Sedimentation (E&S) procedures must be utilized for any ground disturbance and soil stockpiles.

1.4 TASK 1: DEVELOP WORK PLANS

A. The Preliminary and Final Work Plans shall be sent to the Contracting Officer. These work plan drawings shall be well prepared, complete, and accomplished in accordance with the best professional practice to show clearly and concisely the type and extent of work to be performed based on the contract scope of work. These drawings shall be produced in AutoCAD. The project title sheet shall have an index that lists the sheet number, sheet name, and CAD file name of each drawing in the set.

B. Site Investigation to be performed by the contractor to facilitate creation of the Preliminary and Final Work Plans. Site Investigations may include Professional Survey, Camera Inspection of Piping Systems, Ground Penetrating Radar to locate buried utilities, soil sampling and geotechnical investigation to the extent necessary to create complete and accurate work plans.

C. The Project Conceptual drawings include 0.9 acres of earth disturbance which includes the full depth repair areas. Do not exceed this amount in the provided Work Plans. The definition of "disturbed area" on a project includes all areas disturbed, including lay down and staging areas, site access, etc., that require earthwork to facilitate. The government will provide a paved area for staging equipment if necessary.

D. Final Work Plan to include a Hazardous Waste Management Plan. No on-site construction work will be allowed until this plan is accepted by the government.

Sampling and testing of the material/earth in the IRP Site area is to be done as part of the development of the Work Plans. Soil sample results shall be provided to base environmental staff for review.

http://www.wbdg.org/ http://www.e-publishing.af.mil/

E. Preliminary and Final Work Plan Delivery Schedule. The Preliminary Work Plan will be submitted within 45 days after the Contracting Officer issues the Notice to Proceed (NTP). Government review comments on the Preliminary Work Plan will be forwarded to the contractor within 21 calendar days after the date of receipt. The Final Work Plan will be submitted 21 calendar days after government comments are returned to the contractor. If all the government comments on the Preliminary Work Plan are not adequately addressed, the Final Work Plan will be returned to the contractor for corrections. Task 2 may not begin until the Government accepts the Final Work Plan from the Contractor.

1. Included in the Preliminary and Final Work Plan shall be drawings and specifications according to the site investigation activities and based on the Conceptual Drawings and Specifications (See Attachments).

2. The Preliminary Work Plan shall provide at least enough detail which is equivalent to a 50% Architectural-Engineering design.

3. The Final Work Plan shall provide at least enough detail which is equivalent to a 100% Architectural-Engineering design. The Final Work Plan drawings shall be stamped and signed by a registered professional architect/engineer in Pennsylvania and include the Erosion and Sedimentation Control Plan with approval documentation from Allegheny County Conservation District.

4. The drawings shall include the standard 911th signature block in the lower right-hand corner.

F. Construction Schedule. The contractor shall provide a detailed Construction

Schedule as part of the Preliminary Work Plan submittal. The contractor shall incorporate the following requirements in Construction Schedule.

a. All construction items in the base project (Sabre St) are to be completed within 60 (sixty) calendar days after government approval of Final Work Plan.

b. All exercised options are to be completed within 55 (fifty-five) calendar days after receipt of the Notice to Proceed for the identified option(s).

c. Asphalt paving is only to be performed between April 1 and November 1.

d. The 263 calendar day period of performance assumes a Design Notice to

Proceed of 10/10/2025 and accounts for specified winter paving restrictions.

G. Final documents will eventually serve as the basis for as-built documentation of the project and shall be provided electronically including the following:

1. All updated Final Work Plan AutoCAD drawing files (Drawings must be saved in compatible version with 2020 AutoCAD system – Contractor shall coordinate with Contracting Officer prior to submission).

2. All updated Final Work Plan (100%) drawings in .pdf format.

3. All analyses performed for design in .pdf format.

4. Entire compilation of specifications or Catalog Cut Sheets in .pdf format to clearly define types of materials and products used in Task 2.

1.5 TASK 2: CONSTRUCT IMPROVEMENT

A. The contractor shall install improvements as per the Contracting Officer, approved in the Final Work Plan. Permitted deviations from the government-approved Final Work Plan, due to unforeseen/undocumented field conditions, shall be brought to the attention of, and approved by, the Contracting Officer before any changes are made in the field during construction.

B. Construction activities will take place in the area shown in the Final Work Plan. The contractor shall coordinate construction activities with the Contracting Officer to ensure that the primary mission of Pittsburgh ARS is not compromised at any time during construction.

C. Contractor is responsible for all Federal, State, and Local permitting requirements required to complete this work.

D. All installation of materials shall be per manufacturers’ recommendations; UFC guidance; federal, state, and local building and electrical code requirements.

E. Contractor shall provide as-built drawings in AutoCAD format, and specifications for the completed work on the project.

ATTACHMENTS

1. Project Conceptual Drawings (6 Sheets) Dated 30 June 2025

2. Project Conceptual Specifications Dated 30 June 2025

***END OF STATEMENT OF WORK***