SCHEDULE OF MATERIAL SUBMITTALS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ADDITIONAL_REQUIREMENTS_25_May_2017.pdf | ||
| ASHE_16_1030_SOW_Addendum_1.pdf | ||
| ASHE_16_1030_CNS_Cost_Estimate_Breakdown_blank.xlsx | XLSX spreadsheet | |
| FA5682-17-R-0036-0001.pdf | ||
| ASHE_16_1030_CNS_Cost_Estimate_Breakdown_Blank.pdf | ||
| UFGS_BACnet_2015.docx | DOCX document | |
| FA5682-17-R-0036.pdf | ||
| ASHE_16_1030_Technical_Specifications_Rev3.pdf | ||
| 1478_MBF_&_P.O._honeywell.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT TITLE | SOLICITATION / CONTRACT NO. | ||||||||||||||
| ASHE 16-1030 | REPAIR HVAC SYSTEM MULTI | ||||||||||||||||
| (To be completed by Project Architect or Engineer) | |||||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | DESIGN | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | REQUIRED SUBMISSION DATE |
fergusog: Enter the due date from the Contractor (MM/DD/YY)
DATE RECEIVED IN CONTRACTING
fergusog: Enter the date received from the Contractor. (MM/DD/YY)
DATE TO CIVIL ENGINEERING
fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)
RETURN SUSPENSE DATE
fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
SUBMITTAL NUMBERS
fergusog: Enter the Submittal Number
DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL
fergusog: Enter Resubmittal Number
FINAL APPROVAL
fergusog: Enter the submittal final approval date
(MM/DD/YY)
REMARKS
fergusog: Enter any comments pertaining to the submittal
APPROVED
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number
DISAPPROVED
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date
(MM/DD/YY)
fergusog: Enter any comments pertaining to the submittal
| IT.3.1 bldg 14671 | ||||||||
| 1 | 3.1.d BOILER & BURNER | 2 | 2 | 2 | 30 | |||
| 2 | 3.1.e HOT WATER STORAGE TANK | 3 | 30 | |||||
| 3 | 3.1.f VALVES PN50 | 3 | 30 | |||||
| 4 | 3.1.g NEW MAIN ELECTR. PANEL | 3 | 3 | 3 | 3 | 30 | ||
| 5 | 3.1.g NEW ATU | 3 | 3 | 30 | ||||
| IT.3.2 bldg 1478 | ||||||||
| 6 | 3.2.a HVAC DDC | 3 | 3 | 3 | 3 | 30 | ||
| 7 | 3.2.b SURGE PROTECT. DEV. (SPD) | 3 | 3 | 3 | 30 | |||
| IT.3.3 bldg 1204 | ||||||||
| 6 | 3.3b NEW CILLER | 3 | 3 | 3 | 3 | 30 | ||
| 7 | 3.3d PIPE AND VALVES | 3 | 3 | 30 | ||||
| 8 | 3.3f NEW WATER SOFTENER | 3 | 3 | 3 | 3 | 30 |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| 7 |
| 8 |
| 9 |
Schedule of Material Submittals Template, Feb 05 (SAF/AQCP)