ADDENDUM#1 TO SCOPE OF WORK FOR ASHE 19-1039 UPGRADE COMM NETWORK
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions_&_Answers_FA568219RA020.pdf | ||
| Solicitation_Amendment_FA568219RA0200002_SF_30.pdf | ||
| Solicitation_Amendment_FA568219RA0200001_SF_30.pdf | ||
| ASHE_19-1039_SOW_(Rev.1.0).pdf | ||
| ASHE_19-1039_CCEB.xlsx | XLSX spreadsheet | |
| ATCH_2.1_OM_Database_Rev.00_(Template).pdf | ||
| ATCH_1_ASHE_19-1039_Schedule_of_Material_Submittals_(Rev.2.0).doc | DOC document | |
| ATCH_2.2_OM_Database_Rev.00.xlsm | XLSM spreadsheet | |
| Solicitation_-_FA568219RA020.pdf | ||
| ASHE_19-1039_Tech_Specs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #1
PROJECT ASHE 19-1039
UPGRADE COMM NETWORK TO CORE DISTRIBUTION NODES,
AREA F, AVIANO AB, ITALY
Change Item 5.1.1, Geo-Texile fabric (or Innerduct) Installation, to read in the description:
5.1.1 Geo-textile Fabric (or Innerduct) Installation
The Contractor must supply and install a 3x3 (total of 9) Geo-Textile Innerduct Sleeve in an existing 4-Inch conduit MaxCell needs to be 3-Cell with Color Coded Pull Tape IAW the following table (Route marked green, all the distances provided at the table are approximate and are in feet):
From To Approx. Dist. [ft] Approx. Dist. [m] Sketch (s) #
CSM70B MH 8AA 370 113 2
MH 8AA CSM8A 380 116 2 & 3
CSM8A MH 8B 433 132 3
MH 8B MH 8C 260 79 3
MH 8C MH 8D 355 108 3
MH 8D MH 8E 172 52 3 & 4
MH 8E MH 8F 170 52 4
MH 8F MH 8G 300 91 4
MH 8G CSM1 170 52 4
CSM1 CSM2 60 18 4
CSM2 CSM3 375 114 4
CSM3 CSM4 380 116 4 & 5
CSM4 CSM5 350 107 5
CSM5 CSM6 360 110 5
CPM16B CSM17 218 66 8
CSM17 CPM18 400 122 8
CPM18 CSM19 390 119 8
CSM20 CSM21 300 91 9
CSM21 CPM22 315 96 9
CPM22 CSM23 295 90 9
CSM23 CPM24 285 87 9
CPM24 CSM25 270 82 9 & 10
CSM28 CSM29 325 99 10
CSM29 CPM30 302 92 10 & 11
CN-11341 CSM93 25 8 13
CSM93 CSM38A 205 62 13
CSM38A CSM37 290 88 13
CSM38A CPM39 495 151 14
CPM39 CSM40A 348 106 14
CSM40A CSM40 285 87 14
CSM40 CPM41 400 122 14 & 15
CPM41 CSM42 335 102 15
CSM42 CPM43 350 107 15
CPM43 CSM44 356 109 15 $ 16
CSM44 CSM45 385 117 16 & 17
CSM97H CN-1226 30 9 17 (Note-2)
CSM45 CSM46 447 136 18 & 19
CSM46 CSM47 440 134 19 & 20
CSM47 CSM48 405 123 20
CSM48 CSM49 285 87 20
CSM49 CSM50 285 87 20
CSM50 CSM51 395 120 20
CSM51 CSM52 405 123 20
CSM52 CSM53 410 125 20 & 21
CSM53 CSM54 455 139 21
CSM54 CSM55 300 91 21
CSM55 CSM56 245 75 21
CSM56 CSM57 400 122 21
CSM57 CSM58 450 137 21 & 22
CSM58 CSM59 395 120 22
CSM59 CPM60 435 133 22
CPM60 CSM61 320 98 22
CSM61 CSM61B 240 73 22
CSM61B EMHB 175 53 22
EMHB MHTRA 50 15 22
MHTRA MHTR 40 12 22
MHTR EMHA 260 79 22
EMHA CN-1442 60 18 22
CN-1442 EHMC 25 8 23
EHMC MH1 415 126 23 (Note-3)
MH1 MH2 350 107 23 & 24
MH2 MH2A 335 102 24
MH3 MHT4 320 98 24 & 25
MHT4 MH5 210 64 25 (Note-3)
MHT3 CN-1496 75 23 25
Tot 19366 ft 5902 m
NOTEs:
• One of the three geo-textile fabrics listed in the above table shall contain a metallic trace member, Contractor must ensure that the fabric which has a metallic trace wire is extended long enough (2 feet at least) so that the trace wire can be seen and used in the future.
• Contractor must install geo-textile fabrics into the existing conduit that has one small cable.
• Contractor must install the new geo textile innerduct inside one of the new 4-Inch conduit installed under this project.
LUMP SUM
| 5.1.1 Geo-textile Fabric (or Innerduct) Installation |
| The Contractor must supply and install a 3x3 (total of 9) Geo-Textile Innerduct Sleeve in an existing 4-Inch conduit |
| MaxCell needs to be 3-Cell with Color Coded Pull Tape IAW the following table (Route marked green, all the distances provided at the table are approximate and are in feet): |
| LUMP SUM |