APPARATUS INSPECTION AND TESTING.pdf

PDF 73 KB Posted

Attached to
Replace 15KV Cutout Switches, Basewide Federal contract opportunity
Solicitation number
FA6670-10-B-0001
Issued by
Department of the Air Force Reserve Command

About this file

Specifications RVKQ 09-0324 Apparatus Inspection and Testing

View the file

Other files for this federal contract opportunity

Other files attached to Replace 15KV Cutout Switches, Basewide, newest first.
File Type Posted
Davis Bacon Decision NY100012 dated 9 April 2010.pdf PDF
FA6670-10-B-0001 Amendment 0001.pdf PDF
Site Visit Questions and Answers.pdf PDF
Submittal List.pdf PDF
Base Electric Map.pdf PDF
OVERHEAD TRANSMISSION AND DISTRIBUTION.pdf PDF
NY100012 dated 12 Mar 2010.pdf PDF
AF3000.pdf PDF
15kc Switch.PDF PDF
BASIC ELECTRICAL METHODS.pdf PDF
Submittal Procedures.pdf PDF
Sources For Reference Publications.pdf PDF
Table of Contents.pdf PDF
FA6670-10-B-0001.pdf PDF
OPERATION AND MAINTENANCE.pdf PDF
SOW 24 Feb 09.pdf PDF
Cover Page.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RVKQ090324 CUTOUTS

SECTION 26 08 00 Page 1

SECTION 26 08 00

APPARATUS INSPECTION AND TESTING

08/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)

NETA ATS (2003) Acceptance Testing Specifications

1.2 RELATED REQUIREMENTS

Section 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS applies to this section with additions and modifications specified herein.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section 01 33

00 SUBMITTAL PROCEDURES:

SD-06 Test Reports

Acceptance tests and inspections; G

SD-07 Certificates

Qualifications of organization, and lead engineering technician

Acceptance test and inspections procedure; G

1.4 QUALITY ASSURANCE

1.4.1 Qualifications

Contractor shall engage the services of a qualified testing organization to provide inspection, testing, calibration, and adjustment of the electrical distribution system and generation equipment listed in paragraph entitled

"Acceptance Tests and Inspections" herein. Organization shall be independent of the supplier, manufacturer, and installer of the equipment.

The organization shall be a first tier subcontractor. No work required by this section of the specification shall be performed by a second tier subcontractor.

a. Submit name and qualifications of organization. Organization shall have been regularly engaged in the testing of electrical materials, devices, installations, and systems for a minimum of 5 years. The file:///C:\SISGML\JOBS\CUTOUTS\prntdata\word\26%2000%2000.00%2020.doc file:///C:\SISGML\JOBS\CUTOUTS\prntdata\word\01%2033%2000.doc file:///C:\SISGML\JOBS\CUTOUTS\prntdata\word\01%2033%2000.doc file:///C:\SISGML\JOBS\CUTOUTS\prntdata\word\01%2033%2000.doc

SECTION 26 08 00 Page 2 organization shall have a calibration program, and test instruments used shall be calibrated in accordance with NETA ATS.

b. Submit name and qualifications of the lead engineering technician performing the required testing services. Include a list of three comparable jobs performed by the technician with specific names and telephone numbers for reference. Testing, inspection, calibration, and adjustments shall be performed by an engineering technician, certified by NETA or the National Institute for Certification in

Engineering Technologies (NICET) with a minimum of 5 years' experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices.

1.4.2 Acceptance Tests and Inspections Reports

Submit certified copies of inspection reports and test reports. Reports shall include certification of compliance with specified requirements, identify deficiencies, and recommend corrective action when appropriate.

Type and neatly bind test reports to form a part of the final record.

Submit test reports documenting the results of each test not more than 10 days after test is completed.

1.4.3 Acceptance Test and Inspections Procedure

Submit test procedure reports for each item of equipment to be field tested at least 45 days prior to planned testing date. Do not perform testing until after test procedure has been approved.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 ACCEPTANCE TESTS AND INSPECTIONS

Test methods, procedures, and test values shall be performed and evaluated in accordance with the manufacturer's recommendations. Tests identified as optional in NETA ATS are not required unless otherwise specified. Equipment shall be placed in service only after completion of required tests and evaluation of the test results have been completed. Contracting Officer shall be notified at least 14 days in advance of when tests will be conducted.

3.2 SYSTEM ACCEPTANCE

Final acceptance of the system is contingent upon satisfactory completion of acceptance tests and inspections.

3.3 PLACING EQUIPMENT IN SERVICE

A representative of the approved testing organization shall be present when equipment tested by the organization is initially energized and placed in service.

-- End of Section --