ASHE_16_1030_CNS_Cost_Estimate_Breakdown_blank.xlsx
XLSX spreadsheet 14 KB Posted
- Solicitation number
- FA5682-17-R-0036
About this file
CONSTRUCTION COST ESTIMATE BREAKDOWN
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ADDITIONAL_REQUIREMENTS_25_May_2017.pdf | ||
| ASHE_16_1030_SOW_Addendum_1.pdf | ||
| FA5682-17-R-0036-0001.pdf | ||
| ASHE16_1030_MATERIAL_SUBMITTAL_SCHEDULE__Rev.1.xlsx | XLSX spreadsheet | |
| ASHE_16_1030_CNS_Cost_Estimate_Breakdown_Blank.pdf | ||
| UFGS_BACnet_2015.docx | DOCX document | |
| FA5682-17-R-0036.pdf | ||
| ASHE_16_1030_Technical_Specifications_Rev3.pdf | ||
| 1478_MBF_&_P.O._honeywell.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Estimativo
| CONTRACTOR COST ESTIMATE BREAKDOWN | ||||||||||||
| CONTRACTOR | ADDRESS | |||||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||||
| REPAIR HVAC SYSTEM MULTI | ||||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER ASHE 16-1030 | WORK LOCATION Area F, Aviano AB. | ||||||||||
| MATERIAL PLUS LABOR COST | ||||||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | OTHER DIRECT COSTS | LINE TOTAL | |||||
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |||
| 3.1 Bldg 14671 mensa kitchen | ||||||||||||
| 1 | BOILER ROOM, REMOVALS | IT. No. Art. n. | 3.1a | L.S. | 1 | |||||||
| 2 | TEMPORARY BOILER | IT. No. Art. n. | 3.1b | L.S. | 1 | |||||||
| 3 | BOILER ROOM EXPANSION | IT. No. Art. n. | 3.1c | L.S. | 1 | |||||||
| 4 | NEW BOILERS AND BURNERS (2ea) | IT. No. Art. n. | 3.1d | L.S. | 1 | |||||||
| 5 | NEW HOT WATER STORAGE TANKS (2ea) | IT. No. Art. n. | 3.1e | L.S. | 1 | |||||||
| 6 | PIPELINE & VALVES | IT. No. Art. n. | 3.1f | L.S. | 1 | |||||||
| 7 | NEW AIR TREATMENT UNIT | IT. No. Art. n. | 3.1g | L.S. | 1 |
| 3.2 Bldg 1478 UPGRADE DDC IN BASE THEATER & POST OFFICE | |||||
| 8 | NEW DDC SYSTEM | IT. No. Art. n. | 3.2a | L.S. | 1 |
| 3.3 Bldg 1204 HEAVY DROP FACILITY | |||||
| 9 | REMOVAL AND CIVIL WORKS | IT. No. Art. n. | 3.3.a | L.S | 1 |
| 10 | NEW CHILLER | IT. No. Art. n. | 3.3.b | L.S | 1 |
| 11 | MODIFICATION OF AHU1 | IT. No. Art. n. | 3.3c | L.S | 1 |
| 12 | NEW PIPING SYSTEM | IT. No. Art. n. | 3.3d | L.S | 1 |
| 13 | REPLACEMENT OF SPLIT UNIT IN COMM RM | IT. No. Art. n. | 3.3e | L.S | 1 |
| 14 | REPLACEMENT OF WATER SOFTNER | IT. No. Art. n. | 3.3f | L.S | 1 |
TOTAL COST