This document is a Statement of Work (SOW) for a federal contract opportunity for an OWS STI Inspection at Niagara Falls Air Reserve Station. The key details are:
The contractor shall furnish all necessary material, equipment, labor, and services to perform an STI-SP001 Out of Service Inspection on a 10,000-gallon oil water separator underground storage tank. This includes removing water/sludge, pressure washing, conducting mechanical leak tests, and providing an inspection report. Environmental compliance requirements are specified, including proper disposal of waste materials. The contractor must submit an Activity Hazard Analysis and coordinate with base authorities prior to any work or entry.
The related federal contract opportunity is a Request for Quotation (RFQ) solicitation under FAR 12.6 for commercial services, with a NAICS code of 541380. The government intends to award a single firm-fixed price contract to the lowest priced, technically capable offeror. Responses are due by 7 June 2024. This is a 100% small business set-aside.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
For Task Order
RVKQ 24-0001 B919 OWS STI Inspection
21 January 2024
1. SUMMARY OF WORK: The Contractor shall furnish and install all material, equipment, components, parts, tools, labor, transportation, hauling, disposal/recycling, cleaning, inspection, testing, commissioning, training, reporting, etc., necessary to perform this project as described in the contract-delivery order, including this Statement of Work and any / all applicable federal, state and local laws, regulations, and standards. Unless otherwise stated, any / all requirement for contractor to remove and properly dispose of / recycle off base, and to furnish and install / incorporate any / all new materials / equipment / components needed to properly complete the work item; any Government furnished property and / or reinstallation of existing materials / equipment / components shall be as stated / specified herein. Contractor shall submit materials / methods for approval prior to ordering and / or incorporation into the work; at a minimum, submittals shall include product literature, SDS, standard color, texture and style samples / swatches / boards, and place of origin / manufacture. Demolished materials, waste / debris is property of the contractor, unless otherwise stated herein; contractor is responsible for proper disposal / recycling of such materials off base; such materials shall be promptly removed from the installation and shall not be stored / stockpiled unless submitted and approved for such. Contractor is responsible for verification of all details, measurement, etc., prior to ordering materials and execution of work.
2. Conduct a certified STI-SP001 Out of Service Inspection at B919’s 10K gallon oil water separator underground storage tank. Included shall be a leak test to ensure isolation valves and all mechanical components are operational.
3. Remove existing water/sludge that is in the tank with vacuum trucks. Pressure (jet) wash inlet and discharge piping to the OWS. See section 9 below for disposal of all hazardous material. After removal of all water/sludge, enter the tank, pressure wash the walls and floor, vacuum out material as needed for inspection.
4. Conduct STI Inspection. After STI inspection is complete, conduct a mechanical leak test by manually shutting the isolation valves and filling the OWS with water. Conduct 4-hour leak
914 MSG / CEC
Niagara Falls Air Reserve Station 2405 Franklin Drive Niagara Falls, New York 14304-5063 test and ensure mechanical isolation valves are functioning as designed and there are no fluids leaking by.
5. After all inspection and operational testing is completed, contractor is to provide the installation with a formal STI-SP001 Engineering Inspection Report.
6. Contractor shall provide an Activity Hazard Analysis (AHA) to include a confined space entry (Permit Required), Control of Hazard Energy, General Safety Requirements.
7. Prior to any work or entry, the contractor shall coordinate with base Fire, Safety and
Bioenvironmental office to ensure confined space entry procedures and all safety procedures are followed and all permits are valid.
8. Prior to mobilization, the contractor shall obtain all necessary permits, clearance for radiation/x-ray equipment from the base. X-Ray equipment shall not be brought on base without prior approval.
9. Environmental Protection
9.1. Collect, containerize and properly dispose of all waste materials generated from the project off base.
9.2. Ensure the work area is clean and free of all debris at the end of each workday.
9.3. The Contractor shall be responsible for following the base sampling results for characterization, storage, describing packaging, labeling, marking and placarding of waste. The Contractor shall characterize the waste as required by the disposal facility. Any analytical results shall be forwarded to 914 MSG/CEV for review and approval. Waste shall not leave the base until approval has been obtained from 914 MSG/CEV. It is anticipated the waste will be characterized as non-hazardous. The Contractor shall manifest, pack, ship and dispose of all waste in compliance with Federal, State and local laws and regulations.
9.4. Comply with Base standards for storage of hazardous materials. Bulk materials and wastes must be secured and stored under cover. Maintain supplies on hand to contain and cleanup any spills generated by the Contractor’s activities. Report any spills to the Base Environmental office in accordance with Base’s HAZMAT Plan.
9.5. Contractor is to recycle or divert as much waste as practical.
9.6. The Contractor must submit the Waste / Recycle Materials Log for Contractors with a list of materials disposed and recycled.
9.7. Green Purchasing: The Contractor shall comply with the Green Purchasing requirements of the contract. Known / possible EPA Comprehensive Procurement Guideline, USDA Biobased, Green Seal Energy Star, etc., items. Recycled materials must be used to fullest extent in accordance with Executive Order 13101.
The EPA web-site, http://www.epa.gov/cpg, can be accessed for further instruction on what is an EPA-designated material.
10. Submittals
10.1. In addition to any submittals required by the general contract, provide the following project specific submittals for government review and approval:
10.1.1. Work Schedule
10.1.2. Waste Logs
http://www.epa.gov/cpg