Questions_&_Answers_FA568219RA020.pdf
PDF 45 KB Posted
- Solicitation number
- FA568219RA020
About this file
Questions & Answers FA568219RA020
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation_Amendment_FA568219RA0200002_SF_30.pdf | ||
| ASHE_19-1039_Add_1.pdf | ||
| Solicitation_Amendment_FA568219RA0200001_SF_30.pdf | ||
| ASHE_19-1039_SOW_(Rev.1.0).pdf | ||
| ASHE_19-1039_CCEB.xlsx | XLSX spreadsheet | |
| ATCH_2.1_OM_Database_Rev.00_(Template).pdf | ||
| ATCH_1_ASHE_19-1039_Schedule_of_Material_Submittals_(Rev.2.0).doc | DOC document | |
| ATCH_2.2_OM_Database_Rev.00.xlsm | XLSM spreadsheet | |
| Solicitation_-_FA568219RA020.pdf | ||
| ASHE_19-1039_Tech_Specs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION FA568219RA020 UPGRADE COMM NETWORK TO CORE DISTRIBUTION NODES, AREA F, AVIANO AB, ITALY
QUESTIONS & ANSWERS
1Q) In the SOW dated 25 July 2019 at the item 5.1.1 Geo‐textile (or Innerduct) Installation it is indicated to install a 2x3 (total 6) Geo‐Textile Innecduct Sleeve in existing 4‐Inch conduit, in all cable route sketches is indicated to install new 3, 3‐cell (Total of nine) Geo‐Textile innerduct sleeve in an existing 4‐inch conduit. Please, clarify if shall be provided 2x3 (Total
6) or 3x3 (total 9) innerduct sleeves.
1A) 3x3” (total 9) innerduct sleeves shall be supplied and installed. Please see the Addendum #1 to correct the typo mistake at par 5.1.1.
2Q) In the SOW at the items 4.2.2; 4.2.2; 4.2.3; 5.2.1 and 5.2.2 have been attached the tables with the approximate lengths of the FOC to be provided. Please, clarify if the lengths exposed include the maintenance loops required at the item 3.5.11 and the lengths to arrive from the MHs outside the buildings to the Comm Racks or if the maintenance loop lengths and incoming cables lengths from the outside MHs to the Comm Racks shall be added.
2A) Tables at items 4.2.2, 4.2.2, 4.2.3, 5.2.1 and 5.2.2 provide the approximate distance of the duct bank between two consecutive HH/MH, that is smaller than the length of the cable to be run through each specific path.
In fact, as per paragraph 3.5.11, contractor shall take into account also the lengths of the entry point in each CDN, as well as the maintenance loops (i.e. a minimum of a 50 feet fiber optic cable maintenance loop at the first MH from the building, at every splice point MH location, at every 3rd MH in the route, before or after the 90 degree MHs/HHs), etc...
Please note that, as per paragraph 4, “it is the responsibility of the contractor to calculate, foresee and perform all quantities and work necessary even if it not mentioned in the specifications but included in the drawings or manifestly necessary to deliver a complete project based on its overall scope.”