CONSTRUCTION COST ESTIMATE BREAKDOWN
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ADDITIONAL_REQUIREMENTS_25_May_2017.pdf | ||
| ASHE_16_1030_SOW_Addendum_1.pdf | ||
| ASHE_16_1030_CNS_Cost_Estimate_Breakdown_blank.xlsx | XLSX spreadsheet | |
| FA5682-17-R-0036-0001.pdf | ||
| ASHE16_1030_MATERIAL_SUBMITTAL_SCHEDULE__Rev.1.xlsx | XLSX spreadsheet | |
| UFGS_BACnet_2015.docx | DOCX document | |
| FA5682-17-R-0036.pdf | ||
| ASHE_16_1030_Technical_Specifications_Rev3.pdf | ||
| 1478_MBF_&_P.O._honeywell.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOR OFFICIAL USE ONLY Sheet 1 of 1
CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTOR ADDRESS
CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE
REPAIR HVAC SYSTEM MULTI
PURCHASE REQUEST NUMBER PROJECT NUMBER ASHE 16-1030 WORK LOCATION Area F, Aviano AB.
LINE
NO. ITEM UNIT OF
MEASURE QUANTITY UNIT TOTAL OTHER DIRECT
COSTS LINE TOTAL
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
1 BOILER ROOM, REMOVALS IT. No.
Art. n. 3.1a L.S. 1
2 TEMPORARY BOILER IT. No.
Art. n. 3.1b L.S. 1
3 BOILER ROOM EXPANSION IT. No.
Art. n. 3.1c L.S. 1
4 NEW BOILERS AND BURNERS (2ea) IT. No.
Art. n. 3.1d L.S. 1
5 NEW HOT WATER STORAGE TANKS (2ea) IT. No.
Art. n. 3.1e L.S. 1
6 PIPELINE & VALVES IT. No.
Art. n. 3.1f L.S. 1
7 NEW MAIN ELECTRICAL DISTRIBUTION PANEL IT. No.
Art. n. 3.1g L.S. 1
8 NEW AIR TREATMENT UNIT IT. No.
Art. n. 3.1h L.S. 1
9 NEW DDC SYSTEM IT. No.
Art. n. 3.2a L.S. 1
10 SURGE PROTECTION DEVICES (SPD) IT. No.
Art. n. 3.2b L.S. 1
11 REMOVAL AND CIVIL WORKS IT. No.
Art. n. 3.3.a L.S 1
12 NEW CHILLER IT. No.
Art. n. 3.3.b L.S 1
13 MODIFICATION OF AHU1 IT. No.
Art. n. 3.3c L.S 1
14 NEW PIPING SYSTEM IT. No.
Art. n. 3.3d L.S 1
15 REPLACEMENT OF SPLIT UNIT IN COMM RM IT. No.
Art. n. 3.3e L.S 1
16 REPLACEMENT OF WATER SOFTNER IT. No.
Art. n. 3.3f L.S 1
TOTAL COST
2017 $/Euro Currency Rate = 0.899
3.1 Bldg 14671 Mensa kitchen Boiler
MATERIAL PLUS LABOR COST
3.2 Bldg 1478 UPGRADE DDC IN BASE THEATER & POST OFFICE
3.3 Bldg 1204 HEAVY DROP FACILITY
ASHE 16-1030