SOW 24 Feb 09.pdf
PDF 23 KB Posted
- Attached to
- Replace 15KV Cutout Switches, Basewide Federal contract opportunity
- Solicitation number
- FA6670-10-B-0001
About this file
Specifications RVKQ 09-0324 Scope of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Davis Bacon Decision NY100012 dated 9 April 2010.pdf | ||
| FA6670-10-B-0001 Amendment 0001.pdf | ||
| Site Visit Questions and Answers.pdf | ||
| Submittal List.pdf | ||
| Base Electric Map.pdf | ||
| OVERHEAD TRANSMISSION AND DISTRIBUTION.pdf | ||
| NY100012 dated 12 Mar 2010.pdf | ||
| AF3000.pdf | ||
| 15kc Switch.PDF | ||
| BASIC ELECTRICAL METHODS.pdf | ||
| Submittal Procedures.pdf | ||
| Sources For Reference Publications.pdf | ||
| Table of Contents.pdf | ||
| FA6670-10-B-0001.pdf | ||
| APPARATUS INSPECTION AND TESTING.pdf | ||
| OPERATION AND MAINTENANCE.pdf | ||
| Cover Page.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RVKQ 09-0324 Replace 15kv Cutout Switches
Section 01 11 00
24 February 2009
SUMMARY OF WORK
RVKQ 09-0324
REPLACE 15 KV CUTOUT SWITCHES
BASEWIDE
DESCRIPTION OF PROPOSED REPLACEMENT:
1.) Provide all material and labor to repair and upgrade the existing utility poles and overhead distribution systems as noted below.
a. Pole 13 Needs Insulator for High Voltage Wire,
b. Pole 16 - Needs Insulator for High Voltage Wire , Need pin connector installed for water in secondary,
c. Pole 19 - Needs Insulator for High Voltage Wire
d. Pole 30 - Needs Pin Terminal, Water in Secondary
e. Pole 40 - Needs Insulator for High Voltage Wire
f. Pole 42 – Replace load break cutout ( Sectionalizers)
g. Pole 43-3 - Tighten Triplex
h. Pole 45 – Replace load break cutout ( Sectionalizers)
i. Pole 60 - Needs Insulator for High Voltage Wire, Water in Secondary
j. Pole 64 - Tighten Triplex
k. Pole 65 - Needs Pin Terminal, Water in Secondary
l. Pole 66 – Replace load break cutout ( Sectionalizers)
m. Pole 67- Replace load break cutout ( Sectionalizers)
n. Pole 68-1 – Replace Pole
o. Pole 74-1 - Water in Secondary
p. Pole 78- Replace load break cutout ( Sectionalizers)
q. Pole 99- Replace load break cutout ( Sectionalizers)
r. Pole 105- Replace load break cutout ( Sectionalizers)
s. Pole 105-4 - Replace Pole
t. Pole 105-5 - Straighten Pole/ Install guy
u. Pole 105-6 - Replace Pole
v. Pole 110 - Needs Pin Terminal, Water in Secondary
w. Pole 112 - Needs Insulator for High Voltage Wire, Needs Pin Terminal, Water in Secondary
x. Pole 123 - Resag Triplex
y. Pole 123-1 - Replace Pole
z. Pole 123-2 - Resag Triplex
aa. Pole 129 - Needs Pin Terminal, Water in Secondary
bb. Pole 132-4 - Replace Pole
cc. Pole 132-6 - Straighten Pole/ Install guy
RVKQ 09-0324 Replace 15kv Cutout Switches
dd. Pole 132-7 - Straighten Pole/ Install guy
ee. Pole 132-8 - Straighten Pole/ Install guy
ff. Pole 135 - Needs Pin Terminal, Water in Secondary
gg. Pole 136 - Needs Pin Terminal, Water in Secondary
hh. Pole 138 - Needs Pin Terminal, Water in Secondary, Replace load break cutout ( Sectionalizers)
ii. Pole 139 - Replace load break cutout ( Sectionalizers)
jj. Pole 143 – Broken tie wire
kk. Pole 143-1 - Reposition Triplex / Rubbing on Guy, Replace broken tie wire on insulator
ll. Pole 156 - Needs Pin Terminal, Water in Secondary
mm. Pole 161- Replace load break cutout ( Sectionalizers)
2.) Provide all material and labor to upgrade the existing electrical 15 KV cutouts and lighting arrestors that has metal support hardware from utilities poles base wide.
