REQUEST FOR INFORMATION / CLARIFICATION FORM
FOR CONTRACTOR USE ONLY
CONTRACT NO:
RFI NO: 0001 DATE (YYYYMMDD)
20150804
SUBJECT:
Solicitation FA6675-15-R-0004
DRAWING REFERENCE/ DETAIL:
ATTACHMENT SENT UNDER SEPARATE
COVER(__)
RESPONSE NEEDED BY:
REQUEST:
Referencing the SF 1442 and FAR 52.228-1 on page 17 of 50.
Both of these references indicate a Bid Bond is required. However, the Section L requirements do not indicate a bid bond is to be submitted.
Also, if a bid bond is required, is an SF 24 acceptable?
PROPOSED SOLUTION (If applicable:
Amend the solicitation at the appropriate location (SF 1442/Section I or Section L) to clarify if or where a Bid Bond is to be submitted.
TO(Contracting Officer): 301 CONF/LGC
FROM (Contractor):
Dakota Meyer Enterprises, Inc.
DATE (YYYYMMDD)
20150804
TYPE OR PRINT NAME AND TITLE
John P. Feiler, Technical Writer
SIGNATURE:
//SIGNED//
FOR GOVERNMENT USE ONLY
FROM CONTRACTING TO:
BCE: Charles Tehan (__); Robert Dudley(__; OR OTHER(__)
For Evaluation and Action
DATE (YYYYMMDD) TYPE OR PRINT NAME AND TITLE SIGNATURE:
RFI RESPONSE / CLARIFICATION (refer to page 2)
REQUEST FOR INFORMATION / CLARIFICATION FORM
RFI RESPONSE / CLARIFICATION:-
Government to complete following sections:
The bid bond is required and should be submitted with your proposal on the SF24.
We will not amend the solicitation as the clause is clear that the bid bond should be furnished.
TO:(AF Contractiing Office)
DATE (YYYYMMDD)
TYPE OR PRINT NAME AND TITLE
SIGNATURE:
TO:(Contractor from Contracting Office)
DATE (YYYYMMDD)
20150804
TYPE OR PRINT NAME AND TITLE
Ron Pyles, Contracting
SIGNATURE:
CONTRACTOR REVIEW
After reviewing the Government response, does the contractor anticipate A change order will be required? YES NO There will be an increase in the cost of the project? YES NO
Reviewer:
DATE (YYYYMMDD) TYPE OR PRINT NAME AND TITLE SIGNATURE:
*Contractor- return reviewed form to Contracting Officer. Should the review results in YES for either of the two questions, if any further action is required by the contractor (i.e. submission of change proporsal), they will be notified by the contracting office.