REQUEST FOR INFORMATION / CLARIFICATION FORM
FOR CONTRACTOR USE ONLY
CONTRACT NO:
DDPM 160001
RFI NO: IES-03 DATE (YYYYMMDD)
2015/08/22
SUBJECT:
Secondary Feeders
DRAWING REFERENCE/ DETAIL:
SOW 3.8
ATTACHMENT SENT UNDER SEPARATE
COVER(__)
RESPONSE NEEDED BY:ASAP
REQUEST:
SOW section 3.8 does not address existing underground or aerial secondary feeders.
PROPOSED SOLUTION (If applicable):
Provide clarification as to whether the existing secondary feeders are to remain for reuse.
TO(Contracting Officer): 301 CONF/LGC
FROM (Contractor):
Izoro Electrical Systems inc.
DATE (YYYYMMDD)
2015/08/22
TYPE OR PRINT NAME AND TITLE
Samuel Blakley/General Manager
SIGNATURE:
FOR GOVERNMENT USE ONLY
FROM CONTRACTING TO:
BCE: Charles Tehan (__); Robert Dudley(__; OR OTHER(__)
For Evaluation and Action
DATE (YYYYMMDD) TYPE OR PRINT NAME AND TITLE SIGNATURE:
RFI RESPONSE / CLARIFICATION (refer to page 2)
RFI RESPONSE / CLARIFICATION:-
Government to complete following sections:
1191522202C Typewritten Text X
1191522202C Typewritten Text
1191522202C Typewritten Text 20150824
1191522202C
Ron Pyles, Contract Admin
REQUEST FOR INFORMATION / CLARIFICATION FORM
TO: AF Contractiing Office From Responding Agency
TO:(Contractor from Contracting Officer
CONTRACTOR REVIEW
After reviewing the Government response, does the contractor anticipate A change order will be required? YES NO There will be an increase in the cost of the project? YES NO
Reviewer:
*Contractor- return reviewed form to Contracting Officer. Should the review results in YES for either of the two questions, if any further action is required by the contractor (i.e. submission of change proporsal), they will be notified by the contracting office.
1101986434C
1101986434C Typewritten Text The disconnect on the outside of Building 1344 is wired for 200A, 3-phase, 120/208V. The secondary service feeding the facility shall be adequate for the 200 Amp service, but not the 400 Amp service described in paragraph 3.8.12. Therefore, the Statement of Work shall be modified to read new 200A disconnect rather than a 400A disconnect. The secondary feed coming in cannot handle a 400A service.
1101986434C Typewritten Text 20150825
1101986434C Typewritten Text Charles D. Tehan, GS-11, USAFR Engineering Technician, 301 MSG/BCE
1101986434C Typewritten Text
1376454971C Typewritten Text 20150825
1376454971C
Yvette Todtenhoefer, Contracting Officer
| 2015-08-24T07:20:43-0500 | |
| PYLES.RONALD.GENE.1191522202 |
| 2015-08-25T16:08:13-0500 | |
| TEHAN.CHARLES.D.1101986434 |
| 2015-08-25T17:30:09-0500 | |
| TODTENHOEFER.YVETTE.1376454971 |
File details come from the government source that posted it. Updated .