REPAIR LIVE FIRE TRAINING FACILITY AIRCRAFT MOCK-UP
Solicitation number
FA665626R0006
Issued by

About this file

This is a Questions and Answers document for federal contract opportunity FA665626R0006, Project ZQEL 26-0010.

The solicitation addresses a FAR Part 15 proposal for fire trainer equipment repair and compliance work. The proposal due date has been extended to September 25, 2026, at 10:00 AM EST, with electronic submission required. This is not a sealed bid procurement. The performance period is 90 calendar days beginning from the effective date of the Notice to Proceed issued by the Contracting Officer, with the dates in Section F representing anticipated administrative dates only. All solicitation attachments, including drawings AS-1 through AS-7, proposal/price schedules, and past performance information, have been posted to SAM.GOV. Key technical clarifications confirm that: the Statement of Work will be amended to remove tail section ignitor work per Technical Order; no work is included for water conservation pond repairs or associated valve and wash down system corrections; the fire trainer must be brought into compliance with the latest NFPA standard; Tetra Tech conducted the August 2025 and March/April 2026 reports; and schedule relief for Government-approved long-lead replacement components will be evaluated on a case-by-case basis. Additional questions remain under review and will be posted upon receipt.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA665626R0006 Questions and Answers Page 1

Question and Answer Project: ZQEL 26-0010

1. Proposal extension request: Due to the number of technical scope clarifications required for accurate subcontractor/vendor pricing, please extend the proposal due date by fourteen (14) calendar days. If possible, please establish the revised proposal deadline at least 14 calendar days after the Government issues responses to these RFIs. Proposal due date extended to 9/25

2. Proposal due date, submission method, and bid opening: The Combined Synopsis/Solicitation states proposals are due electronically on 16 September 2026 at 1000 Eastern Time, while SF 1442 Item 13a states sealed offers are due on 21 September 2026 at 0900 local time and will be publicly opened. Please confirm the controlling proposal due date and time, whether electronic submission is permitted/required, whether hard-copy sealed offers are required, and whether a public bid opening will occur. This is NOT a Sealed bid. Proposals due 9/25 by 1000 EST, electronically.

3. Complete solicitation attachments: Please confirm that the complete solicitation package has been issued. The Combined Synopsis/Solicitation references project drawings AS-1 through AS-7, a proposal/price schedule, past performance information, site-visit instructions, and additional technical documentation/inspection report, while Section J of the solicitation lists only Attachment 01, Statement of Work. Please provide any missing attachments, including the complete inspection/evaluation report and all current drawings/specifications. All attachments posted to

SAM.GOV.

4. Award, Notice to Proceed, and 90-day period: Please confirm that the full 90-calendar-day performance period will run from the actual Notice to Proceed date if award/NTP occurs later than the dates currently shown in Section F. Also confirm whether schedule relief will be considered for Government-approved long-lead replacement components that cannot reasonably be obtained within the stated performance period. Since this is a FAR Part 15 proposal, period of performance

is. 90-calendar-day performance period will begin on the effective date stated in the written Notice to Proceed (NTP) issued by the Contracting Officer. The dates currently shown in Section F are anticipated administrative dates and do not reduce the full 90-calendar-day performance period. If Section F contains fixed dates that conflict with this intent, the Government will clarify the requirement by amendment before award. Schedule relief for long-lead replacement components will be evaluated on a case-by-case basis under the terms of the resulting contract.

5. Who concluded the reports in August 2025 and March/April 2026? Tetra Tech did the report.

6. Is there a full report available it seems like section 3 ends with paragraph 2 and section 4 begins with section 6.1.3 then jumps to 6.4. No, excerpts were taken from the report sent.

7. Will SOW be updated to remove the points base tech crew indicated as repaired or will a confirmed list of solved issues be included? SOW will be amended to remove Tail section ignitor work. No longer required per Technical Order.

8. Is it the intention that the fire trainer be brought to compliance with latest NFPA standard or to follow Air Force standard. NFPA will govern

9. Is it a firm requirement to have the non-standard point resolved, such as return line from water-conservation pond, moving of valves and correction of the wash down system or is it repairs mentioned in section 4 list of works only. No work included for water conservation Pond

10. It was mentioned that the controls for high tail were used for another fire, what fire is that and is it intended to keep both operational after the repair. Work to be omitted for tail section.

FA665626R0006 Questions and Answers Page 2

*Remaining questions under review. Will post once received.