Removal of all existing cutout and lighting arrestors and metal support brackets from poles base wide. Install new wood cross arms with existing 100 ampere, open style, 15
KV cutouts and 10 KV lightening arrestors. Install proper grounding on all poles that upgraded and provide ground resistance test results for each pole that is upgraded.
a. Pole 13
b. Pole 14
c. Pole 16
d. Pole 17
e. Pole 19
f. Pole 21
g. Pole 24
h. Pole 25
i. Pole 31
j. Pole 34
k. Pole 37
l. Pole 40
m. Pole 46
n. Pole 51
o. Pole 60
p. Pole 65
q. Pole 67
r. Pole 72
s. Pole 73
t. Pole 74-1
u. Pole 80
v. Pole 97
w. Pole 99
x. Pole 104
y. Pole 110
z. Pole 111
aa. Pole 112
bb. Pole 114
cc. Pole 117
dd. Pole 121
ee. Pole 126
ff. Pole 130
gg. Pole 132
hh. Pole 135
ii. Pole 136
jj. Pole 139
kk. Pole 144 (2)
ll. Pole 146
mm. Pole 156
3.) Provide all material and labor to upgrade the existing utilities pole electrical components.
Replace fiberglass high voltage support arms with wooden cross arms, pins and insulators.
a. Pole 6
b. Pole 7
c. Pole 9
d. Pole 10
e. Pole 11
f. Pole 12
g. Pole 13
h. Pole 14
i. Pole 43
j. Pole 46
k. Pole 53
l. Pole 64
m. Pole 68
n. Pole 69
o. Pole 70
p. Pole 72
q. Pole 120
r. Pole 121
s. Pole 122
t. Pole 125
u. Pole 126
v. Pole 128
w. Pole 130
x. Pole 134
RVKQ 09-0324 Replace 15kv Cutout Switches
y. Pole 18
z. Pole 19
aa. Pole 22
bb. Pole 23
cc. Pole 26
dd. Pole 28
ee. Pole 30
ff. Pole 31
gg. Pole 33
hh. Pole 34
ii. Pole 37
jj. Pole 38
kk. Pole 39
ll. Pole 40
mm. Pole 41
nn. Pole 73
oo. Pole 74
pp. Pole 79
qq. Pole 95
rr. Pole 98
ss. Pole 101
tt. Pole 103
uu. Pole 106
vv. Pole 107
ww. Pole 108
xx. Pole 110
yy. Pole 112
zz. Pole 116 aaa. Pole 117 bbb. Pole 118 ccc. Pole 135 ddd. Pole 136 eee. Pole 137 fff. Pole 140 ggg. Pole 145 hhh. Pole 150
iii. Pole 151 jjj. Pole 154 kkk. Pole 155 lll. Pole 156 mmm. Pole 157 nnn. Pole 158 ooo. Pole 159 ppp. Pole 160
4.) Replace all 8 foot fiberglass insulator guide wire extensions with 12 foot fiberglass insulator guide wire extensions. All poles with guy wires shall have a 12 foot fiberglass insulator guide wire extensions installed.
5.) All work shall meet the National Electrical Code, current edition.
6.) All work shall be coordinated with base maintenance personnel, base civil engineering personnel and facilities personnel that will be affected.
7.) Provide four copies of any manufactures technical/support documentation to include all testing certifications and preventative maintenance for all electrical components.
8.) All electrical materials for this project will require submittals and acceptance by 914 th
Civil Engineer Section in accordance with Section 01330.
9.) On completion of the project vender shall provide as built/update of base drawing G-4
(Electrical Distribution System).