About this file
This document contains Questions and Answers (Q&A) related to a federal contract opportunity for 31 MXS JP-8 Fuel Tanks. The solicitation requires three (3) JP-8 fuel tanks for flightline operations, with the contractor responsible for dismantling the old tanks and assembling the new ones.
The key details include:
- Required fuel tank capacity of 2,000 gallons/7,570 liters
- Tanks must be located at different places around the base, with each having its own console
- Level indication is required, but no external command or automatic start/stop features
- Tanks will be refueled from the top, with no requirement for a front load or loading pump
- No specific filter requirements are stated
- The solicitation is being issued by the Department of the Air Force United States Air Forces in Europe - Air Forces Africa.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ASHE 20-1089_Drawings_Final.pdf | ||
| 20240603_132850.jpg | JPG image | |
| 20240603_132459.jpg | JPG image | |
| 20240603_132437.jpg | JPG image | |
| 20240603_132834.jpg | JPG image | |
| Large JP8 Tank.png | PNG image | |
| 20240603_132507.jpg | JPG image | |
| 300-gallon-eco.png | PNG image | |
| 20240603_132452.jpg | JPG image | |
| 20240603_132530.jpg | JPG image | |
| FA568224Q8047 COMBINED SYNOPSIS.pdf | ||
| Attachment 4 - Statement of Work - Amended.pdf | ||
| Questions and Answers.pdf | ||
| Questions and Answers.docx | DOCX document | |
| Attachment 1 - Provisions and Clauses.pdf | ||
| Attachment 2 - 52.212-1 Instructions to Offerors.pdf | ||
| FA568224Q8047 COMBINED SYNOPSIS.pdf | ||
| Attachment 3 - Salient Characteristics.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers (Q&A)
Q1: What is the fuel tank capacity?
A: Storage capacity needed is 2,000 gallons/7570 liters.
Q2: As it is known, ATG and SGB consoles/screens/devices can be connected to more than one tank and we can control the status of tanks with a single console/screen. For this, the tanks must be next to each other or close to each other. And if to proceed with a single console, this will reduce the total project amount. Hence request for information about the positions of the tanks at the site.
A2: The tanks must be located at different places around base, geographically separated enough to where each must have their own console.
Q3: Accordingly, do you have the P&ID where we can see this layout plan better? Or do you have a working principle / scenario planned?
A3: As each tank is individual they are not underground and should be a direct replacement for the ones in place. They are currently placed above ground, no P&ID on hand as these were bought 20 years ago.
Q4: Level indicator is written in the specification only for level information. Is it enough to just see the levels here? Will no external command be given? Where will the pumps get fuel from (for 3x7500L tanks)? Is there a main storage tank? Will these pumps and (motorized valves, if any), operate in together automation with the ATG? So will there be an automatic start & stop feature? According to the levels of the 3x7500 L fuel tanks, will it automatically take the fuel from the main tank at L level and finish filling it automatically at H level? Are alarms required at these levels?
A4: These tanks are filled from the large POL trucks that have a pump. When these tanks disperse fuel it will be done from the pump on top of the tank. Level only is fine. I do not believe there is a current automatic stop since they monitor the level indicator on the side of the tanks.
Q5: Which kind of management system do you need?
A5: I assume by management system they mean fuel level sensing. We would prefer the simplest fuel sensor. A simple fuel gauge is preferred it does not need to be electronic.
Q6: Concerning the filers, do you have any requirements?
A6: We do not have any filter requirements.
Q7: Do you need a frontal load, and a loading pump?
A7: We do not need a front load or loading pump. The tank can be refueled from the top.