RFI 3 Pavement Markings_Before Award (2).pdf
PDF 568 KB Posted
- Attached to
- Maintain Pavement Markings
- Solicitation number
- FA6606
About this file
This document contains a request for information report related to contract FA6606-22-B-0001 for maintaining pavement markings at a military base. The contractor submitted questions regarding allowable methods for removing existing markings, disposal of wastewater, and details on several bid items. The contracting officer representative provided responses indicating contractors may dispose of wastewater on surrounding grass if local requirements are met, and covered specifications and standard details for the undefined bid items related to entry control points, fuel pits, parking stop bars, equipment boxes, and static ground points. Site visits were held to allow measurements and pictures, and additional escorts are available prior to the March 9 bid opening.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Abstract of Offerc OF 1419 Pg TOTALS PAGE.pdf | ||
| RFI 3 Pavement Markings_Before Award.pdf | ||
| RFI 2 Pavement Markings_Before Award.pdf | ||
| RFI 1 Pavement Markings_Before Award.pdf | ||
| Solicitation - FA660622B0001 Issued.pdf | ||
| Wage Determinations 1.7.22.pdf | ||
| ttb1325d.pdf | ||
| YTPM 22-3001 Pav Mkings SOW FINAL .docx | DOCX document | |
| Bid Schedule Blank for KTR.xlsx | XLSX spreadsheet | |
| 32 17 23 01 Airfield Pavements and Roadways Marking.docx | DOCX document | |
| GROUNDING POINT MARKINGS UFC 3-575-01.docx | DOCX document | |
| 2022 Airfield Marking Overall Plan.pdf | ||
| 32 01 11 52 Airfield Pavements Rubber and Paint Removal.docx | DOCX document | |
| TT-P-1952F (1).pdf | ||
| Engineering Appendix A Airfield Runway Friction Testing.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION REPORT (RFI)
RFI NO. PAGE NO.
CONTRACT NO. CONTRACT TITLE PRIME CONTRACTOR
Contractor's Request for Information
REQUESTED BY: DATE REQUESTED Potential Cost Impact
[No] Potential Schedule
Impact [No]SUBCONTRACTOR
RFI
SUBJECT:
DRAWINGS
INFORMATION REQUESTED:
ATTACHMENTS FROM CONTRACTOR:
Question 6:
Response:
NOTE: THE RFI SYSTEM IS INTENDED TO PROVIDE AN EFFICIENT MECHANISM FOR RESPONDING TO CONTRACTOR'S REQUESTS FOR
INFORMATION. IT DOES NOT PROVIDE AUTHORITY TO PROCEED WITH ADDITIONAL WORK. IF THE CONTRACTOR CONSIDERS
THE RFI RESPONSE A CHANGED CONDITION, PROVIDE WRITTEN NOTICE TO THE CONTRACTING OFFICER'S REPRESENTATIVE
IN ACCORDANCE WITH CONTRACT PROVISIONS.
QA REVIEWER'S SIGNATURE DATE
RFI FORM
FA6606-22-B-0001 YTPM 22-3001
Cornerstone 1 March 2022
Question 7:
Response:
Maintain Pavement Markings
Will the government allow the contractors the use of water to complete the removal of the existing markings or do they need to bring their own water?
During the cleaning and or removal process of existing markings there will be grey water to be disposed of. The units doing this process will separate the solids from the grey water to allow for only grey water to be disposed of with no hazardous materials. Will the government have and allow the subcontractor to dispose of this grey water on site in an existing oil water separator basin or does the contractor need to figure to dispose off site?
Please read specification 32-01 11 52, section 7.2 Based on equipment specifications and the ability to separate particulates out, the contractor may dispose of waste water onto surrounding grass areas provided all local, state and federal requirements have been met.
Please read specification 32-01 11 52, section 3.4.2
Question 8: There is no detail for Bid items:- 008, - 012, - 014, - 015, - 016, - 018. Can the government provide a detail for each bid item?
Response: Covered under UFC 3-260-04 Entry Control Points and signs (Entry Control Points vary in length based on location) Fuel Pits Parking Stop Bars Static Ground Points Fire Extinguisher box is 3.5’*3.5’ Nose Wheel Box 4’*6’ Air Craft Equipment Boxes 60’*20’…..6 inch lines in white As a site visit was held on 22 Feb at 1000, an opportunity to take pictures and measurements was provided. However, we would be happy to escort prospective bidders through the site in order capture required information PRIOR to 9 March bid opening.
| RFI NO: 3 |
| PAGE NO Page 1 of: |
| CONTRACT TITLE YTPM 223001: |
| PRIME CONTRACTOR: |
| Contractors Request for Information: |
| REQUESTED BY PS Construction Inc: |
| DATE REQUESTED 14 Feb 2022: |
| Potential Cost Impact No Potential Schedule: |
| SUBCONTRACTOR: |
| RFI: |
| DRAWINGS: |
| INFORMATION REQUESTEDRow1: |
| ATTACHMENTS FROM CONTRACTOR 1 attachment: |
| QA REVIEWERS SIGNATURE: |
| DATE: |
File details come from the government source that posted it. Updated .